Audit, Risk & Assurance Committee, Wednesday 19 July 2023 at 10.00am

Transport Programme Capital Governance Review (TfWM)

Noted Finance 1 paper

Audit, Risk & Assurance Committee noted this item on Wednesday 19 July 2023. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

Resolved that :the WMCA’s response to the findings of the independent review following the breach of financial regulations within the Wolverhampton Interchange programme be noted.
Word for word from the decision West Midlands Combined Authority published for this meeting. Source: governance.wmca.org.uk

Follow this further

Built from West Midlands Combined Authority's papers

What the report saysPro

Report to Audit, Risk & Assurance Committee

Background

3.1Mazars LLP were appointed to complete an investigation with their findings being presented to the Chair of ARAC, section 151 officer and the monitoring officer in April ’23. No evidence of any wrongdoing was found, the recommendations related to ways in which governance might be improved to reduce the risks of further overspends. 3.2 Following a review of the findings and recommendations made, officers consider that it would be sensible to review these alongside a number of other reviews carried out by TfWM and a recognition that in recent years a number of projects have exceeded the approved budget due to scope changes and/or construction challenges which have emerged on site. It has been recognised these are not uncommon in transport projects however following a sharp rise in costs due to national and global events, this has, and continues to be, a major impact on budgets and the capacity to deliver programmes which is constrained by the quality of programme management and monitoring arrangements in place.

3.3It has therefore been agreed that a high level internal review of the Governance and Monitoring arrangements should be undertaken, to facilitate due diligence and effective programme management control measures are in place for the TfWM capital programme. TfWM is currently going through a process called TfWM Reimagined, which is making significant changes to the directorate, and which it is expected will address many of the issues raised in the various reviews. It is intended that this internal review will pull together all of the issues raised, and work with officers in the directorate to ensure that they are all being addressed, and if not, make further recommendations as to how they could be addressed.

3.4Internal Audit will complete the review to ensure independence of operational services and will assess the Governance and Monitoring arrangements in place, and those proposed to be introduced. The scope of the review has been determined to: Assess the programme management, risk practices and financial control measures in place for major projects of all modes and to provide recommendations for improvements to be made where applicable. Consideration should be given to the governance processes, risk management and monitoring arrangements relating to all key stages of programme management applied, and project lifecycle

3.5.1 It is estimated that given the size of the department, and the extent of work involved in carrying out a thorough review, that the review will take a minimum of 3 months to complete, and members will be provided with a summary of the findings at a subsequent meeting.

Financial implications

None

None

Equalities implications

None

7. Inclusive Growth Implications Not applicable.

8. Geographical Area of Report’s Implications Not applicable.

9. Other Implications Not applicable.

10. Schedule of Background Papers

n/a

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Transport Programme Capital Governance Review (TfWM)Report 227 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 12 attended
MS
Mark SmithChair, present
KA
Councillor Karen AshleyCommittee Member, present
NB
Councillor Nick BardsleyCommittee Member, present
RB
Councillor Richard Baxter-PayneCommittee Member, present
DB
Councillor Dave BorleyCommittee Member, present
JJ
Councillor Jaspreet JaspalCommittee Member, present
BJ
Councillor Brigid JonesCommittee Member, present
LK
Councillor Leslie KayeCommittee Member, present
RL
Councillor Ram Lakha OBECommittee Member, present
RM
Councillor Rose MartinCommittee Member, present
LP
Councillor Liam PreeceCommittee Member, apologies
LR
Lisa RitchieCommittee Member, present

On this subject at West Midlands Combined Authority

Search all
  1. Transport Programme Capital Governance Review (TfWM)This decision
  2. Transport Capital Investment ProgrammeApproved
  3. Transport Capital Delivery ProgrammesAgreed
  4. Transport for West Midlands Capital Spending Pressures and Programme UpdateApproved
  5. West Midlands Transport Investment Programme & City Region Sustainable Transport Settlement ReviewNoted
  6. City Region Sustainable Transport Settlement ProgrammeApproved

More from West Midlands Combined Authority Audit, Risk & Assurance Committee

All decisions
MeetingDecisionOutcome
14 Jul 2026 Terms of Reference - To NoteResolved that: The Terms of Reference be noted. Noted Open
14 Jul 2026 West Midlands Combined Authority (WMCA) Financial Monitoring Outturn 2025/26Resolved that: The update be noted. Noted Open
14 Jul 2026 Annual Review Letter 2025/26Resolved that: The Local Government and Social Care Ombudsman’s annual review letter for 2025/26 be noted. Noted Open
14 Jul 2026 Business Continuity Programme Update(1) That a reduction in overall programme risk and that Business Continuity Resilience, Response and Recovery (BCRRR)... Noted Open
14 Jul 2026 Consideration of Private Internal Audit Reports(1) The contents of the latest Internal Audit Update Report and progress against delivery of the 2025/26 Internal Aud... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies