Resolved
(1) The committee endorsed the approach and assurance of monitoring the Annual Business Plan for 2024/25. (2) The committee considered areas of interest including the Thrive to Work Programme to form part of its future work programme.
Overview & Scrutiny Committee decided this item on Monday 3 March 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
(1) The committee endorsed the approach and assurance of monitoring the Annual Business Plan for 2024/25. (2) The committee considered areas of interest including the Thrive to Work Programme to form part of its future work programme.
Appendix 1 – Q1-Q3 RAG status trend (2024/2025)
Monitoring On Target At Risk Attention Complete Not Started Total Required period
Apr-24 100 2 0 0 18 120
May-24 106 4 0 0 10 120
Q1 Jun-24 110 2 2 1 5 120
Jul-24 108 6 2 1 3 120
Aug-24 105 9 2 2 2 120
Q2 Sep-24 100 14 1 3 2 120
Oct-24 101 14 1 4 0 120
Nov-24 94 16 5 5 0 120
Q3 Dec-24 86 17 7 10 0 120 Appendix 2 - Q3 mitigation commentary by exception PI No. and Name RAG KPI Milestone No Mitigation Commentary status or PI and Name
97 - Deliver WMCAs refreshed PI 9701 - WMCA This milestone has been delayed due to the significant organisational medium term strategy. Medium Term changes in preparation for the IS. It has been determined that it would be Strategy more practical to review and refresh the medium term corporate strategy next year. 54 - Fund and effectively PI 5405 - Ring & This milestone will not be fully delivered by the year-end as the intention was manage essential supported Ride to incorporate Demand Responsive Transport into the new Ring & Ride services that provide a social Mobilisation operating model for early 2025. This will now be considered later in the year benefit including concessions, due to changes in the way HMG is providing its funds to WMCA and the ring and ride, and tendered bus Medium Term Financial Challenges facing the CA and its ability to deliver services. local public transport provision from 2026/27 onwards.
33 - Work with Local Authorities KPI 3302 - Connect This milestone has been delayed due to ongoing conversations with Local to develop a delivery model for to Work Authorities to commission activity for the Connect to work programme. Connect to Work, Contracting Completion is now unlikely this financial year following delayed clarification Commissioning and of requirements from DWP. Commencement Delivery. PI No. and Name RAG KPI Milestone No Mitigation Commentary status or PI and Name
36 - Delivery of Active Travel PI 3603 - ATF This programme is delivered by the Local Authorities and the milestone will Fund: Work across the region to Programme 4 & not be achieved in this financial year, with only 50% completed by the year- support our Local Authority 4e end. The bulk of the funding is secured until March 2026 and there is partners, and in collaboration minimal risk of any funds being clawed back. WMCA Is in active with Active Travel England, to conversations with the WM Local Authorities to maximise delivery by the end support the delivery of the Active of the programme. Travel Fund programme including developing a pipeline of shovel ready scheme to take forward for future funding tranches.
49 - Deliver the transport capital KPI 4901 - Dudley Business Justification Case(BJC) for Phase 2 will commence on conclusion programme under City Regional Port of BJC Phase 1. Sustainable Transport Interchange Settlements, ATF and other Phase 2 legacy funds. 4902 - VLRRP Awaiting detailed costed proposal and programme from Coventry City Trackform R & Council. This process has been delayed due to further engagement with D full size trams specialist consultants to refine the proposal. Proposal expected early in the new year.
Once received, we will review the detailed proposal, subject to agreement we will proceed to entering into a Services Agreement with Coventry City Council.
4904 - Dudley We are holding the development funding for Phase 3 until certainty exists Port and DfT / Network Rail have agreed their funding allocation and the process Interchange for early stage studies. Phase 3 PI No. and Name RAG KPI Milestone No Mitigation Commentary status or PI and Name
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
AppendicesReport | 93 KB | DownloadRead as text |
PDF |
Q3 Performance monitoring against the Annual Business PlanReport | 153 KB | Download |
Follow Overview & Scrutiny Committee at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Feb 2026 | WMCA Reserves Policy(1) A briefing note on the use of reserve and associated costs for maintaining and developing 16 Summer Lane, includi... | Decided | Open |
| 16 Feb 2026 | Air Quality Programme Update - Presentation(1) The Head of Environment provide the committee with the research undertaken by the University of Birmingham on the... | Decided | Open |
| 16 Feb 2026 | Q3 Performance monitoring against the Annual Business Plan(1) The Chair of the Overview & Scrutiny Committee write to the Chair of the Transport Delivery Overview & Scrutiny C... | Decided | Open |
| 16 Feb 2026 | Work ProgrammeThe work programme be noted. | Noted | Open |
| 16 Feb 2026 | Exclusion of the Public and PressIn accordance with s100(A) of the Local Government Act 1972, the public and press be excluded from the meeting for th... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.