Resolved
In respect of LCCP Infirmary Street - That following a recommendation from the Investment Committee, the Combined Authority approves: (a) That the Infirmary Street Gateway scheme proceeds through decision point 4 and work commences on activity 5 (full business case with finalised costs). (b) That an indicative approval to the total project value of £8.90 million is given from the West Yorkshire plus Transport Fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs). (c) That future approvals are made in accordance with the Assurance pathway and Approval route outlined in the submitted report including at decision point 5 through a delegation to the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.
Word for word from the decision West Yorkshire Combined Authority published for this meeting.