(1) The rebased 2025/26 capital programme was approved. (2) The financial position as at 31 May 2025, including the material improvement in treasury management forecasts, was noted. (3) Authority was delegated to the Section 73 Officer, in consultation with the relevant Executive Directors, to accept funds awarded to the WMCA ahead of the next WMCA Board meeting. (4) The revised funding strategy for the transition and management costs associated with bus franchising was approved. (5) The recharge of 2025/26 Business Rates Growth monies was noted. (6) The treasury management outturn 2024/25 was noted.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
Report title: Financial Monitoring Report 2025/26 – Month 2 Linda Horne, Executive Director of Finance and Business Responsible Director: Hub Beverly Sullivan, Financial Planning & Co-ordination Report author: Manager Key Decision? No
Is the ability for the Combined Authority to make a decision internally reliant on Constituent or Non-Constituent Councils making a formal decision first?
☐Yes ☒No
(If Yes – please contact the Member Relationship Manager to manage this process)
Recommendations (1) Approve the rebased 2025/26 capital programme as detailed in paragraphs 2.1 to 2.6 and Appendix 1 of this report. (2) Note the financial position as at 31 May 2025, as detailed in paragraphs 2.7 to 2.16, including the material improvement in Treasury management forecasts. (3) Delegate authority to WMCA’s S73 Officer and Executive Directors to accept funds awarded to WMCA ahead of the next WMCA Board meeting, as detailed in paragraph 2.20. (4) Approve the revised funding strategy for the transition and management costs associated with bus franchising, as outlined in paragraphs 2.22 to 2.24. (5) Note the recharge of 2025/26 Business Rates Growth monies, as outlined in paragraphs 2.25 to 2.26 (6) Note the Treasury Management Outturn 2024/25 as detailed in paragraphs 2.27 to 2.31 and Appendix 7 of this report.
Voting Requirements The Mayor, and separately, at least two-thirds of the members appointed by the constituent councils, in attendance in the meeting room and indicating their preference, are required to vote in favour of any recommendation/proposition for it to become a decision of the board [‘Requirement B’ as specified in paragraph 18.9(b) of the constitution]. 1. Executive Summary 1.1 This report provides an update of the West Midlands Combined Authority finances as at the end of May 2025. This is the first financial monitoring report of the 2025/26 fiscal year. The revised capital programme is also brought for approval, in line with standard practice.
2. Matters for Consideration
2025/26 Capital Budget updates 2.1 When the WMCA Board approved the 2025/26 capital budget in March 2025, it was made explicit that the figures were indicative only and would be updated when there was clarity on the 2024/25 outturn position. This update has now taken place, and the capital budgets have been rephased to take account of the outturn position, capital financing pressures, new grants received, as well as resourcing capacity and practical delivery expectations.
2.2The proposed budget for 2025/26 is £622.0m, which is £264.3m (74%) higher than the 2024/25 outturn. Contributory factors to the increase are the updated delivery expectations of projects in train from 2024/25, and new grants primarily derived from the single year Integrated Settlement in 2025/26. The main increases are on:
• Transport (Internal) +£71.6m – investment in the transport infrastructure as follows: Metro +£33.5m, Bus +£31.6m, Rail -£10.5m, SPRINT +£8.8m.
• Grants to Local Authorities (External) +£47.9m – mainly spend on Coventry City Centre South project +£27.4m and the Active Travel Fund Programme +£9.7m.
• Rail (External) +£29.2m – to progress Very Light Rail Demonstration Route +£28.4m
2.3The updated capital programme profile is shown in Table 1 below, which is predominantly funded by grants. Further details on the rephased capital budgets can be found in Appendix 1 of this report.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.