That the Executive: 1. Recommend to Council that the total cost detailed in Annex A is allocated to the project from the Investment Properties Programme. 2. Recommend to Council that delegated authority be given to Director of Finance (S151) in consultation with Executive Member for Finance to approve the final cost of the projects
Word for word from the decision West Oxfordshire published for this meeting.Source: meetings.westoxon.gov.uk
Name and date of EXECUTIVE – 9 JULY 2025 Committee COUNCIL – 16 JULY 2025
Subject CARTERTON UNITS 1-3 AND STATION LANE ROOFING PROJECTS
Wards affected All
Accountable member Executive Member for Finance Alaric Smith Email: [email protected]
Accountable officer Madhu Richards, Director of Finance (S151) Email: [email protected]
Report author Barry Bodin-Jones, Lead Project Manager Email: [email protected]
Summary/Purpose To request allocation of funding for the re-roofing of investment and service properties that form part of the Capital Expenditure Budget for 2025/26 and the rationale for undertaking these works.
To seek approval of these costs so that officers can proceed with the works with external contractors.
Annexes Exempt Annex A – Detailed Financial Cost Breakdown and Projected Income from the Investment Properties
Recommendation(s) That the Executive resolves to: 1. Recommend to Council that the total cost detailed in Annex A is allocated to the project from the Investment Properties Programme. 2. Recommend to Council that delegated authority be given to Director of Finance (S151) in consultation with Executive Member for Finance to approve the final cost of the projects
Corporate priorities Working Together for West Oxfordshire
Key Decision YES Exempt NO (Annex A only Exempt)
Consultees/ Director of Finance, Interim Executive Director Publica, Executive Consultation Members 1. EXECUTIVE SUMMARY 1.1 These projects are included in the 2025/2026 Capital Expenditure Budget for Investment Properties Programme as these locations need significant roofing upgrades as existing roofs have failed. The works are critical to ensure that the buildings are watertight and in a lettable condition.
2. BACKGROUND 2.1 The Council acquired the Headleases of Plots 1-3 on 14th July 2021, already being the freehold owner. A 5-year lease was simultaneously granted. At the time the business case included planned works to the roofs at the site (£698,500). 2.2 The projects are included in the 2025/2026 Capital Expenditure Budget for Investment Properties Programme as these locations need significant roofing upgrades to avoid further degradation of the building structures themselves as well as the Council’s obligation as landlords to keep the buildings in a good working order for current tenants and for the purposes of attracting new tenants for revenue income generation. 2.3 Some of the current roofing structures are asbestos based and are not environmentally friendly both in terms of their material make up nor in terms of their sustainability credentials. The existing roofs have failed, and the works are critical to ensure that the buildings are watertight. 2.4 A tender process has been undertaken with a Framework selected due to the scale and complexity of the work that needs to be carried out, including controlled asbestos removal. Detailed negotiations have taken place with the main contractor with the assistance of a consultant who was able to advise on technical matters outside of the scope and knowledge of officers ensuring that every aspect of the proposed Schemes of Works is appropriately addressed and costed. This due diligence exercise has sought to ensure value for money for the Council, as tendering for all these works together provides economies of scale in terms of cost, project management and timescales.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.