Wednesbury - Brierley Hill Metro Extension Phase 2B

Approved Committee 2 papers

WMCA Board approved this item on Friday 15 November 2024. Below is the council's own wording, with the papers it was decided on.

Item35

Resolved

(1) Subject to ministerial sign off, the continuation of the construction of the metro extension to Merry Hill in line with the business case and funding package which has been formally reviewed and supported by the Department for Transport was approved. (2) Subject to appropriate/binding funding confirmations in line with the above, the Section 73 Officer was authorised to establish within the capital programme a budget for the delivery of the metro extension phase 2B totalling £261.4m, noting that work was ongoing to finalise the contractual Target Cost 2 position which could be below this figure. (3) The ringfencing of £4.84m of City Region Sustainable Transport Settlement overprogramming to enable the project to move forward was authorised, pending the formal incorporation of identified opportunities in the project budget. (4) The Executive Director for Transport for West Midlands, in consultation with the Section 73 Officer, was authorised to approve the Target Cost 2 documentation and any adjustments with the Midland Metro Alliance to deliver the necessary phase 2 works. (5) The implications of this decision for the Medium-Term Financial Plan and the progress made by Dudley Metropolitan Borough Council on the development of its place-based strategy and expected growth in housing and employment opportunities which would drive up patronage with the intention of mitigating increased metro subsidy costs over time was noted. (6) It was noted that this place-based strategy would advance growth proposals and support the development of a further business case seeking to deliver the final stage of delivery to Brierley Hill High Street. [NB. At its meeting on 9 May 2025, the WMCA Board agreed an amendment to resolution (2) above to correct an error within the original recommendation. This amendment clarified that a budget for the delivery of the metro extension phases 2B totalling £261.4m would be established.]
Word for word from the decision West Midlands Combined Authority published for this meeting. Source: governance.wmca.org.uk

Follow this further

Built from West Midlands Combined Authority's papers

What the report saysPro

Report to WMCA Board

Change Request Form Single Assurance Framework

1 METRO WBHE PHASE 1 - CHANGE REQUEST DETAIL

CHANGE SUMMARY Project Name: Metro WBHE Phase 1 Programme Name (if applicable) Wednesbury to Brierley Hill Metro Extension Directorate (if WMCA internal): TfWM This Change Request is seeking £36.0m new funding, plus confirmation of £212.5m additional WMCA funding of: This Change Request is seeking a Approx 5 years (2023 to 2028) time extension of: This Change Request is seeking the Reduction of 0.6km track following change to the scope:

STAKEHOLDER INVOLVEMENT Role Name Input Date Senior Responsible Owner Amanda White Signed Off 1/5/24 (SRO): WMCA Executive Director: Anne Shaw Consented DSO, 22/4/24 Mandatory

Finance Lead: PJ Dubb Provided 19/4/24 (if WMCA internal complete comments Section 4) Legal Representative: Kieran Stockley Signed Off 17/4/24 (if WMCA internal complete Section 4) Procurement Lead: N/A Choose an item.

VERSION CONTROL Version: 1.0 Date: 21/05/2024 Change Prepared by: Tom Oldershaw Job Title: Delivery Planning Lead

1 WMCA-SAF-TP006 Change Request Form v4.1 Change Request Form Single Assurance Framework

2 BASELINE ASSESSMENT, CHANGE REQUEST DESCRIPTION AND RATIONALE

2A WHICH BUSINESS CASE STAGE IS THIS CHANGE AGAINST? (SELECT ONE OPTION IN THE DROP- DOWN LIST)

Full Business Case (FBC)

2B ROOT CAUSE AS DETERMINED BY STRATEGIC RISK CATERGORIES

Financial - Seeking safe delivery options with little residual financial loss only if it could yield upside opportunities.

2C CHANGE DESCRIPTION AND RATIONALE (MAX 500 WORDS)

The full business case (FBC) for Wednesbury to Brierley Hill Extension was approved by WMCA in March 2019 (190222 WBHE FBC TAP IAG Submission updated clean.pdf (sharepoint.com)) and stated that the Transport and Works Act Order (TWAO) would be granted in December 2019 and the scheme would open to passenger service in December 2023. The business case was also founded on the assumption that an agreement to acquire the disused South Staffordshire Railway corridor from Network Rail would complete when the TWAO was granted at the end of 2019 to facilitate delivery of the scheme.

The agreement with Network Rail was not completed until July 2020 and the TWAO was not granted until September 2020. The impact of the pandemic and rising inflation rates all contributed to the full project delivery costs exceeding the funding allocation approved in the final business case. Given the increase in project costs, WMCA Board took the decision to phase the delivery of the scheme 15 July 2022 (see attached minutes item 34 (9) (moderngov.co.uk)).

The result of this phasing was to split the scheme in two sections: • Phase 1 : Wednesbury to Dudley • Phase 2 : Dudley to Brierley Hill

This change request addresses the delivery of Phase 2, in timescales, finances and scope.

Additional funding had been made available from Central Government to cover the shortfall in costs, with significant work undertaken to revise and update the business case to confirm this funding. At the time of the funding award, it was anticipated that the additional Government funding was sufficient to construct the line to The Waterfront (known as Phase 2a), with funding identified locally to proceed to Merry Hill (Phase 2b). Construction to Brierly Hill town centre (Phase 2c) would rely on further local funding to be identified.

Updating the costs of the scheme using latest construction prices showed that even with the additional funding from Government, Phase 2a is now unaffordable. In addition, the local funding for Phase 2b is not available and there is no source of funding identified for Phase 2c. The business case work identified that Phase 2b was the most viable option when considering affordability and value for money. The difference between the available funding and the project costs will be met by an alternative source of local funding, using additional over-programming of CRSTS following principles previously agreed by WMCA Board.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Enc. 1 for Wednesbury Brierley Hill Metro Extension Phase2Report 503 KB DownloadRead as text
PDF
Wednesbury: Brierley Hill Metro Extension Phase 2BReport 258 KB Download

At this meeting

Whole meeting

Who was there

16 of 29 attended
RP
Richard ParkerChair, present
ST
Councillor Sharon ThompsonVice-Chair, present
AA
Councillor Adrian AndrewCommittee Member, present
JB
Councillor Joe BakerNon-Constituent Member, absent
PB
Councillor Paul BradleyCommittee Member, present, as expected, virtual
KC
Councillor Kerrie CarmichaelCommittee Member, present
LC
Councillor Lee CarterNon-Constituent Member, apologies
JC
Councillor John CottonCommittee Member, apologies
IC
Councillor Ian CourtsCommittee Member, present
ID
Councillor Ian DavisonNon-Constituent Member, apologies
CD
Councillor Carol DeanNon-Constituent Member, absent
GD
Councillor George DugginsCommittee Member, present

All 29 on the meeting page

On this subject at West Midlands Combined Authority

Search all
  1. Wednesbury - Brierley Hill Metro Extension Phase 2BThis decision
  2. Wednesbury to Brierley Hill Metro Extension – Phase 2Approved
  3. Wednesbury - Brierley Hill Metro Extension Funding Mitigation MeasuresNoted
  4. Wednesbury - Brierley Hill Metro Extension UpdateNoted
  5. Midland Metro Wednesbury to Brierley Hill ExtensionNoted
  6. Midland Metro Wednesbury to Brierley Hill Extension UpdateNoted

More from West Midlands Combined Authority WMCA Board

All decisions
MeetingDecisionOutcome
17 Jul 2026 Apologies for AbsenceCecilie Booth (Audit, Risk & Assurance Committee), Councillor Paul Bradley (Dudley), Councillor George Duggins (Coven... Decided Open
17 Jul 2026 Chair's RemarksThe Chair provided a summary of the recent delivery and activity that he had been involved in. Decided Open
17 Jul 2026 Minutes - 12 June 2026Agreed as a correct record. Agreed Open
17 Jul 2026 Constitution Review(1) The proposed amendments to parts A and B of the constitution, as amended, were approved. (2) Authority was delega... Approved Open
17 Jul 2026 Rosewell Review Phase 2 / Transport for City Regions(1) The work undertaken as part of phase 2 of the Rosewell Review, including its proposals regarding how the Transpor... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies