WMCA Financial Monitoring Report - November 2023

Noted Committee 1 paper

WMCA Board noted this item on Friday 17 November 2023. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

(1) The financial position as at 30 September 2023 was noted. (2) The early warning of a further projected overspend of £1.5m on the Metro Wolverhampton City Centre Extension project was noted, and the proposed funding solution and potential budget increase of £1.5m was approved. (3) The new grant awards to the WMCA were noted. (4) The updated financial planning position for the period 2024/25 to 2028/29 was noted. (5) The updated position on the Sustainable Warmth competition was noted. (6) The Treasury and Prudential Indicators for the period ending September 2023 (Quarter 2) was noted. (7) The outcome of the annual review of the Single Assurance Framework, undertaken in accordance with the requirements mandated by Government, was noted. (8) The performance to date of the West Midlands 100% Business Rates Retention Pilot was noted. (9) The Memorandum of Understanding with the Government regarding the offer of 10-year, 100% Business Rate Retention for the West Midlands, in accordance with the Trailblazing Devolution Deal, was approved. (10) Authority was delegated to the Section 151 Officer (following consultation with the relevant portfolio holder) to accept grants awarded to the WMCA between 17 November 2023 and the January 2024 WMCA Board meeting, subject to the terms and conditions of those grants being acceptable to the Monitoring Officer, Section 151 Officer and the relevant Executive Director, and the relevant Single Assurance Framework process being followed.
Word for word from the decision West Midlands Combined Authority published for this meeting. Source: governance.wmca.org.uk

Follow this further

Built from West Midlands Combined Authority's papers

What the report saysPro

Report to WMCA Board

WMCA Board Date 17 November 2023

Report title Financial Monitoring Report 2023/24

Portfolio Lead Finance - Councillor Bob Sleigh

Accountable Chief Laura Shoaf, West Midlands Combined Authority Executive email: [email removed]

Accountable Linda Horne, Executive Director of Finance and Employee Business Hub email: [email removed]

Report has been Executive Board – 8 November 2023 considered by WM FDs – 9 November 2023

Recommendation(s) for action or decision:

WMCA Board is recommended to:

(1) Note the financial position as at 30 September 2023, as detailed in Sections 2 and 3.

(2) Note the early warning of a further projected overspend of £1.5m on the Metro Wolverhampton City Centre Extension project and approve the proposed funding solution and potential budget increase of £1.5m.

(3) Note the new grant awards to the WMCA as shown in Section 5.

(4) Note the updated financial planning position for the period 2024/25 to 2028/29, as detailed in Section 6.

(5) To note the updated position on the Sustainable Warmth Competition, as outlined in Section 8.

(6) Note the Treasury and Prudential Indicators for the period ending September 2023 (Quarter 2) as outlined in Section 9 and Appendix 6 of this report.

(7) To note the outcome of the annual review of the Single Assurance Framework (SAF), undertaken in accordance with the requirements mandated by Government (Section 14). (8) Note the performance to date of the West Midlands 100% Business Rates Retention Pilot, as detailed in private Appendix 12.

(9) Agree to the Memorandum of Understanding (MoU) with Government regarding the offer of 10-year, 100% Business Rate Retention for the West Midlands, in accordance with the Trailblazing Devolution Deal (private Appendix 12).

(10) Delegate to the Section 151 Officer (following consultation with the relevant portfolio holder) the ability to accept grants awarded to WMCA between the date of this meeting and the January 2024 WMCA Board meeting; subject to the terms and conditions of those grants being acceptable to the WMCA Monitoring Officer, Section 151 Officer and the relevant Executive Director and the relevant SAF process being followed.

1.0Purpose

1.1To provide an update on the Combined Authority’s finances as at 30 September 2023, an update on the medium term financial plan and risks facing the organisation.

2.02023/24 Year to Date Revenue Position

2.1Appendix 1 shows the overall consolidated revenue position for the West Midlands Combined Authority, whilst Appendices 2 to 4 present the detailed summaries for Transport, the WMCA Delivery Portfolios and the Mayoral office respectively.

2.2The position at the end of September is a surplus of £4.0m which is a favourable variance from budget of £3.9m.

2.3Within Transport there is a surplus of £2.6m which represents a favourable variance from budget of £2.2m. The year to date position is due to the impact of staffing vacancies as well as receipt of Local Transport Fund grant which will meet contractual costs of the tendered bus service across the rest of the financial year. Concessionary related underspends have arisen due to patronage remaining below pre pandemic levels. In line with agreement from the Board, these savings have been transferred to a reserve to protect against future transport network risks.

2.4Within the Portfolio budgets there is a favourable variance of £1.7m due to staff vacancies, underspends on external advice and receipt of new grant income. There remain underspends against the grants within Economic Skills and Communities totalling £38.3m to date, including AEB, Multiply, Digital Skills and UKSPF. This position is only of timing only, with fully recovery of the position anticipated at year end.

2.5The Mayoral Office position as at the end of September 2023 was in line with budget.

3.02023/24 Capital Programme Position

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
WMCA Financial Monitoring Report: November 2023Report 404 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 29 attended
AS
Andy StreetChair, present
BS
Councillor Bob SleighVice-Chair, present
AA
Councillor Adrian AndrewCommittee Member, absent
MB
Councillor Mike BirdCommittee Member, present
PB
Councillor Paul BradleyCommittee Member, present
KC
Councillor Kerrie CarmichaelCommittee Member, apologies
JC
Councillor John CottonCommittee Member, present
IC
Councillor Ian CourtsCommittee Member, present
SD
Councillor Shaun DaviesNon-Constituent Member, absent
ID
Councillor Ian DavisonObserver Member Awaiting Membership, absent
MD
Councillor Matthew DormerNon-Constituent Member, present
GD
Councillor George DugginsCommittee Member, present

All 29 on the meeting page

On this subject at West Midlands Combined Authority

Search all
  1. WMCA Financial Monitoring Report - November 2023This decision
  2. West Midlands Combined Authority (WMCA) Financial Monitoring Outturn 2025/26Noted
  3. WMCA Financial Monitoring ReportNoted
  4. WMCA Financial Monitoring ReportApproved
  5. WMCA Financial Monitoring Report 2024/25 - Month 6Noted
  6. WMCA Financial Monitoring ReportNoted

More from West Midlands Combined Authority WMCA Board

All decisions
MeetingDecisionOutcome
17 Jul 2026 Apologies for AbsenceCecilie Booth (Audit, Risk & Assurance Committee), Councillor Paul Bradley (Dudley), Councillor George Duggins (Coven... Decided Open
17 Jul 2026 Chair's RemarksThe Chair provided a summary of the recent delivery and activity that he had been involved in. Decided Open
17 Jul 2026 Minutes - 12 June 2026Agreed as a correct record. Agreed Open
17 Jul 2026 Constitution Review(1) The proposed amendments to parts A and B of the constitution, as amended, were approved. (2) Authority was delega... Approved Open
17 Jul 2026 Rosewell Review Phase 2 / Transport for City Regions(1) The work undertaken as part of phase 2 of the Rosewell Review, including its proposals regarding how the Transpor... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies