Resolved
The Committee:- (1) thanks the officers for their report and presentation; and (2) support the work being undertaken by the Network Management and Infrastructure Maintenance Groups to develop services to meet the needs of the borough.
All: Place and Environment Scrutiny Committee decided this item on Wednesday 13 March 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee:- (1) thanks the officers for their report and presentation; and (2) support the work being undertaken by the Network Management and Infrastructure Maintenance Groups to develop services to meet the needs of the borough.
Appendix 1 – Typical Highway Carriageway Minor Defects
From an engineering perspective, the majority of highway minor repairs can be broadly categorised as being either a surface depressions or surface deterioration. An overview of the most common type of defects is outlined below.
Surface Depressions (and rutting)
Carriageway surface depressions are generally formed when a section of the carriageway substructure fails. Common causes of failure can be linked to underground utility failures (such as water leaks/broken pipes/poor compaction on reinstatements) and/or highway drainage infrastructure failures. Typical examples of this type of defect is shown below:
Surface Deterioration
Carriageways will naturally deteriorate over time, but deterioration can also be accelerated by a number of factors including high volumes and weight of vehicles, higher than normal ambient temperatures, lower than normal cold weather and precipitation (both rain and snow). As the carriageway surface deteriorates the surface texture will become more ‘open’ allowing moisture to penetrate the surface material and this can result in ‘freeze/thaw’ action to take effect, in cold weather conditions. Typical examples of this type of defect are shown below.
1 ‘Potholes’
If left unchecked, surface deterioration will erode both the surface course of the carriageway and the lower sub-base bituminous layers. These defects are typically referred to as ‘Potholes’ and during the winter months can form over a very short period of time. Typical examples of this type of defect are shown below.
2 Appendix 2 – Typical Highway Carriageway Minor Repair Techniques
1. Hot Lay Patch – Reactive Works
This process is seen as a traditional method and will typically involve excavating the defective area (squaring) with pneumatic hammers to remove all existing loose material and debris. The area is then treated with a bonding coat and laying new surface course material, which is compacted. This method provides a permanent repair and can be applied to any size of repair. Typical examples of this repair technique are shown below.
2. Hot Lay Patch – Planned Works In addition to the reactive repairs (in 1 above) the council also carries out a planned patching program. This enables us to carry out repairs to the carriageway that may not require immediate repairs but if not addressed, would affect the overall condition of the highway surface course. Planned maintenance generally reduces the cost of the repairs and impact on the disruption on the network. Typical examples of this repair technique are shown below
3. Cold Lay Patch – Reactive Repair
Compared to the hot lay process, this process involves the use of specially developed bitumous materials that do not require the use of pneumatic hammers to remove the loose material nor the application of bond coat. The advantage of the use of this type of process is that a permanent repair can be carried out in usually less than 20 minutes, which is faster than any other method and so reduces impact on highways users.
This makes it particularly suitable for use on emergency repairs and also for difficult to access sites (such as the middle of a busy road junction) or locations that would require high cost temporary traffic management or incur road diversions (such as high speed roads and dual carriageways). However, this product has a premium cost compared to the more traditional hot lay materials and as such is not suitable for use in repairing high numbers of
3 carriageway defects. It is also primarily aimed at repairing small areas and can be perceived as a temporary or poor quality repair by highway users (as the material is shaped to the defective area – not ‘squared’).
The use of a typical cold lay product can be viewed on line via the following link: www.viatec- uk.com/case-study-1-viafixquick-for-pothol.
4. Thermal Patching
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Enc. 1 for Well Maintained Highways (Pot Holes)Report | 536 KB | DownloadRead as text |
PDF |
Enc. 2 for Well Maintained Highways (Pot Holes)Report | 128 KB | Download |
PDF |
Well Maintained Highways (Pot Holes)Report | 180 KB | Download |
Follow All: Place and Environment Scrutiny Committee at Wigan and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Sep 2026 | Whipping DeclarationsThere were no declarations | Decided | Open |
| 9 Sep 2026 | Executive's Forward Plan of Key and Non-Key DecisionsThe Committee notes the forthcoming decisions, with no items being requested to be placed on a future agenda of the C... | Decided | Open |
| 9 Sep 2026 | Scoping Report - 'The Restoration of Haigh Hall'The Committee:- (1) directs the Task and Finish Group to undertake further scoping work and resubmit the proposal for... | Decided | Open |
| 9 Sep 2026 | Highways Asset Management Annual ReportThe Committee:- (1) thanks the officer for their report; and (2) notes the content of the report. | Decided | Open |
| 9 Sep 2026 | Flood Risk and Resilience UpdateThe Committee:- (1) thanks the officers for their report; and (2) notes the content of the report. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.