Resolved
Resolved – That (1) the proposed actions be approved; and (2) details of future corporate risk register workshops be circulated to Members in due course.
Audit and Risk Management Committee approved this item on Monday 24 September 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That (1) the proposed actions be approved; and (2) details of future corporate risk register workshops be circulated to Members in due course.
1.1The committee needs to understand the authority’s most significant risks in order to fulfil its role of providing independent assurance of the Council’s Risk Management Framework.
2.0OTHER OPTIONS CONSIDERED
2.1None.
3.0BACKGROUND INFORMATION
3.1My report of 23 July 2018 indicated that work would be undertaken in the following month to develop a revised Corporate Risk Register.
3.2A facilitated discussion with SLT took place on 14 August 2018. This sought to draw out the Team’s views on the current most critical risks facing the Council. A perspective on key risk areas had been prepared by the Director of Finance and Investment in order to initiate discussion. This is summarised in the table below.
Risk Area 1. Unsustainable future financial situation 2. Integrated Commissioning Hub unable to mitigate demand 3. Over-exposure to risk from regeneration projects 4. Insufficient public engagement in local decision making 5. Public Health outcomes do not improve resulting in increased reactive services 6. Staff engagement and fit with the new operating model 7. Failure to recognise the opportunities from working across the Liverpool City Region 8. Local Plan not published/implemented resulting in intervention 9. Failure to work more commercially and generate income to mitigate funding gaps 10.Ineffective Business Continuity arrangements 11.Safeguarding of vulnerable children and adults 12.Information Governance 13.Failure of digital infrastructure 14.Wirral Growth Company does not proceed / deliver anticipated benefits
3.3The Team were asked to consider those risks, their criticality and potential impact on the Corporate Plan. Team members were also asked for their individual views on additional risks of potential corporate significance. The impact of Brexit, failures in the management of health and safety and of assets, the effectiveness of preventative activity and the impact of market failures were amongst the additional areas proposed for consideration.
3.4The discussion within the workshop was summarised in a report for SLT, from which a draft list of possible corporate risks was produced. This was subjected to further consideration and comment by the Team to refine the definitions and to begin populating a risk register template with the output from the work undertaken to date.
Further action planned
3.5In September 2018 SLT will agree their view of the revised corporate risks, how they are to be defined and the criticality of each.
3.6As proposed and agreed at the last meeting of this committee there will be a workshop for Members so that their views on the most significant risks facing the Council are taken into account in developing the revised baseline Corporate Risk Register. Arrangements for the workshop are currently being finalised.
3.7The key controls for each risk and the responsibilities for these will be determined and documented.
3.8An exercise will be undertaken to draw out the appetite of political and executive leaders for each of the revised corporate risks.
4.1There are no immediate financial implications arising directly from this report.
5.1There are no immediate legal implications arising directly from this report.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Development of the Revised Corporate Risk RegisterReport | 104 KB | DownloadRead as text |
Follow Audit and Risk Management Committee at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Jun 2026 | External Audit Plan for Wirral Council 2025-26Resolved – That the external audit plan for Wirral Council’s Statutory financial statements for 2025/26 as prepared b... | Noted | Open |
| 24 Jun 2026 | External Audit Plan for Merseyside Pension Fund 2025-26Resolved – That the external audit plan for the Merseyside Pension Fund’s Statutory financial statements for 2025/26 ... | Noted | Open |
| 24 Jun 2026 | Annual governance statement 2025/26Resolved – That the draft Annual Governance Statement for 2025/26, including the actions planned in 2026/27 to addres... | Approved | Open |
| 24 Jun 2026 | Birkenhead town centre management action plan updateResolved – That 1. The progress made to date in implementing the Birkenhead Town Centre Management Action Plan recomm... | Noted | Open |
| 24 Jun 2026 | Annual cctv surveillance activity reportResolved – That the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.