Resolved
The Committee:- (1) notes the performance and progress of the Council’s waste collection and disposal programme; and (2) thanks the Officers for ... view the full minutes text for item 26.
All: Place and Environment Scrutiny Committee decided this item on Wednesday 25 September 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee:- (1) notes the performance and progress of the Council’s waste collection and disposal programme; and (2) thanks the Officers for ... view the full minutes text for item 26.
Waste Collection and Disposal
Update for Scrutiny Committee What are we committed to? • OJEU Procurement of new waste treatment and disposal solution and HWRC management - contracts to start 1 April 2015 • Drive up local household waste recycling rates - 45% by 2015 and 50% by 2020 • Achieve £14 million cost avoidance for council by reducing amount of waste to landfill, which will cut treatment and disposal costs • Drive up efficiency and customer satisfaction in waste collection service and achieve service aim: - ‘Empty every bin that’s presented correctly on the normal day of collection’
Confident Place, Confident People. Recycling roll-outs •Roll out completed •New collection service embedded •Significant increase in recycling and composting •36.1% in 11/12 • 48.5% in 12/13 •Ahead of our 2015 target of 45% •Landfilled waste reduced from 51% to 17% •7.63% reduction in total waste collected per person (6216 tonnes less waste)
Confident Place, Confident People. Waste Procurement
• Residual treatment/transfer station/HWRCs – Procurement progressing well. – Currently in final stage of dialogue prior to submission of final tenders in December. – Two bidders remaining Viridor and FCC (current contractor-formerly WRG). – On track for selection of Preferred Bidder in March 2014. – This will then give us 12 months prior to contract commencement for mobilisation to allow smooth transition into the new contract in 2015.
Confident Place, Confident People. Waste Procurement
• Organics (green bin) solution – Change of direction to ensure the solution remains within affordability and can deliver technically. – The Authority is now going to build the organics transfer station ourselves on Makerfield Way for our green bin collection vehicles to tip at. – Let a separate contract for collection and composting of the green bin waste (during 2014). – Currently producing the site design with planning application by the end of 2013. – Anticipate build to start March 2014-allows 12 months
Confident Place, Confident People. Risks around procurement • Buy back of Kirkless • Consultation/communication for waste transfer station build • Contractual delays • Cost of future provision
Confident Place, Confident People. Waste Collection • Managed weekly collections for 12 months • Rounds realigned with contingency support • Rural round brought in line with domestic rounds • Implementation of “non return” policy • Vehicle fleet reduced from 46 to 41 • 23 vehicles replaced • IT – Kirona in-cab and CRM – integrated paperless system for crews, contact centre and back office. Confident Place, Confident People. In-Cab Mobile system Property Issues Dashboard
Confident Place, Confident People. In-Cab Mobile system Job Ticket Dashboard
Confident Place, Confident People. In-Cab Mobile system Digital Round Maps
Confident Place, Confident People. Waste Collection Performance – On average, we collect 99.9% of bins each day – Improved data being collected at the end of the day – analysis and action, moving to fully electronic – % Round non-completion improved from an average of 35 per week to 1 – Results displayed to workforce – Process of dealing with non completed rounds and jobs has been revised – Complaints/service failure investigation process
Confident Place, Confident People. Waste Collection • Staffing & Workforce issues – Cleansing and Waste Collection restructure – Area based supervision – Cross service working and multiskilling
• Communication – Improved links with Customer Team, providing information on return dates for daily non collections – Weekly team meetings with Supervisory team established – Regular union contact established – Notice Boards to display information to crews and seek feedback – Workforce cluster groups to help shape future service
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Waste Programme: modernisation and commissioning of waste management:Report | 137 KB | DownloadRead as text |
Follow All: Place and Environment Scrutiny Committee at Wigan and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Sep 2026 | Whipping DeclarationsThere were no declarations | Decided | Open |
| 9 Sep 2026 | Executive's Forward Plan of Key and Non-Key DecisionsThe Committee notes the forthcoming decisions, with no items being requested to be placed on a future agenda of the C... | Decided | Open |
| 9 Sep 2026 | Scoping Report - 'The Restoration of Haigh Hall'The Committee:- (1) directs the Task and Finish Group to undertake further scoping work and resubmit the proposal for... | Decided | Open |
| 9 Sep 2026 | Highways Asset Management Annual ReportThe Committee:- (1) thanks the officer for their report; and (2) notes the content of the report. | Decided | Open |
| 9 Sep 2026 | Flood Risk and Resilience UpdateThe Committee:- (1) thanks the officers for their report; and (2) notes the content of the report. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.