Wigan Metropolitan Borough Council
Cabinet, Thursday 16 April 2026 at 10.30am

Building Services Framework Procurement (Housing Services – Repairs and Maintenance)

Approved Executive 1 paper

AI summaryWigan Cabinet approves new Building Services Framework for housing repairs and maintenance across 21,000 council homes, replacing the current arrangement with a four-area model. New contracts start 1 April 2027, with interim deals to current contractors bridging the gap.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedPreferred option for repairs and maintenance delivery
MoneyCosts expected to riseIndicative 15% to 33% uplift on recent bids
What happens nextNew contracts start 1 April 2027Interim contracts with incumbents until then
Who it affectsAll 21,000 council homesTenants, contractors, and internal staff across the borough

What was decided

Cabinet approved the proposed model as the preferred option for future repairs and maintenance across the housing stock, with three external principal contractors across three areas and the in-house service in the fourth. Report 2.2, 2.3, 2.4

Cabinet approved delegated authority for the Director of Place, in consultation with the Portfolio Holder for Housing and Welfare, to award the new contracts after the procurement exercise. Report P6

Cabinet approved interim contracts with incumbent contractors, including three sole traders, to run until 1 April 2027, and supported the move to NATFED Schedule of Rates. Report 3.1

Why

The current framework ends in July 2026, and re-procurement is required under the Procurement Act 2023 to meet legal and regulatory obligations, including the Social Housing (Regulation) Act 2023 and Awaab's Law. Report P7, P29, 1.2, P73

Existing contractor rates have not been consistently uplifted for over four years, and the move to NATFED is expected to bring pricing in line with current market conditions. Report P21, 3.1, 3.2

Tenant engagement, contractor feedback, and external consultant reviews identified weaknesses in the current model, including multiple handoffs, inconsistent communication, and limited transparency. Report P7, 1.4, 5.2, 5.3

What happens next

A formal procurement exercise will commence, with new contracts due to begin on 1 April 2027, structured as 3+3+2 years. Report 2.1

Interim contracts will be awarded to incumbent contractors to maintain service continuity until the new arrangements start. Report P25, P26

A budget release will be sought once tendered rates are confirmed, with uplifts expected to be reviewed at years 3 and 6 of the contract. Report P28, P113

The money

  • 15% to 33% Potential indicative uplift on recent mini-tender and disrepair project bids Report P21
  • 20% Minimum social value weighting in tender evaluation, up from 15% Report 6.1
  • approximately 350 Number of codes in the current in-house Schedule of Rates Report 3.2
  • 21,000 Council homes covered by the new framework Report P83

Options considered

  • Chosen: Move to NATFED Schedule of Rates (selected). Nationally benchmarked, transparent, already used by the Council's Disrepair Team, lower cost than Gordian alternatives Report 3.1, 3.3, P106
  • Rejected: Retain and expand the in-house Schedule of Rates. Limitations including inconsistent uplifts, few codes, heavy reliance on variations, and difficulty benchmarking Report 3.1, 3.2
  • Rejected: Purchase a national schedule of rates with associated software (Gordian). Significantly higher annual licence costs Report 3.3, P106
  • Rejected: No re-procurement. Re-procurement is a statutory requirement under the Procurement Act 2023 Report P73

Implications

  • Financial: Overall repairs costs are expected to rise under the new framework, with a pre-emptive allowance already ringfenced in the Housing Revenue Account budget. Report P21, P24, P28
  • Legal: Awarding interim contracts to incumbent contractors carries a risk of legal challenge under the Procurement Act 2023, as no applicable direct award or modification ground has been identified. Report P35, P61
  • Staffing: Contract management will move from Resident Services into the Place Directorate, and TUPE considerations for contractor staff may arise once work packages are allocated. Report P36, 7.2, P37, P38
  • Risk: Key risks include financial pressures, staffing capacity, systems readiness, contractor viability, tenant experience, and regulatory compliance, each with mitigation in place or planned. Report P47, P48, P50, P52, P54, P56, P58, P62, P64, P67
  • Equalities: The model is aligned with the Housing Ombudsman's Spotlight Report on Vulnerabilities, and tenant voice and co-production are embedded throughout. Report P42, P43, 1.4
  • Climate: Timely repairs are expected to improve energy performance and support decarbonisation targets, while reducing the need for major replacements. Report P69

Who and where

  • Tenants in all 21,000 council homes across all wards Report P17, P83
  • Incumbent contractors, including three sole traders Report P25
  • Potential principal contractors and specialist contractors responding to the tender Report 2.2, 2.5, 2.8
  • Council staff in the contract management function, moving to the Place Directorate Report P36, 7.2
  • Care leavers living in council homes Report P46
  • Local SMEs and the wider supply chain in the borough Report 6.1, P138, P140

Timeline

  • 17 March 2026: Report signed off by the directorate Report P79
  • 16 April 2026: Cabinet decision taken Report P2
  • Before 28 April 2026: Key decision call-in period ends, unless exempt Report P75
  • July 2026: Current Building Services Framework due to end Report P25
  • 1 April 2027: New contractual arrangements commence, with interim contracts bridging the gap Report P25
  • Years 3 and 6 of the 8-year term: Uplift thresholds for NATFED rates to be reviewed Report P113

Plain English for the jargon

  • NATFED: National schedule of rates widely used across the social housing sector for pricing repairs work.
  • BSF: Building Services Framework, the current arrangement for delivering housing repairs and maintenance.
  • TUPE: Transfer of Undertakings (Protection of Employment) regulations, which can transfer staff when work moves between employers.
  • Awaab's Law: Legal duty on social landlords to respond to hazards such as damp and mould within set timescales.
  • HRA: Housing Revenue Account, the ringfenced landlord account used to manage council housing finances.
  • SOR: Schedule of Rates, the priced list of works used to calculate payments for repairs.
  • TSM: Tenant Satisfaction Measure, the standardised score used to gauge tenant experience of repairs.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item104

Resolved

The Cabinet:- (1) notes the approach taken to develop the proposed delivery model for the replacement of the Building Services Framework, including the use of data from the wider repairs transformation work, learning from the current framework, and extensive engagement with tenants, officers, and the supplier market; (2) approves the proposed model as the preferred option for future delivery of repairs and maintenance services across the Council’s housing stock; (3) approves delegated authority for the Director of Place in consultation with the Portfolio Holder for Housing and Welfare to award the new contractual arrangements in line with the proposed model following the procurement exercise; (4) approves the award of interim contracts to the incumbent contractors, which includes three sole traders, to ensure continuity of service delivery until the new arrangements commence on 1st April 2027; (5) supports the transition to the use of the NATFED Schedule of Rates for specifying works, replacing the current local Schedule of Rates system, and note the work undertaken to assess the financial implications of this change based on the limited benchmark and cost information currently available; (6) acknowledges the significant contribution of tenants, operational staff, and market feedback in shaping and refining the final model presented in this report; and (7) notes the key risks associated with the proposed approach and the actions already in place or planned to mitigate these risks.
Word for word from the decision Wigan published for this meeting. Source: democracy.wigan.gov.uk

Follow this further

Built from Wigan's papers

What the report saysPro

Report to Cabinet

This is an open report Report to: Cabinet

Date of Meeting(s): Thursday, 16 April 2026

Subject: Building Services Framework Procurement (Housing Services – Repairs and Maintenance)

Report of: Aidan Thatcher, Director - Place

Contact Officer: Stephanie Saxon ([email protected])

Cabinet Portfolio Holder and area: Councillor Susan Gambles - Portfolio Holder for Housing and Welfare

Summary: This report seeks approval to proceed with a formal procurement exercise to replace the existing Building Services Framework (BSF) with a new delivery model for repairs and maintenance services across the Council’s housing stock. The proposed model forms a key part of the wider transformation programme for housing repairs and has been shaped by extensive learning from the current framework arrangements, direct tenant feedback, contractor insight, and the findings and recommendations of external consultants who have recently reviewed the Council’s repairs service.

This proposal has been endorsed by the Housing Business Board, SMT and Housing Advisory Panel.

‘Progress with Unity’ Missions: As residents, businesses, public services and community organisations of this borough we have come together to deliver two key missions:

Mission 1: Create fair opportunities for all children, families, residents & businesses. “Together, we will break down the barriers that create financial, health, education and environmental inequalities in our borough.”

Mission 2: Make all our towns and neighbourhoods flourish for those who live and work in them. “Together, in genuine partnership with our residents and businesses, who know our community best, we will help each town and neighbourhood in the borough celebrate and maintain their identity whilst understanding and helping to achieve what is needed to thrive.”

Outline how this report supports our ‘Progress with Unity’ missions. This programme supports the missions by:

• Mission 1: Create fair opportunities for all children, families, residents and businesses, by tackling the financial, health and environmental inequalities that arise when homes are not well maintained. A reliable, compliant and person centred repairs service ensures tenants live in safe, warm and healthy homes to reduce risks associated with damp, mould and building safety issues, and supporting improved outcomes for children and families. As part of meeting the Regulator for Social Housing’s consumer standards, Awaab’s Law, Building Safety requirements and Decent Homes expectations, the model embeds a commitment to seeing the person, understanding vulnerabilities and individual needs, and adjusting how services are delivered so that barriers are removed rather than reinforced. This helps ensure that no tenant is disadvantaged by their circumstances and that the service fully reflects the Council’s ambition to reduce inequality across the borough.

In addition, the model contributes to Mission 1 by strengthening fairness, respect and opportunity within local communities and the local supplier market. The shift to a transparent nationally set rate product ‘NATFED rates’, replacing Wigan Council’s locally defined Schedule of Rates provides clearer commercial arrangements enabling more accessible opportunities for local businesses, while the model itself has been co designed with tenants, operational teams and contractors. A key part of this transformation is bringing contractors with the Council into a more person centred, respectful and accountable way of working that explicitly addresses the stigma that some residents experience simply because they live in a council home. By challenging this stigma, improving communication, and embedding a culture of dignity, the model supports stronger relationships between residents and service providers and promotes a fairer, more inclusive experience for all households.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Building Services Framework Procurement (Housing Services: Repairs and Maintenance)Report 725 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 23 attended
DT
Councillor David Trevor Molyneux MBEExecutive Leader, apologies
KC
Councillor Keith CunliffeDeputy Leader, present
KA
Councillor Kevin Anderson B.A (Hons)Committee Member, present
DA
Councillor Dane AndertonCommittee Member, present
SG
Councillor Susan GamblesCommittee Member, present
PP
Councillor Paul PrescottCommittee Member, apologies
CR
Councillor Christopher ReadyCommittee Member, present
NR
Councillor Nazia RehmanCommittee Member, present
AC
Ann ClarksonOfficer, in attendance
SC
Stuart CowleyOfficer, in attendance
JD
Janet DaviesOfficer, in attendance
LG
Lewis GreenwoodOfficer, in attendance

All 23 on the meeting page

On this subject at Wigan

Search all
  1. Building Services Framework Procurement (Housing Services – Repairs and Maintenance)This decision
  2. Building Services FrameworkAgreed
  3. HRA Building Services FrameworkAgreed
  4. Review of Options for the Council’s Building DLO (Leigh Building Services)Agreed

More from Wigan Cabinet

All decisions
MeetingDecisionOutcome
24 Sep 2026 Exclusion of the PublicThat the public is excluded from the meeting when the Cabinet discusses the following item for the reason set out bel... Decided Open
24 Sep 2026 Medium Term Financial Plan 2027/28 - 2029/30The Cabinet:- (1) notes the updated Medium-Term Financial Plan forecast; (2) notes the forecast budget gap for 2027/2... Approved Open
24 Sep 2026 Annual Standards Report 2025/26The Cabinet approves the . Approved Open
24 Sep 2026 Task and Finish (Cabinet Response) - CLA and PCLA Support in SchoolsThe Cabinet:- (1) notes the Director – Children and Family Services’ response to the Task and Finish Outcome Report; ... Approved Open
27 Aug 2026 Exclusion of the PublicThat the public is excluded from the meeting when the Cabinet discusses the following item for the reason set out bel... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies