(1) The achievements since the July meeting of the Transport Delivery Committee were noted. (2) The progress of deliverables and outturn of the 2022/23 capital programme was noted. (3) Where indicated, the variations from the baseline programme were noted. (4) The approach on future reporting arrangements to the Transport Delivery Committee were endorsed.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
2.1The 2022/23 Capital Programme allocation was approved by WMCA Board as part of the draft capital and revenue budget in February 2022.
2.2As with recent years, the ITB allocation for 2022/2023 has been fully utilised on continuing committed schemes and managing the existing asset base with respect to replacement and or renewal of life expired/obsolete equipment. Through this approach, a steady state of asset condition across the estate can be maintained.
2.3Attached to this report (Appendix 1) is the detailed monitoring report for the TfWM Capital programme outlining deliverables, indicating the baseline date with an indication of the current forecast date with a RAG indicator.
2.4As the Committee will be aware, the reporting provided through this report has historically only focussed on schemes that had elements of funding allocated via the Integrated Transport Block (ITB). As part of the City Region Sustainable Transport Settlement (CRSTS) for the West Midlands (2022 to 2027), ITB has been incorporated into this overall funding allocation. Going forwards, it is proposed that we broaden the capital reporting for Transport Delivery Committee to reflect the wider CRSTS programme as well other capital funded schemes. Officers will work with TDC Members on developing an appropriate reporting format over the coming months.
3.0Achievements
3.1The following elements within the 2022/23 Capital Programme have been completed between July and September:
Dudley Interchange - The tender process for appointing the design consultant to progress the detailed design in readiness for a build only contractor has formally closed with submissions being evaluated. The full planning application has now been submitted and was granted permission at DMBC Planning committee.
Making the KRN Safer - Contract has been awarded to support Local Authority applications to secure the required Designation Order and the project will commence in September for a period of 12 months.
Perry Barr Rail Station and Bus Interchange – Both the station and bus interchange operated as planned during the Commonwealth Games. No issues were reported and positive feedback was received from operators and passengers. Subway infill works were completed ahead of programme. Footbridge parapet painting is also complete. Digital Panel Rollout – Positive progress continues with a list of 22 shelters that have planning approved for digital advertising provided by Clear Channel
4.0Variations to Baseline Programme
4.1The following variation to the baseline programme should be noted:
University Station – revision to opening date following a review of the programme due to a number industry wide challenges.
Financial implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Transport Delivery Committee at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.