CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Winchester City Council
Cabinet, Tuesday 14 October 2025 at 9.30am

Woodman Close, Sparsholt - Final Business Case (less exempt appendix)

Agreed Executive 1 paper

AI summaryWinchester City Council Cabinet approves construction of 5 homes at Woodman Close, Sparsholt, with project budget increased by £101,000 to a total of £2,057,000.

AI summaryIn plain English

Written from the decision wording; the report is not read yetPDF Pro
OutcomeAgreedJCT Design & Build contract to be awarded
Money£2,057,000 totalIncrease of £101,000 on previous budget
What happens nextAward contractCorporate Head of Asset Management to act
Who it affectsSparsholt area and tenantsFive new council homes to be built

What was decided

Cabinet authorised the Corporate Head of Asset Management to award a JCT Design & Build Contract to construct 5 homes at Woodman Close, Sparsholt, and to negotiate easements, wayleaves and related agreements with utility suppliers, telecom and media providers, and neighbours.

Cabinet approved a £101,000 increase in the project budget, setting total scheme cost at £2,057,000, and authorised that full expenditure against that budget, drawing on Homes England funding (subject to award) and Section 106 affordable housing developer contributions.

Cabinet agreed to deploy Section 106 affordable housing developer contribution funding, and authorised the Strategic Director, in consultation with the Cabinet Member for Good Homes, to use up to £1,687,500 of that funding and/or raise rents from Social Rent to Affordable Rent if Homes England money falls short or contingency spending differs.

Why

The scheme is described in the decision as only viable if substantial Section 106 affordable housing developer contribution funding is used.

Homes England funding is being applied for, but only subject to a successful award, so a contingency route is needed.

The fallback measures are intended to keep the scheme affordable to the Housing Revenue Account in net present value terms.

What happens next

Award and enter into a JCT Design & Build Contract for the 5 homes.

Negotiate terms for easements, wayleaves and related legal agreements with utilities, telecom and media providers, and neighbours.

If Homes England funding is not secured or is lower than expected, the Strategic Director and Cabinet Member for Good Homes may deploy up to £1,687,500 of Section 106 funding (£337,500 per unit) and/or raise rents to Affordable Rent.

The money

  • £101,000 Increase in project budget
  • £2,057,000 Total scheme cost
  • £1,687,500 Maximum Section 106 funding fallback if Homes England money is not secured
  • £337,500 Per unit Section 106 funding fallback

Options considered

  • Chosen: Construct 5 homes at Woodman Close using a JCT Design & Build Contract, funded by Homes England (subject to award) and Section 106 contributions
  • Chosen: Fallback: deploy up to £1,687,500 of Section 106 funding and/or raise rents from Social Rent to Affordable Rent if Homes England funding is unavailable or lower than expected. To keep the scheme affordable to the Housing Revenue Account in net present value terms

Implications

  • Financial: Project budget rises by £101,000 to £2,057,000, with up to £1,687,500 of Section 106 funding available as a fallback against Housing Revenue Account net present value.
  • Legal: A JCT Design & Build Contract is to be awarded, alongside easements, wayleaves and related legal agreements with utilities, providers and neighbours.
  • Risk: Scheme viability depends on a successful Homes England funding award; if it is not secured or is reduced, contingency measures are required.
  • Staffing: The Corporate Head of Asset Management acts on contract and easement matters; the Strategic Director, with the Cabinet Member for Good Homes, decides on the fallback.

Who and where

  • Future tenants of the 5 new homes at Woodman Close, Sparsholt
  • Neighbours of the Woodman Close site
  • Utility suppliers, telecom and media providers
  • The council's Housing Revenue Account

Plain English for the jargon

  • JCT Design & Build Contract: A standard UK construction contract where one contractor designs and builds the project.
  • Section 106 (S106): A planning obligation under which a developer contributes money or land to offset the impact of a development, often used to fund affordable housing.
  • Easement: A legal right to use another person's land for a specific purpose, such as running pipes or cables.
  • Wayleave: A licence or agreement allowing a utility, such as pipes, cables or wires, to cross or use someone's land.
  • Homes England: The government agency that funds new affordable housing in England.
  • Social Rent: Rents set by a national formula, typically well below market rent, for low income households.
  • Affordable Rent: Rents set at up to 80% of local market rent for eligible households.
  • Housing Revenue Account (HRA): The ringfenced account councils use to manage income and spending on their own housing stock.
  • Net present value (NPV): A measure of the current value of a scheme's future income and costs, used to test its financial viability.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

RESOLVED: 1. That the Corporate Head of Asset Management be authorised to: a. award and enter into a JCT Design & Build Contract to construct 5 homes at Woodman Close, Sparsholt. b. negotiate and agree terms for easements, wayleaves and related agreements with utility suppliers, telecom/media providers and neighbours and relevant legal agreements to facilitate the development. 2. That an increase of £101,000 in the project budget be approved to meet the total scheme cost of £2,057,000, and expenditure of £2,057,000 against that budget be authorised, applying Homes England funding (subject to successful award) and the council’s S106 affordable housing developer contribution funding to the total scheme budget to enable viability. 3. That it be noted that the proposed scheme is only viable if substantial S106 affordable housing developer contribution funding is used, and that the deployment of S106 affordable housing developer contribution funding to develop the proposed scheme be agreed. 4. That if Homes England funding is not available or lower than anticipated or contingency spending is different than expected, the Strategic Director, in consultation with the Cabinet Member for Good Homes, be authorised to deploy S106 affordable housing developer contribution funding of up to £1,687,500 (£337,500 per unit) and/or increase rents from Social Rent to Affordable Rent to ensure the scheme remains affordable to the Housing Revenue Account in terms of net present value of scheme, as set out in 2.15 of report CAB3451 and the exempt appendix.
Word for word from the decision Winchester published for this meeting. Source: democracy.winchester.gov.uk

Follow this further

Built from Winchester's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
CAB3451 Woodman Close Sparsholt: Final Business CaseReport Copy on its way

At this meeting

Whole meeting

More from Winchester Cabinet

All decisions
MeetingDecisionOutcome
25 Aug 2026 Membership of Cabinet bodies etc.That Councillor Laming be appointed as a deputy on the Hampshire and Solent Combined County Authority Planning Adviso... Decided Open
25 Aug 2026 Minutes of the previous meeting held on 21 July 2026That the minutes of the previous meeting held on 21 July 2026 be agreed as a correct record. Agreed Open
25 Aug 2026 St. Peter's Car Park: Proposed affordable housing scheme (less exempt appendix)That capital expenditure of up to £480,000 be authorised to allow for professional fees, site investigative work and ... Noted Open
25 Aug 2026 Central Winchester Regeneration (CWR) - updated business case (less exempt appendix)That the updated Business Case as presented in Appendix A and Exempt Appendix B be noted. 2. That the submission, by ... Noted Open
25 Aug 2026 To note the future items for consideration by Cabinet as shown on the September 2026 Forward Plan.That the list of future items as set out in the Forward Plan for September 2026 be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies