CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
West Yorkshire Combined Authority
West Yorkshire Combined Authority, Thursday 5 April 2018

Capital Spending and Project Approvals

Approved Committee 1 paper

West Yorkshire Combined Authority approved this item on Thursday 5 April 2018. Below is the council's own wording, with the papers it was decided on.

Item107

Resolved

( i ) In respect of Rail Park and Ride Programme – Garforth Rail Station Car Park Project (decision point 2 –case paper) – That following a recommendation from the Investment Committee, the Combined Authority approves: (a) That the Garforth Station Car Park project proceeds through decision point 2 and work commences on activity 5 (full business case with finalised costs). (b) That an indicative approval to the total project value of £825,000 is given from the Transport Fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business cases with finalised costs). (c) That development costs of £45,000 are approved in order to progress the scheme to decision point 5 (full business case with finalised costs), taking the total project approval to £59,000. (d) That the Combined Authority enter into a funding agreement (Section 56) with Arriva Rail North for expenditure of up to £45,000 from the Transport Fund. (e) That future approvals are made in accordance with the approval pathway and approval route outlined in the submitted report including at decision point 5 (full business case with finalised costs) through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the submitted report. (ii) In respect of Apprenticeship Grants for Employers (AGE) Extension (decision point 2 case paper) – That following a recommendation from the Investment Committee the Combined Authority approves: (a) That the AGE Extension Programme proceeds through decision point 2 and work commences on activity 5 (full business case with finalised costs). (b) That an indicative approval to the total grant fund value of £1.2million is given to be funded from the unallocated AGE Programme 2015-2017 funds with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full businesss case with finalised costs). (c) That future approvals are made in accordance with the approval pathway and approval route outlined in the submitted report including at decision point 5 (full business case with finalised costs) through a delegation to the Combined Authority’s Managing Director following recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the submitted report. (iii) In respect of North East Calderdale Transformational Programme study (decision point 2 case paper) – That following a recommendation from the Investment Committee, the Combined Authority approves: (a) That the North East Calderdale Transformational Programme study proceeds through decision point 2 (case paper) and work commences on the strategic case for the programme . (b) That full approval is given for the total study costs of £400,000. (c) That the Combined Authority enters into a funding agreement with Calderdale Council for expenditure of up to £400,000 to be funded from the Transport Fund. (d) That any change requests relating to the study are ... (i) In respect of Rail Park and Ride Programme – Garforth Rail Station Car Park Project (decision point 2 –case paper) – That following a recommendation from the Investment Committee, the Combined Authority approves: (a) That the Garforth Station Car Park project proceeds through decision point 2 and work commences on activity 5 (full business case with finalised costs). (b) That an indicative approval to the total project value of £825,000 is given from the Transport Fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs). (c) That development costs of £45,000 are approved in order to progress the scheme to decision point 5 (full business case with finalised costs), taking the total project approval to £59,000. (d) That the Combined Authority enter into a funding agreement (Section 56) with Arriva Rail North for expenditure of up to £45,000 from the Transport Fund. (e) That future approvals are made in accordance with the approval pathway and approval route outlined in the submitted report including at decision point 5 (full business case with finalised costs) through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the submitted report. (ii) In respect of Apprenticeship Grants for Employers (AGE) Extension (decision point 2 case paper) – That following a recommendation from the Investment Committee the Combined Authority approves: (a) That the AGE Extension Programme proceeds through decision point 2 and work commences on activity 5 (full business case with finalised costs). (b) That an indicative approval to the total grant fund value of £1.2 million is given to be funded from the unallocated AGE Programme 2015-2017 funds with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full businesss case with finalised costs). (c) That future approvals are made in accordance with the approval ... view the full minutes text for item 107.
Word for word from the decision West Yorkshire Combined Authority published for this meeting. Source: westyorkshire.moderngov.co.uk

Follow this further

Built from West Yorkshire Combined Authority's papers

What the report saysPro

Report to West Yorkshire Combined Authority
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Spending and Project ApprovalsReport 501 KB Copy on its way

At this meeting

Whole meeting

On this subject at West Yorkshire Combined Authority

Search all
  1. Capital Spending and Project ApprovalsThis decision
  2. Capital Spending and Project ApprovalsApproved
  3. Capital Spending and Project ApprovalsDecided
  4. Capital Spending and Project ApprovalsApproved
  5. Capital Spending and Project ApprovalsApproved
  6. Capital Spending and Project ApprovalsApproved

More from West Yorkshire Combined Authority West Yorkshire Combined Authority

All decisions
MeetingDecisionOutcome
18 Sep 2025 Bus Franchising Update– That the Combined Authority: 1. Noted and endorsed the strategic approach to developing network service specificati... Noted Open
18 Sep 2025 Mass Transit Programme– That the Combined Authority: 1. Noted progress and the current position of the West Yorkshire Mass Transit programm... Noted Open
18 Sep 2025 West Yorkshire Local Nature Recovery Strategy– That the Combined Authority: 1. Noted the engagement and strategy development work undertaken in collaboration with... Noted Open
18 Sep 2025 West Yorkshire Local Remediation Acceleration Plan– That the Combined Authority: 1. Adopted the West Yorkshire Local Remediation Acceleration Plan as set out in Append... Approved Open
18 Sep 2025 Cluster Action Plans– That the Combined Authority: 1. Approved the six Cluster Action Plans developed to accelerate growth across West Yo... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies