Resolved
(1) The report be noted.
Transport Delivery Overview & Scrutiny Committee noted this item on Monday 13 January 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
(1) The report be noted.
Appendix 1
VLRRP Highlight Report P Project Summary Information Project Name VLR (Very Light Rail) Regional Programme (VLRRP) SRO Anne Shaw Programme CRSTS VLRRP Programme Nicola Small (Deputy SRO) Date 5th December 2024 Director Funding Allocated: CVLR £40.5m VLRNIC £12m TfWM Mass Transit Corridor Studies £5m
Total £57.5m Brief Description (Project scope and deliverables) • Coventry Very Light Rail (CVLR) scheme promoted by Coventry City Council (CCC) (£40.5m) • Dudley Very Light Rail National Innovation Centre (VLRNIC) promoted by the Black Country Innovative Manufacturing Organisation (BCIMO) and Dudley Council (£12m) • Mass Transit Options Appraisal study which is to include an assessment of urban VLR promoted by Transport for West Midlands (TfWM) (£5m) The three schemes within the business case complement each other: • CVLR is the pilot scheme, with Coventry leading the development of the VLR product (CVLR Vehicle and CVLR Track) and facilitating the construction of the first in-highway section of CVLR track as the final demonstration of the proof of concept for the system. • VLRNIC is supporting the CVLR R&D (Research & Development) programme by providing test facilities for the system before the installation in a live highway. • TfWM are in the early stages of exploring the use of CVLR technology (as well as other mass transit options) for corridors in the West Midlands
VLRRP Update Update from CCC on CVLR Programme • Coventry City Council are currently preparing to do an on road test in Coventry City Centre in early 2025. The following provides a work stream update in preparing for the on road test. • Vehicle: The CVLR vehicle is undergoing a period of engineering design validation and testing at a component and whole vehicle level. This testing will be complete by March 2025. Final modifications to align to the case for safety will be completed prior to demonstrations in May 2025. Case for safety documentation is being compiled to present to the independent competent person prior to demonstrations. • Track: Slabs to be used in the on road test have been ordered. Development of the Uni-Track (slab that can accommodate standard weight trams) has started and being fully scoped to determine performance requirements. Development of the Ultra-Thin slab (to be used where there is insufficient space in the highway to accommodate 300mm such as bridge decks) is progressing well with the concept proven as feasible. • Route: Long lead time items (rail, slabs etc.) have been ordered. Detailed design of alignment is complete with operational detail being defined. Construction contractor contract is in process award is anticipated early in the new year. The on road is 220 meters, and will be segregated from pedestrians and vehicles. • Operator: Concept of operations document has been compiled and procurement of an operator for the on road test will begin in early 2025. Current operator input is being provided by PMOL. • Communications and commercialisation: CVLR continue to represent the project at industry events. The project continues to generate significant interest from all aspects from potential customers, funders and suppliers. Update from BCIMO on VLRNIC Programme
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix 1Appendix 1 | 106 KB | Download |
PDF |
Appendix 2Appendix 2 | 523 KB | Download |
PDF |
Enc. 2 for Very Light Rail Regional Programme UpdateReport | 106 KB | DownloadRead as text |
PDF |
Enc. 3 for Very Light Rail Regional Programme UpdateReport | 523 KB | Download |
PDF |
Enc. 4 for Very Light Rail Regional Programme UpdateReport | 2.3 MB | Download |
PDF |
Very Light Rail Regional Programme UpdateReport | 182 KB | Download |
Follow Transport Delivery Overview & Scrutiny Committee at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Mar 2026 | Member Engagement Groups – Progress ReportIt was agreed that this matter would be brought to the May meeting as a potential focus for committee’s 2026/27 work ... | Agreed | Open |
| 8 Sep 2025 | Exclusion of the Public and PressThe public and press be excluded from the meeting for the following item of business under s100(A) of the Local Gover... | Decided | Open |
| 10 Mar 2025 | Presentation on WMCA Air Quality Sensor Network and WebsiteThe report be noted | Noted | Open |
| 10 Mar 2025 | Railways Bill ConsultationThe report be noted. | Noted | Open |
| 10 Mar 2025 | Capital Performance Report (February 2025)The committee report and dashboard be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.