WMCA Board, Friday 19 July 2024 at 11.00am

Wednesbury to Brierley Hill Metro Extension – Phase 2

Approved Committee 1 paper

WMCA Board approved this item on Friday 19 July 2024. Below is the council's own wording, with the papers it was decided on.

Item18

Resolved

(1) The Single Assurance Framework change request to increase the overall budget by £248.5m, including a new funding allocation of £36m City Region Sustainable Transport Settlement overprogramming to allow completion of the phase 2 of the extension to Merry Hill, amending the funding envelope, scope and timescale was approved, noting that the overall funding package was subject to the Department for Transport approving the business case. (2) The conditional release of the full funding to complete phase 2 to Merry Hill was approved, subject to the development of a robust and credible plan within the locally-led place based strategy that could secure a contribution to the scheme which would off-set the level of City Region Sustainable Transport Settlement financial over-programming currently required in order to build Phase 2, and would drive up the levels of patronage on the overall Wednesbury - Brierley Hill extension line such that operational subsidy requirements were reduced, eg. through a regeneration and land use planning framework. This would require further WMCA Board approval prior to the release of the full funding. (3) The advanced expenditure of up to £6m for phase 2 utilities and advanced works ahead of any Government approval of the phase 2 business case was approved, to be released incrementally to minimise exposure. As set out in the financial implications section of the report, this would be funded from the element of the residual scheme funding that was supported through WMCA capital financing and was within total budget envelope for the Wednesbury - Brierley Hill extension already approved by WMCA Board on 9 June 2023. (4) The Executive Director for Transport and Section 73 Officer (typically referred to as s151 Officer) was authorised to finalise and formally submit the full business case to Government for consideration in order to unlock the required additional funding from the Department for Transport and the Ministry of Housing, Communities & Local Government. (5) It was noted that phase 1 of the Wednesbury - Brierly Hill metro extension was currently under construction to Dudley town centre (due for completion in 2025) and that costs for this element would increase by up to £15m should the phase 2 element of the scheme not be approved, plus any spend incurred relation to the advanced utilities works. (6) The work done on developing phase 2 for construction was noted, including identifying cost savings, financial affordability options and the development of a business case, and that work was on-going to realise other financial opportunities to reduce costs further. (7) It was noted that the outcome of this work recommends that the most economically viable and affordable option was to extend the line as far as Merry Hill with a scheme design that provided passive provision to enable the continuation to Brierley Hill High Street, subject to the development of a further viable business case which would need an affordable funding solution. (8) It was noted that the funding viability of the business case which the WMCA was being asked to approve was ...
Word for word from the decision West Midlands Combined Authority published for this meeting. Source: governance.wmca.org.uk

Follow this further

Built from West Midlands Combined Authority's papers

What the report saysPro

Report to WMCA Board

Name of meeting: WMCA Board

Meeting date: 19 July 2024

Report title: Wednesbury to Brierley Hill Metro Extension – Phase 2

Portfolio Lead: N/A Anne Shaw, Executive Director, Transport for West Responsible Director: Midlands

Mike Waters, Director Policy, Strategy and Innovation, [email removed] Report author: Amanda White, Metro Director, [email removed]

Key Decision? Yes 10/04/24

Is the ability for the Combined Authority to make a decision internally reliant on Constituent or Non-Constituent Councils making a formal decision first?

☐Yes ☒No

(If Yes – please contact the Member Relationship Manager to manage this process)

Public/private Public report:

Exempt by virtue Choose an item. To view the reasons why a report could be made of paragraph: exempt please check the Report Writing Guidance.

1. Decision/s Recommended WMCA Board is asked to:

(1) Approve the Single Assurance Framework Change Request to increase the overall budget by £248.5m including a new funding allocation of £36m CRSTS overprogramming to allow completion of the Phase 2 of the Extension to Merry Hill; amending the funding envelope, scope and timescale, as set out in the body of the report, noting that the overall funding package is subject to DfT approving the business case as detailed below. (2) Approve conditional release of the full funding to complete Phase 2 to Merry Hill, subject to the development of a robust and credible plan within the locally led Place Based Strategy that can:- secure a contribution to the scheme which will off-set the level of CRSTS financial over-programming currently required in order to build Phase 2; and will drive up the levels of patronage on the overall WBHE line such that operational subsidy requirements are reduced, for example through a regeneration and land use planning framework. This will require further WMCA Board approval prior to the release of the full funding.

(3) Approve the advanced expenditure of up to £6m for Phase 2 utilities and advanced works ahead of any HMG approval of the Phase 2 business case, to be released incrementally to minimise exposure. As set out in the Financial Implications section of the report this will be funded from the element of the residual scheme funding that is supported through WMCA Capital Financing and is within total budget envelope for WBHE already approved by WMCA Board in June 2023.

(4) Authorise the WMCA’s Executive Director for Transport and Section 73 Officer (typically referred to as s151 Officer) to finalise and formally submit the Full Business Case to central government for consideration in order to unlock the required additional funding from DfT and DLUHC.

(5) Note that Phase 1 of the Wednesbury to Brierly Hill Metro Extension is currently under construction to Dudley town centre (due for completion in 2025) and that costs for this element will increase by up to £15m should the Phase 2 element of the scheme not be approved, plus any spend incurred relation to the advanced utilities works.

(6) Note the work done on developing Phase 2 for construction, including identifying cost savings, financial affordability options and the development of a business case, and that work is on-going to realise other financial opportunities to reduce costs further.

(7) Note that the outcome of this work recommends that the most economically viable and affordable option is to extend the line as far as Merry Hill with a scheme design that provides passive provision to enable the continuation to Brierley Hill High Street subject to the development of a further viable business case which will need an affordable funding solution.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Wednesbury to Brierley Hill Metro Extension: Phase 2Report 306 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

18 of 29 attended
RP
Richard ParkerChair, present
ST
Councillor Sharon ThompsonDeputy Chair, present
AA
Councillor Adrian AndrewCommittee Member, present
JB
Councillor Joe BakerNon-Constituent Member, apologies, sent representative
PB
Councillor Paul BradleyCommittee Member, present
KC
Councillor Kerrie CarmichaelCommittee Member, present
JC
Councillor John CottonCommittee Member, present
IC
Councillor Ian CourtsCommittee Member, present
SD
Councillor Shaun DaviesNon-Constituent Member, absent
ID
Councillor Ian DavisonNon-Constituent Member, apologies
CD
Councillor Carol DeanNon-Constituent Member, absent
GD
Councillor George DugginsCommittee Member, present

All 29 on the meeting page

On this subject at West Midlands Combined Authority

Search all
  1. Wednesbury to Brierley Hill Metro Extension – Phase 2This decision
  2. Wednesbury - Brierley Hill Metro Extension Phase 2BApproved
  3. Wednesbury - Brierley Hill Metro Extension Funding Mitigation MeasuresNoted
  4. Wednesbury - Brierley Hill Metro Extension UpdateNoted
  5. Midland Metro Wednesbury to Brierley Hill ExtensionNoted
  6. Midland Metro Wednesbury to Brierley Hill Extension UpdateNoted

More from West Midlands Combined Authority WMCA Board

All decisions
MeetingDecisionOutcome
17 Jul 2026 Apologies for AbsenceCecilie Booth (Audit, Risk & Assurance Committee), Councillor Paul Bradley (Dudley), Councillor George Duggins (Coven... Decided Open
17 Jul 2026 Chair's RemarksThe Chair provided a summary of the recent delivery and activity that he had been involved in. Decided Open
17 Jul 2026 Minutes - 12 June 2026Agreed as a correct record. Agreed Open
17 Jul 2026 Constitution Review(1) The proposed amendments to parts A and B of the constitution, as amended, were approved. (2) Authority was delega... Approved Open
17 Jul 2026 Rosewell Review Phase 2 / Transport for City Regions(1) The work undertaken as part of phase 2 of the Rosewell Review, including its proposals regarding how the Transpor... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies