West Yorkshire Combined Authority, Thursday 29 July 2021

Capital Spending & Project Approvals

Approved Committee 7 papers

West Yorkshire Combined Authority approved this item on Thursday 29 July 2021. Below is the council's own wording, with the papers it was decided on.

Item30

Resolved

(a) That in respect of the Clifton (Calderdale) Enterprise Zone Business Rates Receipt, the Combined Authority approves that, subject to the conditions in the submitted report, Calderdale Council retains future business rates income generated from the Clifton Enterprise Zone (up to March 2042). (b) That in respect of the British Library for the North (Temple Works), the Combined Authority approves: ( i ) That the British Library for the North (Temple Works) scheme proceeds through decision point 2 (strategic outline case) and work commences on activity 3 (outline business case). (ii) That an indicative approval of £25 million (to be funded through the Combined Authority’s devolution deal) is given. The total forecast scheme value is £69.810 million. (iii) That approval of £5.35 million development costs to progress the scheme to decision point 3 (outline business case) be given. (iv) That the Combined Authority enters into a funding agreement with Leeds City Council for expenditure of up to £5 million from the Combined Authority’s devolution deal. (v) That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report. This will be subject to the scheme remaining within the tolerances outlined in the report. (c) That in respect of the TCF Network Navigation, the Combined Authority approves : ( i ) That the TCF Network Navigation project proceeds through decision point 3 (outline business case) and work commences on activity 4 (full business case) (ii) That an indicative approval to the total project value of £15.500 million, comprising of £15.200 million from the Transforming Cities Fund, and £0.300 million from Local Transport Plan Integrated Transport Block, is given. (iii) That development costs of £0.200 million are approved to progress the scheme to decision point 4 (full business case) taking the total scheme approval to £0.360 million. (iv) That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report. This will be subject to the scheme remaining within the tolerances outlined in the report. (d) That in respect of the CityConnect Phase 3 Canals - Leeds Liverpool Shipley, the Combined Authority approves, subject to the conditions set by PAT stated in the submitted report: ( i ) That the CityConnect Phase 3 Canals - Leeds Liverpool Shipley scheme proceeds through decision point 4 (full business case) and work commences on activity 5 (Delivery). (ii) That approval to the Combined Authority’s contribution of £1.981 million which will be funded from West Yorkshire plus Transport Fund (£1.057 million), Getting Building Fund (£0.500 million) and £0.424 million yet to be secured is given. The total scheme value is £1.981 million. (iii) That the Combined Authority enters into an addendum to the existing funding agreement with the Canal and River Trust for expenditure of up to £1.981 million. (iv) That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report. This will be subject to the scheme remaining within the tolerances outlined ... (a) That in respect of the Clifton (Calderdale) Enterprise Zone Business Rates Receipt, the Combined Authority approves that, subject to the conditions in the submitted report, Calderdale Council retains future business rates income generated from the Clifton Enterprise Zone (up to March 2042). (b) That in respect of the British Library for the North (Temple Works), the Combined Authority approves: (i) That the British Library for the North (Temple Works) scheme proceeds through decision point 2 (strategic outline case) and work commences on activity 3 (outline business case). (ii) That an indicative approval of £25 million (to be funded through the Combined Authority’s devolution deal) is given. The total forecast scheme value is £69.810 million. (iii) That approval ... view the full minutes text for item 30.
Word for word from the decision West Yorkshire Combined Authority published for this meeting. Source: westyorkshire.moderngov.co.uk

Follow this further

Built from West Yorkshire Combined Authority's papers

What the report saysPro

Report to West Yorkshire Combined Authority
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Spending & Project ApprovalsReport 832 KB Copy on its way
PDF
Item 9: Appendix 1: Assurance FrameworkAppendix 226 KB Copy on its way
PDF
Item 9: Appendix 2: British Library North (Temple Works): Business Case SummaryAppendix 407 KB Copy on its way
PDF
Item 9: Appendix 3: TCF Network Navigation: Business Case SummaryAppendix 131 KB Copy on its way
PDF
Item 9: Appendix 4: Leeds Liverpool Canal: Business Case SummaryAppendix 413 KB Copy on its way
PDF
Item 9: Appendix 6: Halifax Bus Station: Business Case SummaryAppendix 538 KB Copy on its way
PDF
item 9: Appendix 5: Huddersfield Narrow Canal: Business Case SummaryAppendix 406 KB Copy on its way

At this meeting

Whole meeting

On this subject at West Yorkshire Combined Authority

Search all
  1. Capital Spending & Project ApprovalsThis decision
  2. Capital Spending and Project ApprovalsApproved
  3. Capital Spending and Project ApprovalsDecided
  4. Capital Spending and Project ApprovalsApproved
  5. Capital Spending and Project ApprovalsApproved
  6. Capital Spending and Project ApprovalsApproved

More from West Yorkshire Combined Authority West Yorkshire Combined Authority

All decisions
MeetingDecisionOutcome
18 Sep 2025 Bus Franchising Update– That the Combined Authority: 1. Noted and endorsed the strategic approach to developing network service specificati... Noted Open
18 Sep 2025 Mass Transit Programme– That the Combined Authority: 1. Noted progress and the current position of the West Yorkshire Mass Transit programm... Noted Open
18 Sep 2025 West Yorkshire Local Nature Recovery Strategy– That the Combined Authority: 1. Noted the engagement and strategy development work undertaken in collaboration with... Noted Open
18 Sep 2025 West Yorkshire Local Remediation Acceleration Plan– That the Combined Authority: 1. Adopted the West Yorkshire Local Remediation Acceleration Plan as set out in Append... Approved Open
18 Sep 2025 Cluster Action Plans– That the Combined Authority: 1. Approved the six Cluster Action Plans developed to accelerate growth across West Yo... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies