AI summaryWigan's Housing Advisory Panel has endorsed a new delivery model for housing repairs across 21,000 council homes, splitting the borough into four areas with long-term principal contractors. Move to NATFED industry rates brings an indicative 15% to 33% cost uplift.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedPanel backed preferred option for repairs and maintenance delivery
MoneyIndicative 15% to 33% cost upliftBased on recent mini-tender and disrepair bid analysis
What happens nextApril 2027 go-liveNew framework targeted to start, subject to Cabinet approval
Who it affects21,000 council homes and tenantsAll wards affected; housing stock across the borough
What was decided
The Panel endorsed the proposed delivery model as the preferred option for future repairs and maintenance services across the council's housing stock. Report P23
The Panel supported the transition to the NATFED Schedule of Rates for specifying works, replacing the current local Schedule of Rates system. Report P24
The Panel agreed to receive regular updates as implementation and mobilisation of the new arrangements develop. Report P25
Why
The council is a social landlord for around 21,000 homes and must meet revised Consumer Standards, Decent Homes expectations, Building Safety obligations, Awaab's Law, and Housing Ombudsman requirements. Report P9
Overall repair costs are expected to rise under the new framework because of wider market changes, inflationary pressures, and the fact that existing contractor rates have not been consistently uplifted for over four years. Report P27
Re-procurement is described as a statutory requirement under the Procurement Act 2023, with no viable alternative options identified. Report P77
What happens next
Cabinet approval will be sought to commence and award contracts for the proposed model through procurement. Report 9.1, P157
Indicative procurement timeline: PQQ May to July 2026, ITT September 2026, evaluation October 2026, contract award November to December 2026, mobilisation December 2026 to April 2027. Report P145
New framework is planned to go live in April 2027, with interim arrangements with incumbent contractors being discussed to maintain service continuity. Report 8.1, 8.3, P145
The money
potential uplift in the region of 15% to 33% Indicative cost rise from recent mini-tender and disrepair bid analysis Report P27
minimum 20% Social Value weighting within the Building Services Framework tender evaluation, up from the standard 15% Report P122
Options considered
Chosen: Transition to NATFED Schedule of Rates. Offers transparency, industry alignment, and consistency; cheaper than Gordian alternatives and already used by the council's Disrepair Team. Report 3.1, 3.2, P101
Rejected: Retain and expand the bespoke in-house Schedule of Rates. Not preferred after options appraisal; mis-coding and high variation use were identified issues. Report 3.1, 3.2
Rejected: Continue with the existing Building Services Framework without re-procurement. Re-procurement is a statutory requirement under the Procurement Act 2023. Report P77
Implications
Financial: Repair costs are expected to rise under the new framework, with a pre-emptive HRA allowance already ringfenced and a further budget release anticipated once tendered rates are confirmed. Report P27, P30, P31
Legal: Procurement and delivery must comply with the Procurement Act 2023, Social Housing Regulation Act 2023, Awaab's Law, CDM Regulations 2015, Building Safety Act 2022, and the Housing Ombudsman Complaint Handling Code. Report P32, P33, P35
Staffing: The contract management function will move from Resident Services into the Place Directorate; potential TUPE considerations for contractor staff are flagged but not yet determined. Report P38, P39, P40, 7.1, 7.2
Risk: Eight risk areas are identified: financial, staffing, systems, reputational, NATFED implementation, regulatory compliance, market and contractor viability, and tenant experience. Report P50, P51, P53, P56, P58, P60, P62, P66, P71
Equalities: The workstream is aligned with the Housing Ombudsman's Spotlight Report on Vulnerabilities and embeds tenant voice and co-production throughout. Report P44, P45
Climate: Improved repairs are expected to extend the life of housing stock, reduce embodied carbon, and support the council's decarbonisation and climate action commitments. Report P73
Who and where
Tenants in the council's approximately 21,000 council homes, including care leavers Report P9, 1.3, P49
Existing repairs and maintenance contractors and their staff (potential TUPE implications) Report P39, 7.4
Local SMEs and the local supply chain, including specialist trades across 22 framework lots Report P17, P96, P128
Council staff involved in contract management, moving to the Place Directorate Report P38, 7.1
Timeline
May to July 2026: PQQ (Pre-Qualification Questionnaire) issued Report P145
September 2026: ITT (Invitation to Tender) issued Report P145
October 2026: Tender evaluation Report P145
November to December 2026: Contract award Report P145
December 2026 to April 2027: Mobilisation period Report P145
April 2027: Planned go-live of the new Building Services Framework Report 8.1, P145
Plain English for the jargon
NATFED: National schedule of rates used across the social housing sector, providing annually benchmarked rates for repair and maintenance works.
