Cabinet, Thursday 12 February 2026 at 9.30am

Capital Investment Strategy 26-36

Approved Executive 6 papers

AI summaryWinchester City Council Cabinet has recommended a 10-year Capital Investment Strategy totalling £385.6 million to full Council for approval. Cabinet also approved capital spending on IMT equipment, Guildhall clocktower repairs and Guildhall improvements for 2026/27 to 2027/28.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApproved
Money£385.6 millionTotal 10-year programme: £56.1m General Fund and £329.5m HRA
What happens nextFull Council approvalRecommendations to Council are not subject to call-in
Who it affectsDistrict residents, tenants, businessesInvestment in housing, regeneration, climate, leisure and community assets

What was decided

Cabinet recommended to Council the Capital Investment Strategy, including the Capital Programme, the Minimum Revenue Provision Policy, the Flexible Use of Capital Receipts Strategy and the prudential indicators. Report P2

Subject to Council approval, Cabinet approved three capital spends for 2026/27 to 2027/28: £154,000 of IMT equipment, £250,000 of Guildhall clocktower repairs, and £3,300,000 of Guildhall capital improvements. Report P4, P86, P96, P149

Cabinet noted the requirement to ensure members have the right knowledge and skills for their governance role, and that ongoing training and support should be continued and enhanced as required. Report P5, P186

Why

The Capital Investment Strategy is an integral part of the Medium-Term Financial Strategy and impacts directly on the Treasury Management Strategy, supporting delivery of the Council Plan. Report 1.1, P52, P53

The Chief Finance Officer considers the proposed 10-year programme affordable, sustainable and prudent, and the council has a long history of successfully managing its capital assets while minimising risk. Report 2.6, 2.9

The council's overall risk appetite is defined as Moderate, with an Open appetite for Greener Faster and Good Homes for All priorities, reflecting the urgency of the climate crisis and the need for new homes. Report P177, P180

What happens next

Full Council will consider the recommendations; these are not subject to call-in. Report P2

The Scrutiny Committee was due to consider the report at its meeting on 10 February 2026, and any matters it raised were to be reported to the Cabinet meeting. Report 6.4

Inclusion in the programme does not authorise spending: each scheme requires a full project report, business case and an Equality Impact Assessment before approval, in line with Financial Procedure Rule 7.4. Report 8.2, P132, P134

The money

  • £154,000 IMT equipment capital spend in 2026/27, financed from the IMT reserve Report P4, P149, P150, P151
  • £250,000 Essential refurbishment works to the Guildhall clocktower in 2026/27, improving fire safety and thermal comfort Report P4, P96
  • £3,300,000 Capital improvements to the Guildhall in 2026/27 and 2027/28, part of an estimated £5m of works identified in a recent condition survey Report P4, P86
  • £385.6 million Total 10-year capital programme to 2035/36, comprising General Fund and Housing Revenue Account Report 2.1, P68
  • £56.1 million General Fund element of the 10-year capital programme Report 2.1, P68
  • £329.5 million Housing Revenue Account element of the 10-year capital programme Report 2.1, P68
  • £150.7 million Financing from prudential borrowing across the 10-year programme Report 2.2
  • £49.2 million Financing from capital grants and contributions across the 10-year programme Report 2.2

Options considered

  • Chosen: Approve the Capital Investment Strategy 2026 to 2036 as recommended. Strategy is considered affordable, sustainable and prudent, and supports delivery of the Council Plan and carbon neutral goals Report P2, 2.9
  • Rejected: Have no capital programme at all. The council would no longer be able to meet its objectives Report 12.1
  • Rejected: Plan for an alternative capital programme. The council would no longer be able to meet its objectives Report 12.1

Implications

  • Financial: 10-year programme financed by £150.7m prudential borrowing, £131.0m revenue including earmarked reserves, £54.7m capital receipts and £49.2m capital grants and contributions. Report 2.2
  • Financial: Capital Financing Requirement is forecast to increase by up to £3.1m during 2026/27 subject to full delivery of the programme. Report P115
  • Financial: Cost of borrowing has risen from circa 2% at end of 2021 to between 5% and 6% at end of 2025, challenging the viability of potential build projects. Report P103
  • Risk: Project delivery capacity is identified as one of the most significant capital-specific risks, mitigated by robust business cases and resource planning. Report 2.7, P41
  • Risk: Local Government Reorganisation may affect future capital priorities, both before and after reorganisation, and could present new opportunities such as additional sites for new build housing. Report P42, P99
  • Climate: £40.8m is allocated to the Greener Faster priority, including £38.8m for energy efficiency of the council's housing stock and £2m for energy management projects. Report 7.1, P70, P72, P73
  • Equalities: An Equality Impact Assessment must be completed before any scheme can proceed to spend, in line with Financial Procedure Rule 7.4. Report 8.2
  • Legal: The Capital Investment Strategy follows the latest MHCLG and CIPFA codes of practice, with individual projects considered for legal and procurement issues separately. Report 3.1, 3.2

Who and where

  • Council tenants, with £38.8m for energy efficiency of the housing stock and major repairs and maintenance Report P72, P77
  • Private households needing home adaptations, with £15.3m of Disabled Facilities Grant Report P80
  • Community groups, parish councils and small businesses receiving CIL-funded capital grants between £10,000 and £200,000 Report P61, P87
  • Local sports users, with investment in River Park pavilion, play areas, sport pavilion at North Whiteley and Meadowside Leisure Centre Report P59, P90, P91, P92
  • Members of the council, who require ongoing training and support to undertake their governance role Report P5, P186
  • Staff in legal, finance, procurement and estates teams, who support delivery of the capital programme Report P133, P134
  • Residents and businesses in the Central Winchester Regeneration area, with provisional property purchase budget and £4.5m CIL capital grant for infrastructure Report P82

Timeline

  • 10 February 2026: Scrutiny Committee due to consider the report Report 6.4
  • 12 February 2026: Cabinet meeting and decision date
  • 2026/27: IMT equipment spend of £154,000, including corporate network and MFD replacement Report P4, P149, P150, P151
  • 2026/27: Guildhall clocktower repairs of £250,000 Report P4, P96
  • 2026/27 and 2027/28: Guildhall capital improvements of £3,300,000 Report P4, P86
  • Early April 2026: Deadline for formal bids for the former River Park Leisure Centre site Report P93
  • 2026 to 2036: Period covered by the 10-year capital programme totalling £385.6m Report 2.1, P68
  • 31 March 2030: Current expiry date of the MHCLG direction on flexible use of capital receipts Report P129

Plain English for the jargon

  • MRP: Minimum Revenue Provision: the statutory annual charge to revenue that repays capital debt over the life of an asset
  • CFR: Capital Financing Requirement: the council's cumulative outstanding amount of debt finance for capital purposes
  • HRA: Housing Revenue Account: the ring-fenced account that holds rents and service charges for council housing
  • GF: General Fund: the council's main revenue account for non-housing services
  • CIL: Community Infrastructure Levy: a developer contribution used to fund local infrastructure
  • CWR: Central Winchester Regeneration: a major redevelopment of central Winchester
  • LGR: Local Government Reorganisation: restructuring of local authority boundaries and functions
  • MTFS: Medium-Term Financial Strategy: the council's multi-year financial planning document
  • PAC Board: Programme and Capital Board: governance body that oversees capital project business cases and delivery
  • SAPS: Strategic Asset Purchase Scheme: the council's framework for acquiring property to support strategic objectives
  • IMT: Information Management and Technology: the council's IT service, shared with Test Valley Borough Council
  • Prudential Code: CIPFA framework requiring councils to demonstrate that capital spending is affordable, prudent and sustainable
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9

Resolved

That Cabinet recommend to Council* 1. The Capital Investment Strategy be approved including: a) the Capital Programme and Capital Programme Financing (Appendices A and B to report CAB3539 ); b) the Minimum Revenue Provision (MRP) Policy Statement (Appendix E of the report ); c) the Flexible Use of Capital Receipts Strategy (Appendix G of the report); and d) the prudential indicators detailed in the report and Appendix F of the report. That Cabinet: 2. Subject to Council approval of the capital programme, the following capital expenditure be approved: a) IMT equipment in 2026/27 (£154,000) as detailed in paragraph 11.8.6 of the report; b) Repairs to the Guildhall clocktower in 2026/27 (£250,000); and c) Capital improvements to the Guildhall in 2026/27 and 2027/28 (£3,300,000) 3. That the requirement to ensure Members have the right knowledge and skills to undertake their governance role be noted and that the ongoing support and training offered to members is continued and enhanced as required. *NB recommendations to Council are not subject to call-in
Word for word from the decision Winchester published for this meeting. Source: democracy.winchester.gov.uk

Follow this further

Built from Winchester's papers

What the report saysPro

Report to Cabinet, 26 pages

Recommendations

That Cabinet recommends to Council:

1. The Capital Investment Strategy be approved including: • the Capital Programme and Capital Programme Financing (Appendices A and B to the report); • the Minimum Revenue Provision (MRP) Policy Statement (Appendix E); • the Flexible Use of Capital Receipts Strategy (Appendix G); and • the prudential indicators detailed in the report and Appendix F.

