That: 1. subject to completion of heads of terms with Suffolk County Council for their elements of the phase 1 scheme, it be agreed that the Western Way project proceeds to second stage tendering, and its final gateway test, on the basis that all of the financial tests and safeguards required by Council in December 2022 are still capable of being met; and 2. the final budget for the phase 1 Western Way scheme and for interim works to the remainder of the site, including enabling works, remain as agreed by Council in December 2022.
Word for word from the decision West Suffolk published for this meeting.Source: democracy.westsuffolk.gov.uk
Western Way project Report number: CAB/WS/23/014 Report to and date: Cabinet 14 March 2023
Cabinet member: Councillor Joanna Rayner Portfolio Holder for Leisure, Culture and Community Hubs Tel: 01284 750366 Email: [email protected]
Lead officer: Alex Wilson Strategic Director Tel: 01284 757695 Email: [email protected]
Decisions Plan: The decision made as a result of this report will usually be published within 48 hours and cannot be actioned until five clear working days of the publication of the decision have elapsed. This item is included on the Decisions Plan.
Wards impacted: All wards
Recommendation: It is recommended that:
1. subject to completion of heads of terms with Suffolk County Council for their elements of the phase 1 scheme, the Western Way project proceeds to second stage tendering, and its final gateway test, on the basis that all of the financial tests and safeguards required by Council in December 2022 are still capable of being met; and
2. the final budget for the phase 1 Western Way scheme and for interim works to the remainder of the site, including enabling works, remain as agreed by Council in December 2022. Cabinet – 14 March 2023 – CAB/WS/23/014
1. Context to this report 1.1 In December 2022, Council approved an updated business case for phase 1 of the Western Way (WW) project in Bury St Edmunds and agreed that Cabinet could deliver the scheme provided it passed two further gateways. This report covers the first of those two gateways. The second gateway, and the final decision to proceed with the scheme, will not be considered until late summer 2023 at the earliest.
1.2No background information on the project is contained in this report as this has been extensively provided in earlier reports (see background information). Similarly, this report does not revisit earlier decisions taken by Council on the project.
1.3This report does not cover phase 2 of the Western Way project. As agreed by Council in December 2022, this would now be an entirely separate project requiring a new business case in 2024 and a new decision by councillors.
2. Proposals within this report 2.1 Project gateways and financial tests
2.1.1 In December 2022, Council agreed a new budget framework for the Western Way (WW) project to reflect a new phased delivery. In summary, at the time the main construction contract is signed in late summer/early autumn 2023, the Phase 1 scheme must now:
a. cost no more than £65 million in total (excluding the £10 million of interim works to the remainder of the WW frame/site as set out in paragraph 2.1.3);
b. not increase the Council’s existing Medium Term Financial Strategy (MTFS) provision of £724,000 for Bury St Edmunds Leisure Centre; and
c. in relation to other ancillary elements of the new hub, be capable of achieving at least a break-even position over the whole life of the borrowing (40 years).
2.1.2 If those tests are met, then Council has authorised the project to proceed under the normal constitutional provisions.
2.1.3 In addition to the phase 1 scheme defined in the December 2022 update, Council also authorised a further capital allocation of up to £10 million for interim works to the remainder of the WW frame/site. These works were to ensure that the full scheme with planning consent is deliverable in a later phase but also that any holding costs are minimised (and immediate benefits are taken for example, renewables income). This was also Cabinet – 14 March 2023 – CAB/WS/23/014
approved on the basis of at least a break-even income position over the life of the borrowing.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.