That the Executive: 1. Agreed to progress to the construction phase of the Windrush Leisure Centre decarbonisation scheme. 2. Recommended to Council to allocate an additional council contribution of £340,683 towards the project in addition to the £224,866 already included within the capital programme. 3. Requested Officers to bring forward a works programme for the activities identified in the recent condition survey for the Windrush Leisure Centre.
Word for word from the decision West Oxfordshire published for this meeting.Source: meetings.westoxon.gov.uk
Summary/Purpose To present the business case for the decarbonisation of Windrush Leisure Centre.
Annexes None
Recommendation(s) That the Executive resolves to: 1. Agree to progress to the construction phase of the Windrush Leisure Centre decarbonisation scheme. 2. Recommend to Council to allocate an additional council contribution of £340,683 towards the project in addition to the £224,866 already included within the capital programme. 3. Request Officers to bring forward a works programme for the activities identified in the recent condition survey for the Windrush Leisure Centre.
Corporate priorities Putting Residents First A Good Quality of Life for All A Better Environment for People and Wildlife Responding to the Climate and Ecological Emergency Working Together for West Oxfordshire
Key Decision YES Exempt NO
Consultees/ GLL are aware that the Council is working on the decarbonisation of the Consultation Leisure Centre. EXECUTIVE SUMMARY 1.1 The Council has been progressing the Public Sector Decarbonisation Scheme (PSDS) Phase 3c funded project at Windrush Leisure Centre to remove a reliance on gas fired heating and to replace this system with Air Source Heat Pumps (ASHPs). The Investment Grade Proposal (IGP) has been completed and includes the detailed decarbonisation design and costs. Approval is sought to proceed to the construction phase and allocate additional council funding to the project. 1.2 The scheme will save 255.3 tCO2e per annum and reduce the Council’s total annual carbon emissions by 8.8%. The lifetime carbon savings are 5,106 tCO2e. 1.3 It is estimated that the scheme will save around £7,800 per annum in operational energy costs albeit offset by additional operating and capital financing costs totalling £32,800 per annum giving rise to a Council revenue budget pressure of £25,000 per annum. 1.4 The total capital cost of the decarbonisation scheme is estimated to be £2,175,914 with a Council contribution of £565,549, which includes an additional allocation of £340,683 from Council resources in 2025/26, over and above the £224,866 client contribution agreed as a condition of accepting the Salix Grant Offer. Grant funding from Salix received and spent on the project in 2024/25 totalled £430,069. The remaining expenditure of £1,745,845 is allocated to the 2025/26 financial year. 1.5 The project must be delivered and be operational by 31 March 2026 to secure the remaining £1,180,296 of PSDS grant funding. 1.6 A comprehensive condition survey of the Leisure Centre has been conducted, the recommendations from which will form part of a Building Maintenance Programme which will be coming forward to the Executive in September to approve a capital programme for Leisure assets for a rolling five-year period.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.