That Cabinet:

2. Subject to Council approval of the capital programme, approves the following capital expenditure: • IMT equipment in 2026/27 (£154,000) as detailed in paragraph 11.8.6; • Repairs to the Guildhall clocktower in 2026/27 (£250,000); and • Capital improvements to the Guildhall in 2026/27 and 2027/28 (£3,300,000)

3. Notes the requirement to ensure Members have the right knowledge and skills to undertake their governance role and that the ongoing support and training offered to members is continued and enhanced as required. CAB3539

IMPLICATIONS:

1 COUNCIL PLAN OUTCOME

1.1The investment of capital resources will contribute to the achievement of the council’s main objectives and priorities in the Council Plan. The Capital Strategy is an integral part of the Medium-Term Financial Strategy and impacts directly on the Treasury Management Strategy.

1.2More detail on specific projects supporting the priorities in the Council Plan is set out in section 11.2.

Financial implications

2.1The forecast capital programme over the next 10 years to 2035/36 totals £385.6 million of which £56.1 million is General Fund and £329.5 million is Housing Revenue Account.

2.2The proposed financing is made up of £150.7 million of prudential borrowing, £131.0 million from revenue including earmarked reserves, £54.7 million of capital receipts, and £49.2 million of capital grants and contributions.

2.3Further details are provided in the supporting information section below and in the appendices to the strategy.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CAB3539 Appendix AAppendix 2 pages Download
PDF
CAB3539 Appendix BAppendix 1 pages Download
PDF
CAB3539 Appendix CAppendix 1 pages Download
PDF
CAB3539 Appendix DAppendix 1 pages Download
PDF
CAB3539 Appendix EAppendix 3 pages Download
PDF
Capital Investment Strategy 26-36Report 26 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 11 attended
MT
Councillor Martin TodChairperson, present
NC
Councillor Neil Cutler OBEVice-Chair, present
SC
Councillor Steve CramoysanCommittee Member, present
KB
Councillor Kathleen BeckerCommittee Member, present
KL
Councillor Kelsie LearneyCommittee Member, present
JP
Councillor Jackie PorterCommittee Member, present
MR
Councillor Mark ReachCommittee Member, present
LT
Councillor Lucille ThompsonCommittee Member, present
JB
Councillor James BathoGuest, in attendance
SG
Councillor Stephen GodfreyGuest, in attendance
CH
Councillor Caroline HorrillGuest, in attendance

On this subject at Winchester

Search all
  1. Capital Investment Strategy 26-36This decision
  2. To consider and determine the following Recommended Minutes: Cabinet held 12 February 2026 - Capital Investment Strategy 2026 - 36 (CAB3539)Approved
  3. Capital Investment Strategy 2026-2036Noted

More from Winchester Cabinet

All decisions
MeetingDecisionOutcome
25 Aug 2026 Membership of Cabinet bodies etc.That Councillor Laming be appointed as a deputy on the Hampshire and Solent Combined County Authority Planning Adviso... Decided Open
25 Aug 2026 Minutes of the previous meeting held on 21 July 2026That the minutes of the previous meeting held on 21 July 2026 be agreed as a correct record. Agreed Open
25 Aug 2026 St. Peter's Car Park: Proposed affordable housing scheme (less exempt appendix)That capital expenditure of up to £480,000 be authorised to allow for professional fees, site investigative work and ... Noted Open
25 Aug 2026 Central Winchester Regeneration (CWR) - updated business case (less exempt appendix)That the updated Business Case as presented in Appendix A and Exempt Appendix B be noted. 2. That the submission, by ... Noted Open
25 Aug 2026 To note the future items for consideration by Cabinet as shown on the September 2026 Forward Plan.That the list of future items as set out in the Forward Plan for September 2026 be noted. Noted Open