Resolved – That (1) the report be noted; and (2) further updates be provided to Committee on a six monthly basis. Councillor Jeff Green declared a non-pecuniary interest in this item by virtue of his membership of Magenta Housing. He remained in the meeting room whilst the matter was debated.
Word for word from the decision Wirral published for this meeting.Source: democracy.wirral.gov.uk
That further updates be provided to Committee on a six monthly basis.
1 SUPPORTING INFORMATION
Reasons for recommendations
1.1To provide Committee with assurance that the Council is taking appropriate measures to comply with Contract Procedure Rules.
2.0OTHER OPTIONS CONSIDERED
2.1The Council’s Contract Procedure Rules require this report be presented to this Committee. There is an option over the frequency of the reporting and whilst this report covers a 12 month period it is recommended that future report should cover a six month period.
3.0BACKGROUND INFORMATION
3.1Revised Contracts Procedure Rules that came into effect on the 1 December 2013 significantly changed the rules and the way they are applied.
3.2The Rules placed the responsibility for the approval of contracts on officers of the Council and a new process of Officer Decision Notices (ODN’s) was introduced.
3.3Each contract listed on the ODN’s directory has a corresponding ODN document which identifies the purpose and details of the contract and is signed by the authorised Designated Senior Manager, Procurement Officer or Assistant Director of Finance (S151 Officer) according to the nature and value of the contract.
3.4Each contract is posted on the Council’s Contracts Register ‘The Chest’, which is the Regional e-Sourcing Portal for the North West local authorities.
3.5A complete review of the CPRs was undertaken and the revised Rules, approved by this committee on the 24 November 2015, came into effect on the 1 April 2016.
3.6Within the revised Rules the Officer Decision Notice was replaced with four, distinct, Procedure Rules Approval Documents (PRAD) - documents of approval are 1-4, for Exceptions to CPR’s (1); Variations to Contracts (2); Extensions to Contracts (3); Contract Award (4).These form the basis of all reports to this Committee in accordance with Rule 16.
3.7The revised CPRs included the adoption of the Public Procurement Regulations 2015, the Transparency Code 2014, and the requirement to publish all contracts over £5,000 in value.
3.8Prior to the implementation of the revised CPR’s in April 2016, Corporate Procurement provided formal training, for officers involved in contracts, between January 2016 and the end of March 2016. A total 230 officers completed the training.
2 3.9 Corporate Procurement have also produced a new online eForm PRAD approval process, and although there have been problems and amendments, which has prevented an earlier report to Members, officers have found that the system now provides a more efficient approval procedure.
3.10From the 1 November 2016 a new eLearning module, designed by Corporate Procurement with the OD Team, entitled ‘Understanding Procurement Processors’ was introduced as mandatory for managers to complete, the new CPR’s being fundamental to the completion of the course. To date 52% have completed the module.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Annual governance statement 2025/26Resolved – That the draft Annual Governance Statement for 2025/26, including the actions planned in 2026/27 to addres...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.