Capital Spending and Project Approvals

Approved Committee 6 papers

ARCHIVED - West Yorkshire and York Investment Committee approved this item on Wednesday 4 December 2019. Below is the council's own wording, with the papers it was decided on.

Item37

Resolved

(i) That in respect of the Bradford Interchange Carriageway Works the Investment Committee recommends to the Combined Authority: (a) That the Bradford Interchange Carriageway Works proceeds through decision point 2 and work commences on Activity 4 (full business case) (b) That an indicative approval to the total project value of £2 million is given from the Local Transport Plan - Integrated Transport Block with full approval to spend being granted once the scheme has progressed through the Assurance Process to Decision Point 5 . (c) That development costs of £461,400 are approved in order to progress the scheme to Decision Point 5. (d) That the Combined Authority enter into a Funding Agreement with City of Bradford Metropolitan District Council for expenditure up to £300,000. (e) That future approvals are made in accordance with the assurance pathway and approval route outlined in this report including at decision point 6 through a delegation to the Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in this report. (ii) That in respect of the ERDF Connecting Innovation project the Investment Committee recommends to the Combined Authority: (a) That the ERDF Connecting Innovation project proceeds through decision point 2 and work commences on Activity 5 (full business case plus) (b) That an indicative approval of £2,779,846 is given, comprised of £750,961 from the Access to Capital Grants element of the Local Growth Fund and £2,028,885 from the European Regional Development Fund, with full approval to spend being granted once the scheme has progressed through the Assurance Process to Decision Point 5. The total project costs are £4,057,771 million, with Small Medium Enterprise match funding of £1,277,925 million. (c) That future approvals are made in accordance with the assurance pathway and approval route outlined in this report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in this report. (iii) That in respect of the Leeds Public Transport Improvement Programme Leeds Bus Station Gateway project the Investment Committee recommends to the Combined Authority that: (a) That the Leeds Public Transport Improvement Programme Leeds Bus Station Gateway project proceeds through decision point 3 (outline business case) and work commences on activity 5 (full business case with finalised costs) (b) That an indicative approval to the total project value of £4.984 million is given from the Leeds Public Transport Investment Programme fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs. (c) That development costs of £350,000 are approved in order to progress the scheme to Decision Point 5. (d) That the Combined Authority enters into a variation to the Funding Agreement with Leeds City Council for release of expenditure of £350,000 from the LPTIP Fund for further ...
Word for word from the decision West Yorkshire Combined Authority published for this meeting. Source: westyorkshire.moderngov.co.uk

Follow this further

Built from West Yorkshire Combined Authority's papers

What the report saysPro

Report to ARCHIVED - West Yorkshire and York Investment Committee
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Spending and Project ApprovalsReport 358 KB Copy on its way
PDF
Item 6: Appendix 1Appendix 138 KB Copy on its way
PDF
Item 6: Appendix 2: BC Summary: Bradford Interchange Carriageway WorksAppendix 185 KB Copy on its way
PDF
Item 6: Appendix 3: BC Summary: Connecting InnovationAppendix 43 KB Copy on its way
PDF
Item 6: Appendix 4: BC Summary: Leeds Bus Station GatewayAppendix 284 KB Copy on its way
PDF
Item 6: Appendix 5: BC Summary: A58 Beckett Street: York StreetAppendix 287 KB Copy on its way

At this meeting

Whole meeting

On this subject at West Yorkshire Combined Authority

Search all
  1. Capital Spending and Project ApprovalsThis decision
  2. Capital Spending and Project ApprovalsApproved
  3. Capital Spending and Project ApprovalsDecided
  4. Capital Spending and Project ApprovalsApproved
  5. Capital Spending and Project ApprovalsApproved
  6. Capital Spending and Project ApprovalsApproved

More from West Yorkshire Combined Authority ARCHIVED - West Yorkshire and York Investment Committee

All decisions
MeetingDecisionOutcome
8 Jun 2021 Capital Programme Update(i) That the Investment Committee progress made in implementing the Combined Authority Capital Programmes be noted: (... Noted Open
8 Jun 2021 Transforming Cities Fund Programme Review(i) That the progress made in the delivery of the TCF programme, in particular the key messages presented on mileston... Noted Open
8 Jun 2021 Capital Spending and Project Approvals(i) In respect of the Net Zero Region Accelerator the Investment Committee approved that: (a) The Net Zero Region Acc... Approved Open
8 Jun 2021 Entrepreneurship Package of Support(i) In respect of the Entrepreneurship Package of Support the Investment Committee approved that: (a) The Entrepreneu... Approved Open
8 Jun 2021 Transforming Cities Fund: Harrogate Railway Station Gateway - Active Travel Improvement Scheme(i) That in respect of the TCF: Harrogate Railway Station Gateway – Active Travel Improvement Scheme the Investment C... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies