School Organisation: Proposed Permanent Enlargement of Garrett Hall Primary School
DecidedExecutive4 papers
AI summaryWigan Cabinet approves publishing the statutory notice to permanently enlarge Garrett Hall Primary School from 60 to 90 Reception places from September 2028, with a project cost of £6,800,020.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedPermission given to start formal representation period
Money£6,800,020 estimated project costMet from basic need funding
What happens nextFormal representation period to beginDecision cannot be actioned before 28 April 2026
Who it affectsTyldesley, Mosley Common and Astley wardsGarrett Hall Primary School community and nearby schools
What was decided
Cabinet noted the responses received to the consultation on permanently enlarging Garrett Hall Primary School. Report P13
Cabinet gave permission for the statutory notice to be issued so the required representation period could begin, moving the proposal to stages 1 and 2 of the 5-stage prescribed alterations process. Report P13, P57
Why
The school is graded Outstanding by Ofsted (using the previous grading system) and is regularly oversubscribed, and the council's projections show existing capacity in the Tyldesley Primary Place Planning Area is exhausted and insufficient to meet demand from housing developments and birth rate peaks. Report 1.5, 1.6, P113
Officers consider permanent expansion at this site a better option than modular buildings, phasing, splitting places across multiple schools, or building a new school, on grounds of cost, disruption, sustainability and value for money. Report P34, P36, P37, P129
The main objections, set out in 29 of 34 consultation response form replies, concerned traffic, parking, road safety, environmental impacts and possible effects on Catholic schools; officers addressed each in the report. Report P74, 3.1, 3.2, 3.4, P167, P168
What happens next
The statutory notice will be published to begin the formal representation period (stages 1 and 2 of the 5-stage process). Report P13, P57
Following the representation period, the proposal will return to Cabinet at stage 3 for a decision, and a separate planning application with a Transport Assessment and Travel Plan will follow. Report P82, P83, P58
Separate approval to release the £6,800,020 capital funds will be sought, and the school is also being considered for a Department for Education School Rebuilding Programme bid. Report P16, P17, P21
The money
£6,800,020 Estimated total project cost at RIBA 1 stage, including fees, sundry, services, contingency and risk Report P15
Options considered
Chosen: Permanent expansion of Garrett Hall Primary School from 60 to 90 Reception places. School is Outstanding, popular, in the area of need, and capable of being extended on site Report 1.4, 1.6
Rejected: Do nothing and use capacity in other planning areas. Could lead to unreasonable journey times and the council having to fund free travel assistance Report P31
Rejected: Do nothing and wait to see if demand materialises. Could leave children in temporary buildings and increase costs Report P32
Rejected: Phased expansion delivered year on year. Likely to increase costs, disruption for pupils, staff and the community Report P33
Rejected: Temporary or modular buildings. Not good value; shorter design life; less robust; often seen as temporary by users Report P34
Rejected: Expand an alternative school instead of Garrett Hall. Garrett Hall is in the area where places are required and is the preferred site alongside St John's CE Primary Report P35
Rejected: Spread a half form of entry (15 places) across multiple schools. Forces split classes, increases staff workload, fragments capital and reduces value for money Report P36
Rejected: Build a new school. Higher capital cost, site identification is hard, DfE Free School process is outside council control and may not be ready in time Report P37, P156
Implications
Financial: Estimated total project cost of £6,800,020, to be met from existing basic need funding, with a separate budget release request to follow. Report P15, P16, P21
Legal: Process must comply with the School Organisation (Prescribed Alterations to Maintained Schools) (England) Regulations 2013 and DfE guidance 'Making significant changes (prescribed alterations) to maintained schools' August 2025; the Assistant Director, Legal Governance and Elections has confirmed the recommendations are lawful. Report P22, P28
Equalities: An Equality and Diversity Impact Assessment was not required; a relevance check is attached, and admission arrangements give highest priority to Looked After and previously Looked After children. Report P23, P25
Climate: The new building is proposed to be designed as 'zero carbon in operation' to meet the council's carbon reduction policies. Report P27
Risk: If no action is taken, projections show insufficient primary places in the Tyldesley planning area; the expansion would also create more Outstanding school places where needed. Report P26
Staffing: No staffing implications at this stage, but if the proposal goes ahead the school will need to employ additional staff to serve the increased population. Report P22, P176
Other: Land and property are owned by the council; the building will be enlarged if the proposal is approved. The school is also being considered for a potential Department for Education School Rebuilding Programme bid, which is not intended to fund capacity expansion driven by local demographic need. Report P17, P18, P19, P24
Who and where
Children and families in the Tyldesley Primary Place Planning Area who need primary school places Report 1.6, P11, P99
Pupils, staff and governors of Garrett Hall Primary School Report P68, 2.3, P135
Other primary schools in the Tyldesley planning area, including Catholic schools (Holy Family Catholic Primary and St Ambrose Barlow Catholic Primary) and St John's CE Primary School Report P35, P100, P120
Residents in the wards of Tyldesley, Mosley Common and Astley, including those concerned about traffic, parking and road safety around the school Report P12, 3.1, P80
The Roman Catholic Archdiocese of Liverpool, which responded to the consultation Report 2.5, P120
Future secondary schools in the area, with the council monitoring the impact of larger primary cohorts moving through Report P158, P159
Timeline
January 2024: School Place Planning Strategy approved, categorising Tyldesley as Priority 1 (Growth) and identifying Garrett Hall and St John's CE Primary as locations for additional places Report 1.1, P51
May 2024: Garrett Hall Primary School last inspected by Ofsted, graded Outstanding under the previous grading system Report 1.5
9 February 2026: Start of the 6-week non-statutory consultation Report 2.2
25 February 2026: Consultation meeting with school staff Report 2.3
11 March 2026: Open consultation session for stakeholders (2 attendees) Report 2.4
19 March 2026: Cabinet approved St John's CE Primary School expansion to proceed to statutory stages 1 and 2 Report P100
23 March 2026: End of consultation; meeting with school Governors Report 2.2, 2.3
16 April 2026: Cabinet decision to permit publication of the statutory notice Report P2
before 28 April 2026: Earliest date the key decision can be actioned (after the 5 working day call-in period) Report P40
September 2028: Proposed start of permanent enlarged Reception intake of 90 pupils (subsequent years also 90) Report 1.4
Plain English for the jargon
PAN (Published Admission Number): The maximum number of pupils a school will admit into its Reception year group.
RIBA 1: An early-stage feasibility stage in the Royal Institute of British Architects' work stages, used to set out initial cost plans.
Form of entry: The number of classes a school admits per year group; one form of entry equals one class of 30 pupils.
Basic need funding: Government capital funding provided to local authorities to create school places where pupil numbers are rising.
School Rebuilding Programme (SRP): A national Department for Education investment scheme for major rebuilding and refurbishment of schools and sixth form colleges in England.
PPA (Primary Place Planning Area): A local area used by the council to plan the supply of primary school places.
Statutory notice: A formal notice published as part of the prescribed alterations process, beginning the period during which representations can be made.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item103
Resolved
The Cabinet:- (1) notes the responses received to the consultation to permanently enlarge Garrett Hall Primary School; and (2) gives permission for the statutory notice to be issued on the permanent expansion of Garrett Hall Primary School, so that the required representation period can commence.
Word for word from the decision Wigan published for this meeting.Source: democracy.wigan.gov.uk
Subject: School Organisation: Proposed Permanent Enlargement of Garrett Hall Primary School
Report of: Cath Pealing, Assistant Director - Education
Contact Officer: Darren Thomas-Stanley ([phone removed]), Catherine Thompson ([phone removed])
Cabinet Portfolio Holder and area: Councillor Dane Anderton, Portfolio Holder for Children and Families
Summary: The purpose of the report is to request that Cabinet give permission for the statutory notice to be issued so that the required representation period in relation to the proposed permanent enlargement of Garrett Hall Primary School can commence.
‘Progress with Unity’ Missions: As residents, businesses, public services and community organisations of this borough we have come together to deliver two key missions:
Mission 1: Create fair opportunities for all children, families, residents & businesses. “Together, we will break down the barriers that create financial, health, education and environmental inequalities in our borough.”
Mission 2: Make all our towns and neighbourhoods flourish for those who live and work in them. “Together, in genuine partnership with our residents and businesses, who know our community best, we will help each town and neighbourhood in the borough celebrate and maintain their identity whilst understanding and helping to achieve what is needed to thrive.”
Outline how this report supports our ‘Progress with Unity’ missions. The expansion of Garrett Hall Primary School will ensure that children in the local community can access education in the area where they live.
Wards Affected: Tyldesley, Mosley Common and Astley. Recommendation(s): Following the initial non-statutory pre-publication consultation on the proposed permanent expansion of Garrett Hall Primary School, the Cabinet is requested to –
(1) consider the responses received to the consultation to permanently enlarge Garrett Hall Primary School; and (2) give permission for the statutory notice to be issued on the permanent expansion of Garrett Hall Primary School so that the required representation period can commence.
Implications:
What are the financial implications? Feasibility to RIBA 1 with an associated cost plan has been completed. This estimated total project cost is £6,800,020 including allowances for associated fees, sundry and services costs and an allowance for contingency and risk. This capital investment will be met by existing resources of basic need funding.
Permission to release capital funds will be requested separately.
It should also be noted that, Garrett Hall Primary School is currently being considered for a potential bid to the Department for Education’s School Rebuilding Programme (SRP). This is a national Department for Education investment scheme that delivers major rebuilding and refurbishment projects for schools and sixth form colleges across England.
If successful, the SRP would deliver a full or partial rebuild to modern standards, including designing the new buildings to accommodate projected future pupil numbers.
However, SRP funding is not intended to replace or fund capacity expansion projects driven by local demographic need. Should additional places still be required beyond the scope of the SRP funded rebuild, the Council may still need to meet the associated expansion costs separately.
At this stage, the school’s inclusion is subject to the bid being submitted and approved.
Is budget release necessary (Capital Expenditure Only)? Budget release will be required if the proposal goes ahead. LA basic need funding will be confirmed by the Strategic Finance Manager.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.