School Organisation: Proposed Permanent Enlargement of St John’s CE Primary, Mosley Common
DecidedExecutive4 papers
AI summaryWigan Cabinet approved publishing the statutory notice to permanently expand St John's CE Primary School, Mosley Common, from 22 to 60 Reception places. The £8,083,108 scheme is funded mainly through developer Section 106 contributions, with a representation period to follow.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedPermission to issue notice for permanent expansion
Money£8,083,108 S106 funding agreedTotal from developer contributions
What happens nextStatutory notice to be publishedRepresentation period to commence
Who it affectsTyldesley, Mosley Common and Astley wardsWards affected by the proposal
What was decided
Cabinet noted the responses received to the consultation to permanently enlarge St John's CE Primary School. Report P13
Cabinet gave permission for the statutory notice to be issued so the required representation period can commence. Report P13, P7
Why
Projections show insufficient primary school places in the Tyldesley planning area to meet demand from existing births and a large new housing development of around 1,143 homes in Mosley Common. Report P25, P91, P92, 4.1
Of 23 consultation form responses, 6 were in favour and 17 against, with the largest concerns being traffic, parking, road safety and possible effects on nearby Catholic schools, particularly Holy Family Catholic Primary. Report P72, 2.7, P89
What happens next
The Council will publish the statutory notice to start the formal representation period under the 5-stage prescribed alterations process. Report P13, 1.3, P54
Permission to release capital funds will be requested separately once the statutory process is complete. Report P19, P20
The key decision cannot be actioned until 31 March 2026, allowing time for call-in. Report P39
The money
£8,083,108 Total Section 106 funding agreed for the expansion Report P18
£4,449,205.34 S106 contribution from the Northern Site Report P18
£3,383,902.66 S106 contribution from the Southern Site Report P18
£250,000 Further S106 from planning application A/23/94952 Report P18
Options considered
Rejected: Do nothing and use capacity in other planning areas. Could mean unreasonable journey times and free travel costs Report P31
Rejected: Wait and see if pupil numbers materialise. Risk of pupils taught in temporary buildings and higher costs Report P32
Rejected: Phased expansion year on year. Likely to increase cost and disruption Report P33
Rejected: Temporary or modular buildings. Worse value, shorter design life, perceived as temporary Report P34
Rejected: Expand an alternative school or split expansion across multiple schools. Infant class size rules, operational inefficiency, fragmented capital Report P35, P119, P120, P121, P122
Rejected: Build a new school. Council would not control timing and risk it not being ready Report P36
Chosen: Permanently expand St John's CE Primary School to a 60-place Reception intake. School is Good, popular, on the edge of the development with land available, and meets sustained demand Report 1.4, 1.5, 1.6, P93, 4.3
Implications
Financial: Council will need to forward fund the expansion in advance of receiving S106 contributions, which are released only when housing trigger points are met; any shortfall may have to be met from Basic Need. Report P15, P16, P19
Legal: The process must follow the School Organisation (Prescribed Alterations to Maintained Schools) (England) Regulations 2013 and DfE guidance Making significant changes (prescribed alterations) to maintained schools August 2025. Report P21, 1.3
Equalities: An Equality and Diversity Impact Assessment is not required; a relevance check is attached. Admission arrangements give highest priority to Looked After and previously Looked After children. Report P22, P24
Climate: The proposed design aims for a zero carbon in operation building to comply with the council's carbon reduction policies. Report P27
Risk: Without action, projections show insufficient primary places in the Tyldesley area; there is also a financial risk if S106 contributions are delayed or fall short of final cost. Report P25, P26, P16
Staffing: No staffing implications at this stage, but additional staff will be needed once the school is expanded. Report P21, P136
Other: The school is a Church of England Voluntary Aided school, Diocese of Manchester. The site and building will be enlarged, additional land will be provided by the developer, and an existing modular building housing a start well and nursery will be removed. Report P23
Who and where
Children and families in the Tyldesley, Mosley Common and Astley wards Report P12, P11
St John's CE Primary School pupils, staff and governors Report P129, P66
Residents concerned about traffic, parking and congestion on Mosley Common Road Report P77, 2.7
Timeline
January 2024: School Place Planning Strategy approved by the Portfolio Holder Report 1.1, P49
12 January 2026: Start of 6-week non-statutory consultation Report 2.2
20 January 2026: Meeting held with school governors Report 2.3
21 January 2026: Meeting held with school staff Report 2.3
23 January 2026: Open consultation session for stakeholders Report 2.4
23 February 2026: End of 6-week consultation Report 2.2
6 March 2026: Report signed off by Assistant Director Education Report P42, P43
19 March 2026: Cabinet decision to authorise statutory notice Report P2
Before 31 March 2026: Earliest date the key decision can be actioned after call-in period Report P39
September 2027: First expanded Reception intake of 60 pupils proposed Report 1.4
Plain English for the jargon
Section 106 (S106): Developer contribution paid to the council to fund infrastructure needed because of new housing, released when housing milestones are met.
PAN (Published Admission Number): The maximum number of pupils a school will admit into Reception each year.
Primary Place Planning Area (PPA): A local grouping of primary schools used to plan school places for an area.
Voluntary Aided (VA) school: A state school where the governing body and a religious body contribute to capital costs and the building is owned by the religious body; here, the Church of England Diocese of Manchester.
RIBA 1: An early Royal Institute of British Architects work stage covering feasibility and preparation of a brief and cost plan.
Building Bulletin (BB): Department for Education design guidance for school buildings, covering sizes and standards for spaces such as halls, dining and play areas.
Basic Need: Government funding allocated to councils to provide extra school places where they are needed.
Free School: A state school funded by the government but not run by the local authority.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item96
Resolved
The Cabinet:- (1) notes the responses received to the consultation to permanently enlarge St John’s CE Primary School; and (2) gives permission for the statutory notice to be issued on the permanent expansion of St John’s CE Primary School so that the required representation period can commence.
Word for word from the decision Wigan published for this meeting.Source: democracy.wigan.gov.uk
Subject: School Organisation: Proposed permanent enlargement of St John’s CE Primary, Mosley Common
Report of: Cath Pealing - Assistant Director - Education
Contact Officer: Darren Thomas-Stanley ([phone removed]), Catherine Thompson ([phone removed])
Cabinet Portfolio Holder and area: Councillor Dane Anderton, Portfolio Holder for Children and Families
Summary: The purpose of the report is to request that Cabinet give permission for the statutory notice to be issued so that the required representation period in relation to the proposed permanent enlargement of St John’s CE Primary School, Mosley Common can commence.
‘Progress with Unity’ Missions: As residents, businesses, public services and community organisations of this borough we have come together to deliver two key missions:
Mission 1: Create fair opportunities for all children, families, residents & businesses. “Together, we will break down the barriers that create financial, health, education and environmental inequalities in our borough.”
Mission 2: Make all our towns and neighbourhoods flourish for those who live and work in them. “Together, in genuine partnership with our residents and businesses, who know our community best, we will help each town and neighbourhood in the borough celebrate and maintain their identity whilst understanding and helping to achieve what is needed to thrive.”
Outline how this report supports our ‘Progress with Unity’ missions. The expansion of St John’s CE Primary School. Mosley Common will ensure that children in the local community can access education in the area where they live.
Wards Affected: Tyldesley, Mosley Common and Astley. Recommendation(s): Following the initial non-statutory pre-publication consultation on the proposed permanent expansion of St John’s CE Primary School, the Cabinet is requested to –
(1) consider the responses received to the consultation to permanently enlarge St John’s CE Primary School; and (2) give permission for the statutory notice to be issued on the permanent expansion of St John’s CE Primary School so that the required representation period can commence.
Implications:
What are the financial implications? The proposed expansion is intended to be funded primarily through Section 106 (S106) developer contributions. S106 payments are released only when specific milestones, known as trigger points, in the associated housing development are reached, such as a set number of occupied homes or completion of a development phase. As these trigger points occur later in the build out of the housing sites, the Council will need to forward fund the school expansion in advance of receiving the S106 contributions.
This creates a financial risk. If the full S106 contributions are delayed, not triggered, or are lower than the final cost of the scheme, the Council would be required to meet any shortfall. In these circumstances, some or all of the cost of the project may need to be funded by the Council through Basic Need rather than recovered from the developer.
Feasibility to RIBA 1 with an associated cost plan has been completed.
£8,083,108 has been agreed through S106 agreements to fund the expansion of St John’s CE Primary, Mosley Common (£4,449,205.34 from the Northern Site, £3,383,902.66 from the Southern Site and a further £250,000 S106 from planning application A/23/94952).
Permission to release capital funds will be requested separately if the proposal is approved following the completion of the 5-stage statutory process.
Is budget release necessary (Capital Expenditure Only)? Budget release will be required if the proposal goes ahead.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.