That:- 1. The undertaking of the Urgent Works process be authorised. 2. The acceptance of the mitigation measures, as set out in the exempt Appendix to this report, be agreed. That:- 1. The undertaking of the Urgent Works process be authorised. 2. The acceptance of the mitigation measures, as set out in the exempt Appendix to Report No: CAB/WS/20/027, be agreed.
Word for word from the decision West Suffolk published for this meeting.Source: democracy.westsuffolk.gov.uk
Cabinet Member: Councillor Susan Glossop Portfolio Holder for Growth Tel: 01284 728377 Email: [email protected]
Lead officer: Julie Baird Assistant Director (Growth) Tel: 01284 757613 Email: [email protected]
Decisions Plan: The decisions made as a result of this report will usually be published within 48 hours and cannot be actioned until five clear working days of the publication of the decisions have elapsed. This item is included on the Decisions Plan.
Wards impacted: Newmarket West
Recommendation: It is recommended that, Cabinet:
1. Authorises the undertaking of the Urgent Works process:
and
2. Agrees to the acceptance of the mitigation measures, as set out in the exempt Appendix to this report. 1.0 Background/Context
1.1Queensbury Lodge, Queensbury Cottage and Stables are each individually Grade II Listed Buildings and are situated on a prominent site at the entrance to Newmarket’s town centre. The yard is considered to be the second oldest racehorse-training establishment in the town after Palace House Stables.
1.2The buildings are all included in the Suffolk Historic Buildings at Risk Register due to neglect or prolonged lack of maintenance. They are on one of the main approaches to the town centre within the Newmarket Conservation Area and create a poor impression of the town and its attitude towards its horse racing and built heritage.
1.3The site has a long and complex planning history and has been the subject of a number of non-policy compliant planning applications and unsuccessful appeals by the landowner. It is thought the site was last used as a training yard for a short period in the late 1980s and since being in its current ownership has remained disused with no acceptable use being proposed despite some 35 applications and 13 appeals.
1.4In the early-mid 2000’s the owner took steps to protect the buildings including covering some roofs with board and felt and boarding up openings. Eventually, the roofing works began to fail and the need to provide support for parts of the buildings became apparent. The council has therefore made several requests to the owner to undertake further works to protect the buildings from continued deterioration. These requests have been declined.
1.5In the meantime, the condition of the three listed buildings has worsened. A survey in April 2019 identified part of the lodge which was in danger of collapse. If the building collapsed it would fall across the public footpath and road, posing a danger to public safety. Emergency works were therefore carried out under the supervision of the council’s Building Control team and the costs were recovered from the owner. These measures remain in place and, whilst they protect the public using the highway, they are not providing any support to the building itself to prevent collapse into the site. Urgent works are therefore now required to preserve the three buildings whilst discussions with the owner continue.
1.6S.54 of the Planning (Listed Buildings and Conservation Areas) Act 1990 allows the Council to serve an Urgent Works Notice on the owner giving notice of the Council’s intention to undertake works required to keep the buildings weather-tight, secure and safe from collapse. The owner is also given the opportunity to undertake the works themselves.
1.7Historic England’s advisers are aware of the site through previous planning discussions. They agree that the buildings are in urgent need of protection and support the Council’s approach now proposed. 2.0 Current position
2.1The Council has continued to work over the years with the landowner to agree an appropriate scheme for the site and proactive discussions are currently taking place. During this process, however, the condition of the listed buildings has deteriorated.
The Planning Process
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.