Resolved
The Committee endorses the proposals as outlined within the report.
All: Place and Environment Scrutiny Committee decided this item on Wednesday 26 July 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee endorses the proposals as outlined within the report.
THIS IS AN OPEN REPORT
Report to: Confident Places Scrutiny Committee
Date of Meeting(s): 26 July 2017
Subject: Town Centre Cycle Schemes Programme
Report of: Karl Battersby, Director Economy and Environment
Contact Officer: Emma Barton (ext. 89501)
Cabinet Portfolio Holder Councillor David Molyneux, Portfolio Holder for and area: Economic Development and Regeneration
Summary: The purpose of the report is to provide Scrutiny Committee members with information about the proposed Wigan town centre cycle schemes programme and to invite feedback and comments on the proposals prior to seeking Portfolio approval to proceed.
Link to Corporate Priorities: Confident Places Improving economic and social opportunities; An attractive, accessible and lively borough, with a prosperous economy as the location of choice for investment.
Confident People Protecting vulnerable groups and enhancing self-reliance, improving life opportunities and independence for everyone to start well, live well and age well; Particularly for those most dependent on public services.
Confident Council Your Council has re-focused its reduced resources towards early intervention and prevention to achieve more for less – integrating public services around whole life issues to build self-reliance and maximising community assets.
Wards Affected: Wigan Central, Douglas, Pemberton, and Worsley Mesnes
Recommendation(s): Members are asked to consider the proposals described in the report, endorse the recommendations and provide comments and feedback to help shape the plans going forward.
Implications: There are a number of existing cycle links within and around Wigan town centre but these are currently fragmented. Having a fully joined-up network of cycle links will encourage greater use of the network by fully connecting residents and visitors alike with their destination, increasing footfall into the town centre and supporting the local economy to grow.
What are the financial implications? The council has secured external funding from Cycle City Ambition Grant (£2.1m) and Growth Deal (£1.02m) to deliver the proposed town centre cycle schemes programme. This funding will cover staffing costs / fees and all capital / infrastructure requirements to support delivery of the programme, however the council will become responsible for the ongoing upkeep and maintenance of the schemes. It is important to note that this is a specific grant allocation for cycling infrastructure improvements, and is not transferable for other projects or programmes.
Is budget release necessary (Capital Approval for budget release will be sought Expenditure Only)? through a report to the Portfolio holder for Economic Development and Regeneration: seeking approval to accept the construction tender prices, appoint the selected contractors and to approve the designs to proceed to implementation.
What are the legal implications? To ensure that the terms of the grant funding are fully complied with and to oversee that the works are carried out in compliance with the Highways and Works Act and the Design Manual for Roads and Bridges.
What are the staffing implications? The Major Projects team will manage the design and delivery of the programme of works with support from Transport for Greater Manchester (TfGM). All staffing costs will be met from the external grant funding received.
Equality and Diversity Impact A full equality and diversity impact assessment is Assessment attached or not required not required for this project as the scheme will because (please give reason) be available to all members of the community. We are hoping to work with the TfGM active travel teams to ensure training and awareness of the routes with various community groups, including people with disabilities and mobility concerns.
What are the property implications in None applicable. terms of reduction, addition or change to the council’s asset base or its occupation?
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Cycling ProjectsReport | 286 KB | DownloadRead as text |
PDF |
Enc. 1 for Cycling ProjectsReport | 3.6 MB | Download |
PDF |
Enc. 2 for Cycling ProjectsReport | 265 KB | Download |
Follow All: Place and Environment Scrutiny Committee at Wigan and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Sep 2026 | Whipping DeclarationsThere were no declarations | Decided | Open |
| 9 Sep 2026 | Executive's Forward Plan of Key and Non-Key DecisionsThe Committee notes the forthcoming decisions, with no items being requested to be placed on a future agenda of the C... | Decided | Open |
| 9 Sep 2026 | Scoping Report - 'The Restoration of Haigh Hall'The Committee:- (1) directs the Task and Finish Group to undertake further scoping work and resubmit the proposal for... | Decided | Open |
| 9 Sep 2026 | Highways Asset Management Annual ReportThe Committee:- (1) thanks the officer for their report; and (2) notes the content of the report. | Decided | Open |
| 9 Sep 2026 | Flood Risk and Resilience UpdateThe Committee:- (1) thanks the officers for their report; and (2) notes the content of the report. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.