Resolved
Resolved – That the report be noted.
Policy and Performance - Transformation and Resources Committee noted this item on Thursday 3 December 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That the report be noted.
1.1This report sets out the financial monitoring information for this Committee in a format consistent across the Policy and Performance Committees. The report aims to give Members sufficient detail to scrutinise budget performance for the Directorate. The financial information is for Quarter 2 (July-September 2015) and was reported to Cabinet on 5 November 2015. The Directorate is forecasting a year end revenue underspend of £3 million which mainly arises from Treasury Management activity.
2 BACKGROUND AND KEY ISSUES
2.1Members of the Policy and Performance Committees have previously requested that financial monitoring information is provided as a standard item at each Committee.
2.2Since September 2012 regular revenue and capital monitoring reports have been submitted to Cabinet as a means of providing regular, detailed updates on budget performance.
2.3The Coordinating Committee has agreed that in order to fulfil its corporate and strategic scrutiny role, it will continue to review the full versions of the most up to date monitor reports at its future scheduled meetings.
2.4The relevant sections from the most recent revenue and capital monitoring reports reported to Cabinet are summarised into a bespoke report for each Policy and Performance Committee and include the following:
Performance against the revenue budget Performance against in year efficiency targets Performance against the capital budget 3 PERFORMANCE AGAINST REVENUE BUDGETS QUARTER 2 (JULY- SEPTEMBER 2015)
CHANGES TO THE AGREED BUDGET
3.1Changes to the agreed Transformation & Resources Budget for 2015-16 Original Approved Approved Revised Net Budget Budget Net Budget Budget Changes Changes Prior Mths Quarter 2
Transformation & 31,947 -604 -193 31,150 Resources Net Cost of Services 31,947 -604 -193 31,150
3.1.1 The main budget movements in quarter two relate to the transfer of the Liquid Logic support team from Transformation & Resources to Children & Young People and an adjustment to the support services budget.
4 VARIATIONS
4.1The report will use RAGBY ratings that will highlight under and overspends and place them into ‘risk bands’. The ‘risk band’ classification is: Extreme: Overspends - Red (over +£301k), Underspend Yellow (over - £301k) Acceptable: Amber (+£141k to +£300k), Green (range from +£140k to - £140k); Blue (-£141k to -£300k)
4.22015/16 Projected Budget variations £000’s
Directorates Revised Forecast (Under) RAGBY Change Budget Outturn Overspend Class from Quarter 2 prev Transformation & Resources 31,150 28,150 -3,000 Y -1,811 TOTAL 31,150 28,150 -3,000 -
4.3There has been an improvement of £1.8 million in the quarter resulting in a year end forecast underspend of £3 million. This is largely from savings (£2.5 million of the overall total) within Treasury Management. This is due to the continued use of internal funds to minimise the need to externally borrow and further projected slippage within the Capital Programme (which delivers one- off in year savings). Further savings have arisen from continued vacancies during the year across a number of service areas.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Financial Monitoring 2015/16 Quarter 2 (July: September 2015)Report | 99 KB | DownloadRead as text |
Follow Policy and Performance - Transformation and Resources Committee at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Mar 2016 | Customer Relationship Management System Update ReportResolved – (1) That the report be noted. (2) That the CRM development be placed on the Work Programme. (3) That an up... | Noted | Open |
| 22 Mar 2016 | Community Safety PartnershipResolved – (1) That the content of the report and the progress made in the delivery of the two 2020 pledges, be noted... | Noted | Open |
| 22 Mar 2016 | Financial Monitoring 2015/16 Quarter 3Resolved – That the report be noted. | Noted | Open |
| 22 Mar 2016 | Work Programme Update ReportResolved –That with the addition of an item on the Customer Relationship Management System, the work programme be app... | Approved | Open |
| 1 Feb 2016 | Local Welfare Assistance SchemeResolved – (1) That this Committee acknowledges the progress made and recommends to Cabinet that the actions introduc... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.