Item48

Resolved

(a) In respect of Highways Maintenance Challenge Fund allocation 2020/21 – (i) That the expenditure of the DfT Highways Maintenance Challenge Fund grant totalling £3.334 million be approved. (ii) That the allocations of the DfT Highways Maintenance Challenge Fund grant of £1,075,329 to Bradford, £1,514,155 to Leeds and £744,209 to Wakefield, totalling £3.334 million be approved and that allocations are paid quarterly to partner councils. (b) In respect of Huddersfield Stations Gateway package - Preparing for Transpennine Route Upgrade (TRU) at Huddersfield and opening up employment sites – That following a recommendation from the Investment Committee, the Combined Authority approves: (i) That the Huddersfield Stations Gateway package proceeds through Decision Point 2 and work commences on Activity 3 (outline business case). (ii) That an indicative approval to the Combined Authority contribution of £28 million from the Transforming Cities Fund, with full approval to spend once the package has progressed through the assurance process to decision point 5 (full business case plus finalised costs). Total project costs are £42 million (£28 million TCF, £10 million WY+TF and £4 million from Kirklees Council’s Kirklees Town Centre Capital fund). (iii) That development costs of £0.1 million are approved, to progress the scheme to decision point 3 (outline business case), taking the total approval to £0.916 million. (iv) That the Combined Authority issue an addendum to the existing Funding Agreement with Kirklees Council for expenditure of up to £0.916 million from the Transforming Cities Fund. (v) That future approvals are made in accordance with the approval pathway and approval route outlined in the submitted report, which will be subject to the scheme remaining within the tolerances outlined in the report. (c) In respect of Halifax, Walking Cycling and Bus Transformation Package - North Halifax Cycle Super Highways, Park Ward Streets for People, Bus Priority – That following a recommendation from the Investment Committee, the Combined Authority approves: (i) That the Halifax Walking, Cycling, Rail and Bus Transformation package proceeds through decision point 2 and work commences on Activity 3 (outline business case) for individual schemes. (ii) That an indicative approval to the Combined Authority contribution of £53.9 million from the Transforming Cities Fund, with full approval to spend once the package has progressed through the assurance process to decision point 5 (full business case plus finalised costs). Total project costs are £71.805 million (£53.9 million TCF, £16.5 million WY+TF, £0.405 million CMBC and £1 million LTP for Park Ward Streets for People. (iii) That an indicative approval to the total package value of £53.9 million is given from the Transforming Cities Fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5. (iv) That future approvals are made in accordance with the approval pathway and approval route outlined in the submitted report, which will be subject to the scheme remaining within the tolerances outlined in the report. (d) In respect of Active and Sustainable Travel in Wakefield City Centre – That following a ... (a) In respect of Highways Maintenance Challenge Fund allocation 2020/21 – ( i ) That the expenditure of the DfT Highways Maintenance Challenge Fund grant totalling £3.334 million be approved. (ii) That the allocations of the DfT Highways Maintenance Challenge Fund grant of £1,075,329 to Bradford, £1,514,155 to Leeds and £744,209 to Wakefield, totalling £3.334 million be approved and that allocations are paid quarterly to partner councils. (b) In respect of Huddersfield Stations Gateway package - Preparing for Transpennine Route Upgrade (TRU) at Huddersfield and opening up employment sites – That following a recommendation from the Investment Committee, the Combined Authority approves: (i) That the Huddersfield Stations Gateway package proceeds through Decision Point 2 and work commences on Activity 3 (outline business case). (ii) That an indicative approval to the Combined Authority contribution of £28 million ... view the full minutes text for item 48.
Word for word from the decision West Yorkshire Combined Authority published for this meeting. Source: westyorkshire.moderngov.co.uk

Follow this further

Built from West Yorkshire Combined Authority's papers

What the report saysPro

Report to West Yorkshire Combined Authority
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Spending and Project ApprovalsReport 778 KB Copy on its way
PDF
Item 6: Appendix 1Appendix 138 KB Copy on its way
PDF
Item 6: Appendix 2Appendix 2 MB Copy on its way

At this meeting

Whole meeting

On this subject at West Yorkshire Combined Authority

Search all
  1. Capital Spending and Project ApprovalsThis decision
  2. Capital Spending and Project ApprovalsApproved
  3. Capital Spending and Project ApprovalsDecided
  4. Capital Spending and Project ApprovalsApproved
  5. Capital Spending and Project ApprovalsApproved
  6. Capital Spending and Project ApprovalsApproved

More from West Yorkshire Combined Authority West Yorkshire Combined Authority

All decisions
MeetingDecisionOutcome
18 Sep 2025 Bus Franchising Update– That the Combined Authority: 1. Noted and endorsed the strategic approach to developing network service specificati... Noted Open
18 Sep 2025 Mass Transit Programme– That the Combined Authority: 1. Noted progress and the current position of the West Yorkshire Mass Transit programm... Noted Open
18 Sep 2025 West Yorkshire Local Nature Recovery Strategy– That the Combined Authority: 1. Noted the engagement and strategy development work undertaken in collaboration with... Noted Open
18 Sep 2025 West Yorkshire Local Remediation Acceleration Plan– That the Combined Authority: 1. Adopted the West Yorkshire Local Remediation Acceleration Plan as set out in Append... Approved Open
18 Sep 2025 Cluster Action Plans– That the Combined Authority: 1. Approved the six Cluster Action Plans developed to accelerate growth across West Yo... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies