External Audit Plan for Wirral Council 2025-26

Noted Finance 2 papers

AI summaryWirral Audit and Risk Management Committee notes the 2025-26 external audit plan prepared by Grant Thornton for the Council's statutory financial statements.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedPlan prepared by Grant Thornton for 2025-26
MoneyWithin existing revenue budgetSpecific fee not stated in papers
What happens nextOfficers to work with Grant ThorntonRisk-based audit to be completed
Who it affectsWirral Council Statement of AccountsStatutory financial statements 2025-26

What was decided

The Committee noted the external audit plan for 2025-26 prepared by Grant Thornton. Report P19

Why

The Council is required to comply with statutory requirements relating to external audit, and the plan forms part of discharging those requirements. Report 5.1

Grant Thornton will carry out a risk-based audit focusing on areas where there is a risk of material misstatement in the accounts. Report 7.1

If concerns are not addressed, the Council may not meet statutory requirements for the Statement of Accounts, with knock-on effects on value for money, financial resilience and reputation. Report 7.2

What happens next

Officers will work collaboratively with Grant Thornton to complete the audit as soon as possible.

If the audit runs beyond the planned timeline, the Director of Finance, Chair of the Committee and Committee Services will be liaised with, including the possibility of additional Committee meetings.

Options considered

  • Chosen: Note the external audit plan as prepared by Grant Thornton

Implications

  • Legal: The plan forms part of arrangements to discharge statutory external audit requirements. Report 5.1
  • Risk: Risk that the audit process may extend beyond the timeline set out in the plan; officers will work to manage this.
  • Risk: Risk to Statement of Accounts, value for money, financial resilience and reputation if auditor concerns are not addressed. Report 7.2
  • Staffing: No direct staffing, ICT or assets implications. Report 6.1
  • Equalities: No equality implications arising from this report; documents may not be accessible and an alternative format can be requested. Report 9.2, P20
  • Climate: No direct impact on emissions of greenhouse gases. Report 10.1
  • Other: No direct implications for community wealth or crime and disorder. Report 11.1, 12.1

Who and where

  • Wirral Council as audited body Report 5.1, P19
  • Grant Thornton as external auditor Report 7.1, P19
  • Audit and Risk Management Committee Report P22

Timeline

  • 25 June 2025: Previous meeting considered the 2024-25 external audit plan and update. Report P27
  • 2 September 2025: Previous meeting considered 2023-24 external audit recommendations update. Report P26
  • 19 February 2026: Previous meeting considered 2024/25 Statement of Accounts, Annual Audit Report and Annual Governance Statement. Report P25
  • 2026-06-24: Committee meeting considers the 2025-26 external audit plan. Report P22

Plain English for the jargon

  • Value for Money: An auditor's assessment of whether an organisation has used its resources economically, efficiently and effectively.
  • Risk-based audit: An audit approach that concentrates effort on areas identified as carrying a higher risk of material misstatement.
  • Statement of Accounts: The Council's annual statutory financial statements.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

Resolved – That the external audit plan for Wirral Council’s Statutory financial statements for 2025/26 as prepared by Grant Thornton be noted.
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Audit and Risk Management Committee

Financial implications

4.1The audit fees are set out in the Audit Plan and will be met from within existing revenue budget provision.

5.1The Council is required to comply with the statutory requirements relating to external audit. The Audit Plan forms part of the arrangements to discharge those requirements.

6.0RESOURCE IMPLICATIONS: STAFFING, ICT AND ASSETS

6.1None arising directly from this report.

7.0RELEVANT RISKS

7.1Grant Thornton will complete a risk-based audit whereby they will focus audit effort on those areas where they have identified a risk of material misstatement in the accounts.

7.2If any concerns identified by Grant Thornton are not addressed by the Council, there is a risk that the Council will not be able to meet its statutory requirements in respect to the Statement of Accounts as well as impacting upon the Value for Money and Financial Resilience of the Council and the Council’s reputation. 7.3 There is a risk that the audit process may extend beyond the timeline set out in the Audit Plan. Officers will work collaboratively with Grant Thornton to complete the audit as soon as possible and, if required, will liaise with the Director of Finance, Chair of Audit & Risk Management Committee, and Committee Services regarding any consequential changes, including the need for additional Committee meetings.

8.0ENGAGEMENT/CONSULTATION

8.1None arising directly from this report.

Equality implications

9.1Wirral Council has a legal requirement to make sure its policies, and the way it carries out its work, do not discriminate against anyone. An Equality Impact Assessment is a tool to help council services identify steps they can take to ensure equality for anyone who might be affected by a particular policy, decision or activity.

9.2There are no equality implications arising specifically from this report. The files attached may not be suitable to view for people with disabilities, users of assistive technology or mobile phone devices. Interested stakeholders should contact [email protected] should these documents be required in an accessible format.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
The Audit Plan for Wirral CouncilAppendix 1 1.1 MB Download
PDF
External Audit Plan for Wirral Council 2025-26Report 133 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 8 attended
HC
Councillor Helen CameronVice-Chair, present
SK
Councillor Stuart KellySpokesperson, present
JW
Councillor Jerry WilliamsCommittee Member, apologies, sent representative
JS
Councillor James Stewart LaingDeputy, present as substitute
CB
Councillor Colin BaldwinCommittee Member, present
HG
Councillor Harry GormanSpokesperson, present
BH
Councillor Brenda HallChair, present
GW
Councillor Gillian WoodCommittee Member, present

On this subject at Wirral

Search all
  1. External Audit Plan for Wirral Council 2025-26This decision
  2. External Audit Plan for Merseyside Pension Fund 2025-26Noted
  3. External audit plan - statement of accounts 2024/25Noted
  4. External audit plan merseyside pension fund 2025-26Noted
  5. External Auditors Annual Report 2024/25 - Statutory RecommendationsApproved
  6. 2023-24 External Audit Recommendations UpdateNoted

More from Wirral Audit and Risk Management Committee

All decisions
MeetingDecisionOutcome
24 Jun 2026 External Audit Plan for Merseyside Pension Fund 2025-26Resolved – That the external audit plan for the Merseyside Pension Fund’s Statutory financial statements for 2025/26 ... Noted Open
24 Jun 2026 Annual governance statement 2025/26Resolved – That the draft Annual Governance Statement for 2025/26, including the actions planned in 2026/27 to addres... Approved Open
24 Jun 2026 Birkenhead town centre management action plan updateResolved – That 1. The progress made to date in implementing the Birkenhead Town Centre Management Action Plan recomm... Noted Open
24 Jun 2026 Annual cctv surveillance activity reportResolved – That the report be noted. Noted Open
24 Jun 2026 Annual update of whistleblowing concerns raised in the municipal year 2025/26Resolved – That the report be noted. Noted Open