CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Wirral Borough Council
Cabinet, Monday 27 July 2020

Capital Monitoring Quarter 1 2020/21

Approved Executive 1 paper

Cabinet approved this item on Monday 27 July 2020. Below is the council's own wording, with the papers it was decided on.

Item108

Resolved

That (1) the Cabinet recommends to the Council the approval of additional funding for the schemes referred to in paragraph 3.3. of the report and as follows: · Integrated Transport Block Funding - £1,150,000 of allocated to Wirral Council by Liverpool City Region Combined Authority to support the delivery of the Combined Authority Transport Plan Programme in 2020/21. The programme is a package of schemes designed to support increased numbers of journeys to be undertaken by sustainable active modes reducing resident’s reliance on the private car and reducing carbon emissions. · Highways Maintenance Funding - £2,149,000 of allocated to Wirral Council by the Liverpool City Region Combined Authority to support maintenance of the network in 2020/21. The programme of investment in our highway assets will support improvements to roads/footways/bridges and lighting. · Disabled Facility Grant - £4.163,000 allocated to Wirral Council by the Ministry of Housing, Communities and Local Government to provide grants for people with a permanent disability of any sort – including physical and learning disabilities, sensory impairments and mental illness. The grants are to help towards making changes or adaptations to a home to allow the person to continue living there. (2) the Cabinet recommends to the Council the approval of the revised Capital Programme of £131.7 million for 2020-21.
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Cabinet

CABINET

27 JULY 2020

QUARTER 1 2020/21 CAPITAL FINANCIAL MONITORING

Councillor Janette Williamson, Cabinet Member for Finance and Resources said:

“The Council initially set out details of its Capital Programme for 2020/21 on 2 March 2020 shortly before the whole country was plunged into the unprecedented crisis of Covid-19 which, as everyone knows, meant the council – almost overnight – had to completely re-prioritise and re- design how it operated and delivered services.

“The pandemic has meant that many schemes have had to be delayed or deferred. It has also placed extreme financial pressures on the local authority overall, so a review of the Capital Programme is taking place to see how any financial savings could be made as a result of either delaying, deferring or withdrawing some schemes altogether from the programme.”

REPORT SUMMARY

This report provides an update on the progress of the Capital Programme 2020/21 at the end of June 2020. It recommends that Cabinet agree the 2020/21 Capital Programme of £131.7 million which takes account of re-profiling, additional funding requirements and grant variations identified since the Capital Programme was formally agreed on 2nd March 2020.

This matter is a key decision which affects all Wards within the Borough.

RECOMMENDATION/S

1 The Cabinet recommends to Council the approval of additional funding for the schemes referred to in paragraph 3.3.

2 The Cabinet recommends to Council the approval of the revised Capital Programme of £131.7 million for 2020-21. SUPPORTING INFORMATION

1.0REASON/S FOR RECOMMENDATION/S

1.1Regular monitoring and reporting of the Capital Programme enable decisions to be taken faster which may produce revenue benefits and will improve financial control in Wirral Council.

2.0OTHER OPTIONS CONSIDERED

2.1No other options have been considered.

3.0BACKGROUND INFORMATION

3.1Capital Programme 2020/21 Position by Directorate

Table 1: Wirral Council 2020/21 Full Year Capital Budget and Forecast Position Budget Forecast Variance Variance Programme £m £m £m % Adult Care & Health 7.747 9.195 1.448 19% Children, Families & Education 5.500 7.534 2.034 37% Cross Cutting Initiatives 5.500 5.500 0.000 0% Neighbourhoods 25.136 38.934 13.798 55% Regeneration & Place 51.646 61.150 9.504 18% Resources 8.314 9.347 1.033 12% Total 103.843 131.660 27.817 27%

NB: items of significant scheme variation are included below

3.1.1 Table 1 provides an update on the 2020/21 capital Programme. A number of significant variations have arisen since the programme was agreed in March 2020. These include the re-profiling of expenditure into and out of the 2020/21 financial year, inclusion of additional grant funded schemes, variations to spend forecasts and the inclusion of potential new capital schemes that are seeking funding via this report. Further detail is provided below.

3.1.2 Table 2 below categorises the increase in the forecast programme:

Table 2: Movement between previously approved Capital Budget and Forecast Position New Approved Reprofiling Grant Revised Budget from 19-20 Funding New bids Budget Programme £m £m £m £m £m Adult Care & Health 7.747 1.448 - - 9.195 Children, Families & Education 5.500 2.034 - - 7.534 Cross Cutting Initiatives 5.500 - - - 5.500 Neighbourhoods 25.136 10.487 3.299 0.012 38.934 Regeneration & Place 51.646 4.466 4.163 0.875 61.150 Resources 8.314 1.033 - - 9.347 Total 103.843 19.468 7.462 0.887 131.660 3.2 Reprofiling of expenditure from 2019/20

3.2.1 Since the approval of the Capital Programme a number of schemes have had reprofiled budget into 2020/21 from 2019/20. The schemes with significant variation are shown in the table below.

3.2.2 A number of these schemes were those that only received full formal permission to be included in the programme in March 2020, leaving little time for the schemes to start within that financial year.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Monitoring Quarter 1 2020/21Report 144 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 14 attended
PH
Councillor Pat HackettCommittee Member, present
EG
Councillor Elizabeth GreyCommittee Member, present
CJ
Councillor Chris JonesCommittee Member, present
TJ
Councillor Tony JonesCommittee Member, present
AL
Councillor Anita LeechCommittee Member, present
JM
Councillor Julie McManusCommittee Member, apologies
CS
Councillor Christine SpriggsCommittee Member, apologies
TU
Councillor Thomas UsherCommittee Member, present
JW
Councillor Janette WilliamsonCommittee Member, present
SW
Councillor Stuart WhittinghamCommittee Member, present
PS
Paul SatoorOfficer, expected
PM
Philip McCourtOfficer, expected

All 14 on the meeting page

On this subject at Wirral

Search all
  1. Capital Monitoring Quarter 1 2020/21This decision
  2. Capital Monitoring Quarter 1 (2026/27)Approved
  3. Capital Monitoring Quarter 3 2025/26Approved
  4. Capital Monitoring Quarter 3 2025/26Approved
  5. 2025-26 capital monitoring quarter 2Approved
  6. 2025-26 Capital Monitoring Quarter 2Approved

More from Wirral Cabinet

All decisions
MeetingDecisionOutcome
27 Jul 2020 MinutesThat the Minutes of the meetings of the Cabinet held on 17 and 24 February 2020 be confirmed as a correct record. Decided Open
27 Jul 2020 Executive Key Decisions Taken Under Delegated PowersThat the following Key Decisions taken under delegated authority for the period 21 February 2020 to the date of publi... Noted Open
27 Jul 2020 Financial Monitoring Outturn 2019-20That (1) Revenue (a) it be noted that the gross expenditure has been balanced to gross income with the appropriate al... Noted Open
27 Jul 2020 Treasury Management Annual Report 2019/20That (1) the 2019/20 Treasury Management Annual Report be agreed and recommended to the Council for approval at its m... Agreed Open
27 Jul 2020 Exempt Information - Exclusion of the press and publicThat, under section 100 (A) (4) of the Local Government Act 1972, the public be excluded from the meeting during cons... Decided Open