QUARTER 1 BUDGET MONITORING REPORT - CAPITAL

Approved Committee 1 paper

Council approved this item on Monday 15 October 2018. Below is the council's own wording, with the papers it was decided on.

Item50

Resolved

Resolved (61:0) (One abstention) – That the recommendation contained within minute 11 of Cabinet, be approved.
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Council

MINUTE EXTRACT CABINET 16 JULY 2018

11 QUARTER 1 BUDGET MONITORING REPORT - CAPITAL

Councillor Janette Williamson, Cabinet Member for Finance and Resources, said:

“We are making major investments in Wirral this year – improving infrastructure, the public realm and the local environment which residents are rightly proud of.

This report demonstrates this investment, it provides a helpful summary of our progress, and makes it clear that we are using the resources available to us to their best effect to help improve services for local people”.

Councillor Janette Williamson introduced a report which provided an update on the progress in delivering the Capital Programme 2018/19 at the end of June 2018. It recommended that the Cabinet agreed the 2018/19 Capital Programme of £86.4 million which took into account re-profiling identified during the 2017/18 final accounts process together with any additional grant funding notified to the Council. Expenditure to date was £5.0 million. Appended to the report was the Capital Programme and funding 2018/19.

This matter was a key decision which affected all Wards within the Borough.

The report had been provided for monitoring purposes and no other options were being considered.

Councillor Phil Davies welcomed the capital schemes that were now coming to the forefront.

RESOLVED: That

(1) the spend at Quarter 1 of £5.0 million, with 25% of the financial year having elapsed be noted;

(2) the additional funding for the 7 schemes set out below be approved:

 Pensby Wood fit out costs (£172,000)  Beechwood Recreation Centre Additional Works (£430,000)  Frankby Cemetery Extension (£90,000)  Floral Pavilion Audio Mixing Desk Replacement (£35,000)  BAMN Commercial Settlement (£305,000)  Floral Pavilion Chiller Unit (£55,000)  The Oval Grandstand Structural Works (£55,000)

(3) the revised Capital Programme of £86.4 million set out below be agreed and referred to the Council:

Capital Programme 2018/19 at 30 June 2018

Capital Revised Actual Strategy Programme Spend June 2018 £000 £000 £000 Adult Care & Health 7,912 8,543 143 Children & Families 19,099 20,852 2,200 Environment 225 50 0 Finance and Resources 5,213 4,287 130 Highways & Transport 13,787 20,409 1,954 Housing & Planning 7,542 7,791 375 Jobs & Growth 16,785 18,697 0 Law & Order 0 83 38 Leisure & Recreation 3,998 5,679 117 Total expenditure 74,561 86,391 4,957

and (4) the additional grants detailed below be agreed:

Significant Variations (> £0.2m) to the 2018/19 Programme

Scheme £000 Adult Care & Health Pensby Wood - re-profiling from 2017/18 £0.310m; 482 additional requirement £0.172m.

Children & Families Primary Places - re-profiling from 2017/18 742 Healthy Pupils Fund - additional grant allocation 245 Special Educational Needs and Disabilities (SEND) - 206 additional grant allocation. Improvement Plan funded by the flexible use of capital receipts - re-profiling 1,100

Environment Cemetery extensions and improvements - re-profiling from 226 2017/18

Finance and Resources Windows 10 rollout - re-profiling - £0.1m carried forward from 1,100 2017-18 and £1.0m brought forward from 2019/20 Data Centre - re-profiling from 2017/18 339 Improvement Plan - originally to be funded from capital (2,700) receipts but now from revenue Fund to assist land assembly - re-profiling from 2017/18 246

Highways & Transport Bridges - re-profiling from 2017/18 £0.707m and additional 857 grant notification £0.150m. Dock bridges – re-profiling from 2017/18 £0.610m; 752 additional private sector contribution £0.142m Sustainable Transport Enhancement Programme (STEP) 702 schemes - re-profiling from 2017/18 Transport for Growth - re-profiling £2.168m and grant 3,318 confirmation £1.150 Street lighting and LED replacement - re-profiling from 349 2017/18 Transport Advisory Group feasibility studies - additional 245 grant notification BAMN Commercial settlement 305

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
QUARTER 1 BUDGET MONITORING REPORT: CAPITALReport 99 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

63 of 65 attended
GW
Councillor Geoffrey WattMayor, present
TS
Councillor Tony SmithDeputy Mayor, present
RA
Councillor Ron AbbeyCommittee Member, present
TA
Councillor Tom AndersonCommittee Member, present
BB
Councillor Bruce BerryCommittee Member, present
JB
Councillor Jo BirdCommittee Member, present
CB
Councillor Chris BlakeleyCommittee Member, present
AB
Councillor Allan BrameCommittee Member, present
PB
Councillor Phillip BrightmoreCommittee Member, present
DB
Councillor David Burgess-JoyceCommittee Member, present
KC
Councillor Kate CannonCommittee Member, present
CC
Councillor Chris CarubiaCommittee Member, present

All 65 on the meeting page

On this subject at Wirral

Search all
  1. QUARTER 1 BUDGET MONITORING REPORT - CAPITALThis decision
  2. 2026/27 Revenue Budget Monitoring for Quarter One (The Period to 30 June 2026)Noted
  3. 2026/27 Budget Monitoring for Quarter One (the period to 30 June 2026)Agreed
  4. 2026-27 budget monitoring report quarter 1Decided
  5. 2025/26 Budget Monitoring for Quarter ThreeNoted
  6. 2025/26 Budget Monitoring for Quarter Three (the period to 31 December 2025)Noted

More from Wirral Council

All decisions
MeetingDecisionOutcome
20 Jul 2026 MINUTESResolved – That the minutes of the meetings held on 13 May 2026 and 20 May 2026 be approved as a correct record. Approved Open
20 Jul 2026 2025-26 Capital OutturnResolved – That 1. the virements of budget referred to in Appendix F of the report be approved; and 2. the bids in Ap... Approved Open
20 Jul 2026 Revisions to the ConstitutionResolved – That the amendments to the Constitution, as detailed in sections 3.2 to 3.7 of the report, be approved. Approved Open
20 Jul 2026 Appointment of Independent PersonsResolved – That the appointment of the following Independent Persons of the Constitution and Standards Committee be a... Approved Open
20 Jul 2026 Annual Report of the Audit and Risk Management CommitteeResolved – That the ARMC Annual Report for 2025-26 be approved. Approved Open