AI summaryWest Suffolk Cabinet adopts Shepherds Grove Masterplan as informal planning guidance for employment site near Stanton and Hepworth, paving the way for future planning applications.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedSets design framework for allocated employment site
MoneyNo new costsMinor costs from existing budgets
What happens nextFuture planning applications assessed against itBecomes a material consideration
Who it affectsStanton and Hepworth ward residents and businesses. Plus surrounding parishes
What was decided
Cabinet adopted the Shepherds Grove Masterplan as informal planning guidance, as set out in Appendix B to Report CAB/WS/25/053. Report P9
The Masterplan will guide the preparation and determination of future planning applications on the site, which is allocated for employment uses under Policy AP41 of the West Suffolk Local Plan (2025). Report 1.1, 2.2, 2.3
Once adopted, the Masterplan becomes a material consideration in determining future planning applications, alongside the Local Plan and NPPF. Report 2.3, 6.2
Why
Policy AP41 requires planning applications on the allocated site to be determined only after a masterplan is agreed by the local planning authority. Report 3.2
Officers considered the Masterplan had met procedural and engagement standards, demonstrating that Policy AP41 requirements can be achieved through a high-quality design approach. Report 5.2
Adoption is seen as a key stage in bringing forward employment generation and business growth for the district, with risk of failing to deliver development on the allocated rural site if not adopted. Report 5.3
What happens next
The Masterplan will be used as a material consideration in determining future planning applications and reserved matters submissions on the site. Report 6.2, P123
A planning application, supported by documents such as a Flood Risk Assessment, Construction Management Plan, Travel Plan and BNG Phasing Plan, is expected to follow. Report 4.18, 4.22, 4.24, P100, P104, P105
No buildings may be occupied until the new A143 roundabout and access road are completed. Report 4.18, P103
Options considered
Chosen: Adopt the Shepherds Grove Masterplan as informal planning guidance. Required by Policy AP41 and considered procedurally and policy compliant Report P9
Rejected: Consider other development options for the site. Policy AP41 requires a masterplan to be in place before applications are determined Report 3.2
Implications
Legal: No legal implications from adoption; Masterplan becomes a material consideration in determining future planning applications. Report P122, P123
Financial: Minor costs of adoption can be sourced from existing budgets. Report P121
Risk: Failure to adopt could inhibit the Council's ability to deliver employment development on the allocated rural site.
Who and where
Stanton and Hepworth ward residents (Stanton Barningham ward) Report P8
Parish Councils of Stanton, Hepworth, Walsham le Willows, Bardwell and Badwell Ash Report 4.7, P31, P32, P33, P34, P35, P36
Local businesses and 1,500 residences and businesses in Stanton and Hepworth receiving newsletters Report P27
Developer/promoter Jaynic preparing planning applications on the site Report 1.4, 4.4
Future end-user businesses and employees at the employment site Report 4.20, P69
Timeline
27 June 2025: Portfolio Holder for Growth agreed the draft Masterplan could go out for public consultation Report 1.2
27 June 2025 to 12 August 2025: Six week public consultation on the draft Masterplan Report 1.3, 4.2
4 November 2025: Cabinet adopted the Shepherds Grove Masterplan as informal planning guidance Report P2
Plain English for the jargon
Informal planning guidance: A document adopted by the local planning authority that is a material consideration in deciding planning applications, but is not part of the statutory development plan.
Policy AP41: Allocation in the West Suffolk Local Plan (2025) designating Shepherds Grove for employment uses, requiring a masterplan before planning applications are determined.
Biodiversity Net Gain (BNG): A development requirement to deliver a measured improvement in biodiversity, with a minimum 10% increase set in policy.
NPPF: National Planning Policy Framework, the national planning policy document for England.
LLFA: Lead Local Flood Authority, in this case Suffolk County Council, responsible for surface water flood risk management.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item752
Resolved
That the Shepherds Grove Masterplan be adopted as informal planning guidance, as set out in Appendix B to Report number CAB/WS/25/053. That the be adopted as informal planning guidance, as set out in Appendix B to Report number CAB/WS/25/053.
Word for word from the decision West Suffolk published for this meeting.Source: democracy.westsuffolk.gov.uk
Decisions Plan: The decision made as a result of this report will usually be published within 48 hours and cannot be actioned until five clear working days of the publication of the decision have elapsed. This item is included on the Decisions Plan.
Wards impacted: Stanton Barningham (Hepworth)
Recommendation: It is recommended that Cabinet adopt the Shepherds Grove Masterplan as informal planning guidance, as set out in Appendix B to Report number CAB/WS/25/053. Cabinet – 4 November 2025 – CAB/WS/25/053
1. Context to this report The site
1.1The site is allocated for employment uses in the West Suffolk Local Plan (2025) as Policy AP41. The site was previously allocated for employment uses as Policy RV14 of the Rural Vision (2014). The allocation allows for a range of uses to include offices, research and development, light industrial, general industrial and storage and distribution. A site location plan is attached as Appendix A to this report.
1.2On 27 June 2025 the Portfolio Holder for Growth acting under delegated powers from Cabinet agreed that the draft Shepherds Grove Masterplan could go out for public consultation.
1.3The consultation was held between the 27th June and the 12th August 2025.
1.4Following on from the public consultation, all comments from the Parish Council, statutory consultees and residents were collated and then considered by the developer/promoter Jaynic and Officers. The Masterplan has been further amended accordingly. The main changes and updates to the Masterplan are set out within section 4 of this report.
1.5The final version of the draft Masterplan is included as Appendix B to this report.
2. Proposals within this report 2.1 The masterplan sets out a ‘vision’ for the development of Shepherds Grove, and has been prepared to accord with LP10 ‘Masterplans’ of the West Suffolk Local Plan (2025). The requirements of a Masterplan are set out in Appendix D of the Local Plan.
2.2The Masterplan provides a design framework aligned with the adopted Local Plan and will guide the preparation and determination of future planning applications for this site. However, this document is not designed to be prescriptive. It is intended to demonstrate how the policy requirements of can be satisfactorily achieved spatially on the site. It is not the role of this document to test delivery.
2.3Once approved and adopted as Informal Planning Guidance, the Masterplan will constitute a material consideration in the determination of future planning applications but should also be read in conjunction with the policies of the West Suffolk Local Plan and the NPPF. Cabinet – 4 November 2025 – CAB/WS/25/053
3. Alternative options that have been considered 3.1 Policy Allocation AP41 states that applications for planning permission will only be determined once the masterplan has been agreed by the local planning authority. The masterplan will be prepared by the site promoters and be subject to public engagement with the local community and key stakeholders in accordance with the statement of community involvement.
3.2In order to ensure that a comprehensive and policy compliant development comes forward on this allocated site it is necessary for a Masterplan to be prepared and adopted as informal planning guidance, therefore other options regarding the potential development of the site have not been considered as part of this process.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.