(1) The achievements since the October meeting of the Transport Delivery Committee were noted. (2) The progress of deliverables and outturn of the 2022/23 Capital Programme were noted. (3) The variations from the baseline programme were noted.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
2.1The 2022/23 Capital Programme allocation was approved by WMCA Board as part of the draft capital and revenue budget in February 2022.
2.2As with recent years, the ITB allocation for 2022/2023 has been fully utilised on continuing committed schemes and managing the existing asset base with respect to replacement and or renewal of life expired/obsolete equipment. Through this approach, a steady state of asset condition across the estate can be maintained.
2.3Attached to this report (Appendix 1) is the detailed monitoring report for the TfWM Capital programme outlining deliverables, indicating the baseline date with an indication of the current forecast date with a RAG indicator.
2.4As the Committee will be aware, the reporting provided through this report has historically only focussed on schemes that had elements of funding allocated via the Integrated Transport Block (ITB). Further work is being undertaken by TfWM on broadening the capital reporting for Transport Delivery Committee to reflect the wider CRSTS programme as well other capital funded schemes. This work will inform a proposed reporting framework which will be shared with TDC Members. An update on this will be provided at the January committee meeting.
3.0Achievements
3.1The following elements within the 2022/23 Capital Programme have been completed between September and November:
Dudley Interchange – a) A Design Consultant has successfully been appointed following the procurement process to progress the detailed design (RIBA Stage 4) b) The full planning application has been approved at the DMBC Planning committee held on 12th September
Making the KRN Safer- Confirmed Road casualty data has now been released for 2021 and shows a 16% reduction in killed and seriously injured casualties in the West Midlands Metropolitan Region in the second reporting period (2019-2021), up from 13.2% in the first reporting period (2018-2020).
TfWM Asset Renewal Programme – Packages of work that have been carried over from the last financial year are progressing well after delays in digital advertising requirements from Clear Channel. Orders for these shelters are now being placed and all LED light heads have now been received following further supply chain delays.
Page 2 of 7 4.0 Variations to Baseline Programme
4.1There are no variations to the baseline programme to note.
Financial implications
5.1The detailed financial aspects of the TfWM 2022/2023 Capital Programme are reported separately under the Financial Monitoring Report to this Committee. A summary of the position in financial terms is, however, attached to this report as Appendix 2
Legal implications
6.1There are no direct legal implications arising from the recommendations set out in this report. However, legal and procurement will support, as necessary, any deliverables that may arise throughout 2022/2023.
Equalities implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Transport Delivery Committee at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.