That: (1) the principle of participating in the scheme to enable the development of building at Wirral Waters of 500 homes and associated commercial tenancies as an investment vehicle for the Council and to kick-start wider development in the area, be agreed; (2) Cabinet notes that, subject to receipt of a viable business case, the Council being able to satisfy its statutory requirements and budgetary approval, the Council would achieve this objective through: (a) entering into a lease of 500 residential units for up to 50 years; (b) taking an option to acquire 350 residential units at the end of ... view the full minutes text for item 88.
Word for word from the decision Wirral published for this meeting.Source: democracy.wirral.gov.uk
WIRRAL WATERS ONE (LEGACY PROJECT) DOCK ROAD, WALLASEY, WIRRAL
COUNCILLOR PHIL DAVIES
Cllr Phil Davies, Leader of Wirral Council, said:
“This is an exciting proposition which will play a significant part in helping us to deliver the new housing which the area so desperately needs and will also help kick-start even more development on one of the key regeneration sites in Wirral.
“We are seeing huge confidence in Wirral as an area to invest in at the moment. Our plans for regeneration throughout the borough are gaining momentum, and we will see more exciting news in the coming days and weeks about developments on a number of different sites.
“There is still work to be done to take this project forward but, combined with other developments already progressing at the site, this represents a major breakthrough for Wirral Waters.”
REPORT SUMMARY
This report provides a progress report on the potential residential projects in Wirral Waters (now likely to be accelerated given the Housing Infrastructure Fund announcement on 1 February 2018) and specifically focuses on the Wirral Waters One (Legacy) project.
The number of issues on this project has reduced significantly over the past few months (from over 40). There are still issues as set out in the report, resolution of which are considered fundamental to further progress.
The Wirral Waters One project is being considered on an investment basis by the Council and therefore an acceptable rate of return on the investment will be required. It seeks Cabinet’s views in principle on progressing with the Wirral Waters One project, subject to the legal, market economy investor principle and commercial matters set out in this report. Without satisfaction of all these matters the Council could not proceed with this project. Negotiations on a number of matters set out in this report are continuing and therefore will be subject to change.
A further report would be brought back to Cabinet or the Leader of the Council once the outcome of the various matters are known.
RECOMMENDATION/S
It is recommended that Cabinet
1 Agrees to the principle of participating in the scheme to enable the development of building at Wirral Waters of 500 homes and associated commercial tenancies as an investment vehicle for the Council and to kick-start wider development in the area.
2 Notes that, subject to receipt of a viable business case, the Council being able to satisfy its statutory requirements and budgetary approval, the Council would achieve this objective through
(a) entering into a lease of 500 residential units for up to 50 years; (b) taking an option to acquire 350 residential units at the end of the 50 year lease set out in (a) for a long term (in the region of 200 years); (c) establishing a trading company limited by shares to hold the 50 lease and, from year 11, to manage residential tenancies; (d) funding of the trading company referred to in (c) for years 1 to 10; and (e) providing assurance to the funder that the terms of the lease of the 500 residential units can be met from years 11 to 50.
3 Authorises officers to continue to negotiate with the current and potential landowner, developer, landlord and funder and obtain such expert opinions as they consider fit in order to deliver a commercially viable scheme commensurate with the Council’s level of investment
4 Requests a further report, at Cabinet or for a cabinet member decision, at such time as officers are in a position to recommend final approval to enter agreements and establish a Council company for delivery of the scheme. SUPPORTING INFORMATION
1.0REASON/S FOR RECOMMENDATION/S
1.1To ensure that the Council meets its legal and fiduciary requirements.
2.0OTHER OPTIONS CONSIDERED
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring Quarter 1 2020/21That (1) the Cabinet recommends to the Council the approval of additional funding for the schemes referred to in para...
Financial Monitoring Outturn 2019-20That (1) Revenue (a) it be noted that the gross expenditure has been balanced to gross income with the appropriate al...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.