Coventry Very Light Rail Stage Gates

Approved Committee 2 papers

Investment Board approved this item on Monday 22 July 2024. Below is the council's own wording, with the papers it was decided on.

Item25

Resolved

The revisions to the WMCA Board approved Strategic Outline Case made in 2024 by WMCA under delegated powers, as detailed in section 10 of the report be noted; 2. The West Midlands Combined Authority enter into a Grant Agreement with Coventry City Council for Coventry Very Light Rail (CVLR) Stage Gate 2 for £6.85m be approved; 3. The total value of Grant Agreements to be entered into between WMCA and Coventry City Council would not exceed the total value of funding that DfT have approved for release be noted; 4. Delegated authority be granted to the Executive Director of Transport for the West Midlands (TfWM), in agreement with the Section 73/151 Officer and Monitoring Officer to authorise the release of future CVLR allocations, subject to appropriate agreement/consent from the Independent Review Panel and Department for Transport (DfT) be approved and 5. The WMCA can enter into a grant agreement with Coventry City Council for Coventry very Light Rail as appropriate once the delegation above has been exercised and the DfT have released funding in line with the Strategic Outline Case be agreed.
Word for word from the decision West Midlands Combined Authority published for this meeting. Source: governance.wmca.org.uk

Follow this further

Built from West Midlands Combined Authority's papers

What the report saysPro

Report to Investment Board

Executive summary

3.1The Very Light Rail Regional Programme (VLRRP) Strategic Business Outline Case (SOBC) was approved by WMCA Board on 13th January 2023 with specific financial terms and conditions and at the time funding was released for Stage Gate 1 only (£8.9m)

3.2This report sets out the agreed assurance process for the VLRRP which is being funded through the City Region Sustainable Transport Settlement (CRSTS) and the process agreed with the DfT to release funding for CVLR which has an allocation of £40.5m and remains a retained scheme due to its value and Research & Development (R&D) nature.

3.3The 3 projects within the VLRRP are as follows and the amount allocated to each of these through the approved SOBC submission is highlighted:

• Coventry Very Light Rail (CVLR) scheme promoted by Coventry City Council (CCC) (£40.5m allocated £35m originally approved at SOBC with funding for CVLR stage Gate 1 released (£8.9m)) • Dudley Very Light Rail National Innovation Centre (VLRNIC) promoted by the Black Country Innovative Manufacturing Organisation (BCIMO) and Dudley Council (£12m allocated £1.2m approved at SOBC) • Mass Transit Options Appraisal study which is to include an assessment of urban VLR promoted by Transport for West Midlands (TfWM) (£5m allocated £600k approved at SOBC)

3.4CVLR is being delivered in 4 stage gates, as approved by WMCA Board on 13th January 2023. This report focuses on CVLR as set out above and is recommending approval to change the delegated power from Investment Board to the Executive Director of Transport for the West Midlands (TfWM), in consultation with the Section 73/151 Officer and Monitoring Officer.

3.5The process agreed with DfT for funding release is set out in Appendix 1, which also explains how the process will integrate with the WMCA’s Single Assurance Framework (SAF).

3.6An update on the current status of the CVLR programme can be provided upon request. 4. Matters for Consideration

4.1The VLRRP is not a traditional transport delivery programme. It is deemed a R&D programme by DfT and as such a bespoke assurance process has been put in place and agreed with DfT which is explained in Appendix 1.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Integrating CVLR and VLRNIC IRP into SAFAppendix 1 523 KB Download
PDF
Coventry Very Light Rail Stage GatesReport 383 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 25 attended
PH
Councillor Peter HughesChair, present
SC
Councillor Steve ClarkCommittee Member - Voting, present
JO
Councillor Jim O'BoyleCommittee Member - Voting, apologies
BS
Councillor Bob SleighCommittee Member - Voting, present
MS
Councillor Mark StathamCommittee Member - Voting, present
ST
Councillor Sharon ThompsonCommittee Member, present
SS
Sue SummersCommittee Member - Non-Voting, apologies
EB
Ed BradburnOfficer, expected
NO
Nick OakleyOfficer, expected
NS
Nicola SmallOfficer, in attendance
SS
Sandeep ShingadiaOfficer, in attendance
NY
Nicholas YoungerOfficer, in attendance

All 25 on the meeting page

More from West Midlands Combined Authority Investment Board

All decisions
MeetingDecisionOutcome
17 Aug 2026 Minutes - 20 July 2026The minutes of the meeting held on 20 July 2026 were approved as a correct record. Approved Open
17 Aug 2026 Rosewell Review Phase 2/ Transport for City Regions UpdateResolved that: 1. The principles developed to help guide the allocation of the remaining £405m of funding to the Port... Noted Open
17 Aug 2026 Investment Programme UpdateResolved that: 1. Since the previous sitting of the WMCA Investment Board there have been no change requests approved... Approved Open
17 Aug 2026 Investment Programme Dashboard- Red Rated Projects UpdateResolved that: 1. The current position of the eight red-rated projects within the Investment Programme Dashboard, inc... Noted Open
17 Aug 2026 Commercial Investment Fund DashboardResolved that: The report be noted. Noted Open