BSF: Building Services Framework, the existing repairs and maintenance framework that this report proposes to replace.
HRA: Housing Revenue Account, the ringfenced account that funds the council's landlord housing functions.
TUPE: Transfer of Undertakings (Protection of Employment) regulations governing the transfer of staff when work moves between employers.
PQQ: Pre-Qualification Questionnaire, the initial stage of a procurement exercise used to assess bidder suitability.
ITT: Invitation to Tender, the formal stage at which qualified bidders are invited to submit priced tenders.
TSM: Tenant Satisfaction Measure, the regulatory metric used to track tenant experience of housing services.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item33
Resolved
Agreed: The Panel:- (1) thanks the officer for their report; (2) notes the approach taken to develop the proposed delivery model for the replacement of the Building Services Framework; (3) endorses the proposed model as the preferred option for future delivery of repairs and maintenance services across the Council’s housing stock; (4) supports the transition to the use of NATFED Schedule of Rates for specifying works, replacing the current local Schedule of Rates system, and notes the work undertaken to assess the financial implications of this change based on the limited benchmark and cost information currently available; (5) acknowledges the significant contribution of tenants, operational staff, and market feedback in shaping and refining the final model presented in this report; and (6) agrees to receive regular updates on progress as implementation and mobilisation of the new arrangements develop.
Word for word from the decision Wigan published for this meeting.Source: democracy.wigan.gov.uk
Cabinet Portfolio Holder and area: Cllr Susan Gambles, Portfolio Holder for Housing and Welfare
Summary: This report seeks the support of Housing Advisory Panel to proceed with a formal procurement exercise to replace the existing Building Services Framework (BSF) with a new delivery model for repairs and maintenance services across the Council’s housing stock. Housing Advisory Panel have previously received information and fed back on the plans to take this forward. The proposed model set out in this report is a key part of the wider transformation programme for housing repairs. Its development has been shaped by extensive learning from the current framework arrangements, direct tenant feedback, contractor insight, engagement with the supplier market and the findings and recommendations of external consultants who have recently reviewed the Council’s repairs service.
The new approach aligns fully with the Council’s Progress with Unity Missions, placing tenants at the heart of service design and focusing on ensuring that homes are safe, well maintained and supported by a high‑quality, responsive repairs offer. As a social landlord responsible for approximately 21,000 homes, the Council must also demonstrate compliance with a wide range of statutory and regulatory requirements, including: the revised Consumer Standards set by the Regulator of Social Housing, Decent Homes expectations, Building Safety obligations, Awaab’s Law, and Housing Ombudsman requirements. The proposed model is designed to strengthen assurance in all these areas.
This represents a significant and radical shift from the way repairs and maintenance services are currently delivered. Successful implementation will require a coordinated, Council‑wide response, given the close interdependencies with organisational design, digital transformation, financial and commercial mechanisms, procurement strategy, and legal considerations.
Housing Advisory Panel are asked to review the proposed model, the reasons for it and to endorse commencement of the formal procurement activity. This report should also note our sincere thanks to our HAP members and wider tenant representatives whose contributions have helped shape the model being proposed.
‘Progress with Unity’ Missions: As residents, businesses, public services and community organisations of this borough we have come together to deliver two key missions:
Mission 1: Create fair opportunities for all children, families, residents & businesses. “Together, we will break down the barriers that create financial, health, education and environmental inequalities in our borough.”
Mission 2: Make all our towns and neighbourhoods flourish for those who live and work in them. “Together, in genuine partnership with our residents and businesses, who know our community best, we will help each town and neighbourhood in the borough celebrate and maintain their identity whilst understanding and helping to achieve what is needed to thrive.”
Outline how this report supports our ‘Progress with Unity’ missions: This programme supports the missions by:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.