Bury St Edmunds Leisure Centre Maintenance and Refurbishment Project: Consultation and Next Steps

Noted Executive 2 papers

Cabinet noted this item on Tuesday 10 December 2024. Below is the council's own wording, with the papers it was decided on.

Item649

Resolved

Recommended to Council: (17 December 2024) That: 1. The outcome of the full public consultation on the proposed Bury St Edmunds leisure centre maintenance and refurbishment project be noted. 2. Following the outcome of the full public consultation on the Bury St Edmunds Leisure Centre, the additional funding (over and above the £6.2m set out in the approved capital programme), as set out in the business case included in the Council report on 16 July 2024 (report COU/WS/24/012) shall be in the sum of £2.16 million, subject to delegated authority being granted to the S151 Officer in consultation with the Portfolio Holder for Leisure and with the Portfolio Holder for Resources, be agreed to allow: a) any further invest to save/earn case being made by Abbeycroft for an increased capital funding element from the Council investing in our Growth Fund. That any increased capital funding be subject to an updated business case and to align with the outcome of the public consultation outcomes set out in this report. b) one off costs associated with the project, such as net income losses during planned centre disruptions and reprovision service costs, be funded from the capital financing reserve.
Word for word from the decision West Suffolk published for this meeting. Source: democracy.westsuffolk.gov.uk

Follow this further

Built from West Suffolk's papers

What the report saysPro

Report to Cabinet

Cabinet – 10 December 2024 – CAB/WS/24/068

Bury St Edmunds Leisure Centre Maintenance and Refurbishment Project: consultation and next steps Report number: CAB/WS/24/068 Report to and dates: Cabinet 10 December 2024

Council 17 December 2024

Cabinet member: Councillor Ian Shipp Portfolio Holder for Leisure Email: [email protected]

Lead officer: Mark Walsh Director (Operations, Leisure and Culture) Telephone: 01284 757300 Email: [email protected]

Decisions Plan: The decision made as a result of this report will usually be published within 48 hours. This item will be referred to Council for a final decision and is, therefore, not subject to call-in. This item is included on the Decisions Plan.

Wards impacted: All Cabinet – 10 December 2024 – CAB/WS/24/068

Recommendation: It is recommended that Cabinet:

1. Notes the outcome of the full public consultation on the proposed Bury St Edmunds leisure centre maintenance and refurbishment project; and

2. Following the outcome of the full public consultation on the Bury St Edmunds Leisure Centre, agrees the additional funding (over and above the £6.2m set out in the approved capital programme) as set out in the business case included in the Council report on 16 July 2024 (report COU/WS/24/012) shall be in the sum of £2.16 million, subject to delegated authority being granted to the S151 Officer in consultation with the Portfolio Holder for Leisure and with the Portfolio Holder for Resources to allow:

a) any further invest to save/earn case being made by Abbeycroft for an increased capital funding element from the Council investing in our Growth Fund. That any increased capital funding be subject to an updated business case and to align with the outcome of the public consultation outcomes set out in this report.

b) one off costs associated with the project, such as net income losses during planned centre disruptions and reprovision service costs, be funded from the capital financing reserve. Cabinet – 10 December 2024 – CAB/WS/24/068

1. Context to this report 1.1 On 16 July 2024, Council considered a report that presented the business case for the Bury St Edmunds leisure centre maintenance and refurbishment project. Report COU/WS/24/012 refers.

1.2The business case set out a proposed plan for addressing the significant maintenance work and delivering key improvements at the centre. The proposed enhancements to the leisure centre are designed to improve the facilities and services offered, making them better matched to the needs of the community. An amendment of the recommendation to Council was agreed to strengthen the consultation approach that had been proposed and set out the Council’s commitment to the level of engagement that was required. This included to engaging with those that don’t currently use the leisure centre.

1.3Now that the public consultation has been concluded, it is clear that those responding want the improvements to happen as soon as possible. It can therefore be considered necessary for the project to proceed in order that the design work can be progressed, the works can be confirmed and scheduled to minimise the impact to users and the cost of delay to the construction works. This will require the agreed level of additional funding of £2.16 million financed by borrowing on an invest to earn/save basis, funded from the financial returns from the uplift in centre performance.

Purpose of this report 1.4 The purpose of this report is to: (a) provide feedback from the public consultation; (b) set out the impact of the consultation feedback on the proposed maintenance and refurbishment project; and (c) provide a figure for the approved additional funding for the project, over and above the £6.2 million capital budget, to allow the refurbishment project to proceed.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Bury St Edmunds Leisure Centre Maintenance and Refurbishment Project: Consultation and Next StepsReport 97 KB DownloadRead as text
PDF
CAB.WS.24.068 Appendix 1 Consultation FeedbackAppendix 1.9 MB Download

At this meeting

Whole meeting

Who was there

9 of 14 attended
CW
Councillor Cliff WatermanLeader, present
VL
Councillor Victor LukaniukDeputy Leader, present
DH
Councillor Donna Higgins (Portfolio Holder for Families and Communities)Committee Member, present
DH
Councillor Diane Hind (Portfolio Holder for Resources)Committee Member, present
GK
Councillor Gerald Kelly (Portfolio Holder for Governance and Regulatory)Committee Member, present
RO
Councillor Richard O'Driscoll (Portfolio Holder for Housing)Committee Member, present
IS
Councillor Ian Shipp (Portfolio Holder for Leisure)Committee Member, present
DT
Councillor David Taylor (Portfolio Holder for Operations)Committee Member, present
JT
Councillor Jim Thorndyke (Portfolio Holder for Planning)Committee Member, present
IW
Councillor Indy Wijenayaka (Portfolio Holder for Growth)Committee Member, apologies
PA
Councillor Peter ArmitageGuest, in attendance
SB
Councillor Sarah BroughtonGuest, in attendance

All 14 on the meeting page

On this subject at West Suffolk

Search all
  1. Bury St Edmunds Leisure Centre Maintenance and Refurbishment Project: Consultation and Next StepsThis decision
  2. Planning Application DC/26/0963/FUL - 9 Short Brackland, Bury St Edmunds (Report No: DEV/WS/26/026)Approved
  3. Planning Application DC/26/0228/ADV -14 Prospect Row, Bury St Edmunds (Report No: DEV/WS/26/019)Refused
  4. Planning Application DC/25/2028/FUL - West Suffolk Council Depot, Olding Road, Bury St Edmunds (Report No DEV/WS/26/013)Approved
  5. Planning Application DC/25/2035/FUL & Listed Building Consent DC/25/2036/LB - St Marys Church, Crown Street, Bury St Edmunds (Report No DEV/WS/26/014)Approved
  6. Planning Application DC/25/1433/FUL - Abbeycroft Leisure Centre, Beetons Way, Bury St Edmunds (Report No: DEV/WS/26/004)Decided

More from West Suffolk Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 Recommendations of the Overview and Scrutiny Committee: 16 July 2026 - Transport and Infrastructure Task and Finish Group RecommendationsThat the approach, set out in Section 2 of Report number CAB/WS/26/038, to assist infrastructure planning and deliver... Approved Open
15 Sep 2026 Recommendations of the Performance and Audit Scrutiny Committee: 23 July 2026 - Treasury Management Report - June 2026Recommended to Council: (13 October 2026) That the Treasury Management Report (June 2026), as set out in Report Numbe... Approved Open
15 Sep 2026 Recommendations of the Performance and Audit Scrutiny Committee: 23 July 2026 - Annual Treasury Management and Financial Resilience Report (2025 to 2026)Recommended to Council: (13 October 2026) That the Annual Treasury Management and Financial Resilience Report 2025 to... Approved Open
15 Sep 2026 Public Space Protection Orders (PSPO): Review of Existing OrdersThat: 1. To continue with the existing Public Space Protection Orders (PSPOs) for Newmarket, Brandon and Moreton Hall... Agreed Open
15 Sep 2026 Planning Advice Service Review: Proposed Improvements and Associated FeesThat: 1. The new planning advice service be agreed. 2. The fee schedule for the new planning advice service, as set o... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies