Resolved

That subject to business case approval by the Department of Energy, Security and Net Zero (DESNZ) agreement to receive a minimum of £6.2m revenue grant funding from DESNZ to deliver the Local Net Zero Accelerator Programme be approved and 2. The WMCA be authorised to enter into contracts and onward award funding to deliver the be agreed and 3. Authority be given to delegate responsibility for receiving and allocating additional funding for the Local Net Zero Accelerator Programme up to £20m to the Executive Director of Strategy, Economy and Net Zero in consultation with the S.151 Officer be agreed.
Word for word from the decision West Midlands Combined Authority published for this meeting. Source: governance.wmca.org.uk

Follow this further

Built from West Midlands Combined Authority's papers

What the report saysPro

Report to Investment Board

Executive summary

This Programme Business Case (PBC) has been submitted by Alex Gordon/Ayushi Vyas from Strategy, Integration & Net Zero.

This PBC is for the Local Net Zero Accelerator Programme and Fund. This work was formally known as Project CAMPOS (Creating a Market for Place-based Outcomes), a £4.86m funding application made to Innovate UK, which has now been extended and awarded funding directly from the Department for Energy Security and Net Zero (DESNZ) to establish a West Midlands Net Zero Fund and secure an investment partner, as part of regional Trailblazer status. Total funding available for this project from DESNZ is approximately £6.2m of revenue to be spent by March 2026. The core aim of this programme is to develop a scalable, replicable and financeable model for accelerating progress to a Net Zero energy transition. To note, the funding conditions are still being negotiated with the funder.

This project will seek to establish how funding, including devolved funding from Government, can be blended with private and outcomes-seeking finance to achieve Government’s objectives, removing market barriers to place-based Net Zero investment and attracting private investment to ensure that the impact of devolved public funding is maximised.

This project will address the following objectives:

1. Data: Developing a robust data infrastructure solution with metrics and key indicators to measure outcomes, connecting neighbourhood data to project teams and the outcomes market.

2. Governance: Establishing a robust governance structure to manage a regional blended finance fund for Net Zero projects, balancing investor, place and community interests to ensure a just transition.

3. Participation: Building community trust in Net Zero projects and demonstrating resulting quality of life improvements to increase interest and demand.

To accelerate delivery, maximise learning and realise the benefits, the project will work with five Net Zero Neighbourhoods (NZN) demonstration projects across the region, maximising the value and impact of the existing regional NZN programme. The following Local Authorities will be part of this programme Birmingham, Wolverhampton, Solihull, Sandwell and Walsall.

Finance Summary:

Investment Board are required to make a decision on this business case to spend £6,200,000 from DESNZ to accelerate the regions Net-Zero energy transition.

1|P a g e Risk & Investment Appraisal Single Assurance Framework

The PBC has been reviewed by, or had input from, the following stakeholders: • Tahyba Nud, Programme Appraisal • Marzena Kubiak, Programme Assurance • Aqeel Rizvi, Finance Business Partner • Nigel Channer, Legal Representative • Emily Sutton, Procurement ____________________________

2|P a g e Risk & Investment Appraisal Single Assurance Framework

2.0APPRAISAL RECOMMENDATION

Based on an independent assessment of the risks and opportunities presented in this report: The Local Net Zero Accelerator Programme and Fund, the appraisal recommendation is to approve based on the following proposed conditions:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
COMPLETED APPRAISAL: NetZero: WMCA-SAF-GD008 Risk and Investment Appraisal_ReportReport 252 KB DownloadRead as text
PDF
Local Net Zero Accelerator ProgrammeReport 221 KB Download
PDF
WMCA-SAF-TP018_PBC: LNZA -Report 1 MB Download

At this meeting

Whole meeting

Who was there

7 of 12 attended
BS
Councillor Bob SleighChair, present
MB
Councillor Mike BirdCommittee Member, apologies due to council business
SC
Councillor Steve ClarkCommittee Member, present
MD
Councillor Matthew DormerCommittee Member, present
PH
Councillor Peter HughesCommittee Member, present
KG
Councillor Karen GrinsellCommittee Member, present
JO
Councillor Jim O'BoyleCommittee Member, apologies
SS
Councillor Stephen SimkinsCommittee Member, apologies, sent representative
ST
Councillor Sharon ThompsonCommittee Member, apologies
PB
Paul BrownCommittee Member, in attendance, virtual
SS
Sue SummersCommittee Member, present
GT
Gary TaylorCommittee Member, apologies

On this subject at West Midlands Combined Authority

Search all
  1. Local Net Zero Accelerator ProgrammeThis decision
  2. Local Net Zero Accelerator Progress UpdateNoted
  3. Local Net Zero AcceleratorDecided

More from West Midlands Combined Authority Investment Board

All decisions
MeetingDecisionOutcome
17 Aug 2026 Minutes - 20 July 2026The minutes of the meeting held on 20 July 2026 were approved as a correct record. Approved Open
17 Aug 2026 Rosewell Review Phase 2/ Transport for City Regions UpdateResolved that: 1. The principles developed to help guide the allocation of the remaining £405m of funding to the Port... Noted Open
17 Aug 2026 Investment Programme UpdateResolved that: 1. Since the previous sitting of the WMCA Investment Board there have been no change requests approved... Approved Open
17 Aug 2026 Investment Programme Dashboard- Red Rated Projects UpdateResolved that: 1. The current position of the eight red-rated projects within the Investment Programme Dashboard, inc... Noted Open
17 Aug 2026 Commercial Investment Fund DashboardResolved that: The report be noted. Noted Open