West Yorkshire Combined Authority, Thursday 9 January 2020

Capital Spending and Project Approvals

Approved Committee 3 papers

West Yorkshire Combined Authority approved this item on Thursday 9 January 2020. Below is the council's own wording, with the papers it was decided on.

Item55

Resolved

(a) In respect of Leeds Transport Model Update 2020 - That following a recommendation from the Investment Committee, the Combined Authority approves: (i) That the Leeds Transport Model Update 2020 project proceeds through Decision Point 2 and work commences on Activity 5 (full business case with finalised costs). (ii) That an indicative approval of £600,000 is given from the West Yorkshire plus Transport Fund towards a total scheme cost of £1.2 million with full approval to spend being granted once the scheme has progressed through the assurance process to Decision Point 5. (iii) That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at Decision Point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the submitted report. (b) In respect of Leeds City Region Skills for Growth – That following a recommendation from the Investment Committee, the Combined Authority approves: ( i ) That the Leeds City Region Skills for Growth programme proceeds through decision point 2 and work commences on activity 5 (full business case with finalised costs) (ii) That an indicative approval to the Combined Authority’s contribution of £2.429 million (which will be funded through £1.464 million from the ESIF fund and £964,925 from the Local Skills Fund is given with full approval to spend being granted once the outcome of the ESIF bid is known and the scheme has progressed through the assurance process to decision point 5. The total project value is £2.929 million with the remaining £500,000 to be raised from business sponsorship. (iii) That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report. (c) In respect of Bradford Interchange Carriageway Works - That following a recommendation from the Investment Committee, the Combined Authority approves: ( i ) That the Bradford Interchange Carriageway Works proceeds through decision point 2 and work commences on Activity 4 (full business case) (ii) That an indicative approval to the total project value of £2 million is given from the Local Transport Plan - Integrated Transport Block with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5. (iii) That development costs of £461,400 are approved in order to progress the scheme to decision point 5. (iv) That the Combined Authority enter into a Funding Agreement with City of Bradford Metropolitan District Council for expenditure up to £300,000. (v) That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 5 through a ... (a) In respect of Leeds Transport Model Update 2020 - That following a recommendation from the Investment Committee, the Combined Authority approves: (i) That the Leeds Transport Model Update 2020 project proceeds through Decision Point 2 and work commences on Activity 5 (full business case with finalised costs). (ii) That an indicative approval of £600,000 is given from the West Yorkshire plus Transport Fund towards a total scheme cost of £1.2 million with full approval to spend being granted once the scheme has progressed through the assurance process to Decision Point 5. (iii) That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at Decision Point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the submitted report. (b) In respect of Leeds City Region Skills for Growth – That following a recommendation from the Investment Committee, the Combined Authority approves: ( i ) That the Leeds City Region Skills for Growth programme proceeds through decision point 2 and work commences on activity 5 (full business case with finalised costs). (ii) That an indicative approval to the Combined Authority’s contribution of £2.429 million (which will be funded through £1.464 million from the ESIF fund and £964,925 from the Local Skills Fund is given with full approval to spend being granted once the outcome of the ESIF bid is known and the scheme has progressed through the assurance process to decision point 5. The total project value is £2.929 million with the remaining £500,000 to be raised from business sponsorship. (iii) That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal ... view the full minutes text for item 55.
Word for word from the decision West Yorkshire Combined Authority published for this meeting. Source: westyorkshire.moderngov.co.uk

Follow this further

Built from West Yorkshire Combined Authority's papers

What the report saysPro

Report to West Yorkshire Combined Authority
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Spending and Project ApprovalsReport 368 KB Copy on its way
PDF
Item 5: Appendix 2Appendix 100 KB Copy on its way
PDF
Item 5: Appendix 3Appendix 7 MB Copy on its way

At this meeting

Whole meeting

On this subject at West Yorkshire Combined Authority

Search all
  1. Capital Spending and Project ApprovalsThis decision
  2. Capital Spending and Project ApprovalsApproved
  3. Capital Spending and Project ApprovalsDecided
  4. Capital Spending and Project ApprovalsApproved
  5. Capital Spending and Project ApprovalsApproved
  6. Capital Spending and Project ApprovalsApproved

More from West Yorkshire Combined Authority West Yorkshire Combined Authority

All decisions
MeetingDecisionOutcome
18 Sep 2025 Bus Franchising Update– That the Combined Authority: 1. Noted and endorsed the strategic approach to developing network service specificati... Noted Open
18 Sep 2025 Mass Transit Programme– That the Combined Authority: 1. Noted progress and the current position of the West Yorkshire Mass Transit programm... Noted Open
18 Sep 2025 West Yorkshire Local Nature Recovery Strategy– That the Combined Authority: 1. Noted the engagement and strategy development work undertaken in collaboration with... Noted Open
18 Sep 2025 West Yorkshire Local Remediation Acceleration Plan– That the Combined Authority: 1. Adopted the West Yorkshire Local Remediation Acceleration Plan as set out in Append... Approved Open
18 Sep 2025 Cluster Action Plans– That the Combined Authority: 1. Approved the six Cluster Action Plans developed to accelerate growth across West Yo... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies