Spend Freeze Programme NO PO NO Pay Compliance

Noted Finance 1 paper

Audit and Risk Management Committee noted this item on Monday 27 January 2020. Below is the council's own wording, with the papers it was decided on.

Item44

Resolved

Resolved - That the report be noted.
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Audit and Risk Management Committee

Recommendation

Members note the report. SUPPORTING INFORMATION

1.0REASONS FOR REPORT

1.1To provide the members with an overview of progress against the spend freeze programme.

1.2To provide the Members with assurance that the Council is taking appropriate measures to ensure that an effective NO PO NO PAY Policy is applied and monitored.

2.0OTHER OPTIONS CONSIDERED

2.1No other options considered.

3.0BACKGROUND INFORMATION

3.1The spending freeze programme report was presented to members at the previous meeting on the 18th November by the Director of Finance and Investment which summarised the progress of the spend freeze which was implemented in October 2019.

3.2The aim of the spend freeze is to target discretionary expenditure and cease spending as much as possible to eradicate the call on Council reserves.

3.3The Council faces the risk of a significant in-year overspend. If this is not mitigated the Councils’ general balances could be depleted to an extent that takes them below the agreed minimum level, which is not financially sustainable.

3.4The imposing of a spending freeze in 2019-20 is being introduced to rectify this untenable financial position. It is considered prudent to act early rather than leave corrective action to the last minute.

3.5All staff have been communicated this through the intranet and staff briefings. This exercise is not designed to get in the way of business critical expenditure. It is not about creating a huge unwieldy bureaucracy. What this means in practice is that all expenditure is frozen unless it is on the exception list or it has agreement from an officer group which includes the Chief Executive and the Director of Finance and Investment. The Spending freeze will continue for as long as is necessary to control the overspend. Weekly random sampling will be undertaken and any unauthorised spend will be reported to the Senior Leadership Team (SLT).

3.6It should be made clear that activities supporting spend freeze may not be quantified in one robust “savings” figure, as this would be a comparison to what “would have” been spent, which cannot be recorded.

3.7The wider financial impact of spending freeze will be demonstrated across the Directorates in Quarter 3 Revenue Reporting as a reduction to the budget gap. 3.8 The procurement compliance report was also presented at the previous meeting by the Head of Procurement which included a section regarding progress of the Purchase orders (POs) and No PO no Pay policy.

4.0Spending freeze

4.1Further to the verbal update provided to the Audit & Risk Management Committee on 18 November 2019, a spending freeze remains in force. Purchase orders approved have continued to be monitored and a system generated report has recently been created to facilitate this process. The following information is available from the most recent review:

 607 purchase orders reviewed, value £2,692k  81 PO approvers included in the review  465 purchase order data as returned by officers to clarify the reason for the spend, and where appropriate, the reason for using a retrospective order.  There is an escalation process in place for officers who have not responded to the request for information

4.2Instances of non-compliance are being addressed with individual PO approvers, their manager and SLT.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Spend Freeze Programme NO PO NO Pay ComplianceReport 140 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 22 attended
JG
Councillor Jeff GreenChair, present
TA
Councillor Tom AndersonCommittee Member, present
KC
Councillor Kate CannonCommittee Member, present
AG
Councillor Andrew GardnerCommittee Member, apologies, sent representative
PG
Councillor Phil GilchristSpokesperson, present
KG
Councillor Karl GreaneyCommittee Member, apologies, sent representative
KH
Councillor Kathy HodsonCommittee Member, present
AJ
Councillor Adrian JonesSpokesperson, present
MS
Councillor Michael SullivanCommittee Member, absent
SW
Councillor Stuart WhittinghamCommittee Member, present
GW
Councillor Gillian WoodCommittee Member, present
JR
Councillor Jean RobinsonDeputy, present as substitute

All 22 on the meeting page

On this subject at Wirral

Search all
  1. Spend Freeze Programme NO PO NO Pay ComplianceThis decision
  2. Spend Freeze Programme and No PO No Pay ComplianceNoted

More from Wirral Audit and Risk Management Committee

All decisions
MeetingDecisionOutcome
24 Jun 2026 External Audit Plan for Wirral Council 2025-26Resolved – That the external audit plan for Wirral Council’s Statutory financial statements for 2025/26 as prepared b... Noted Open
24 Jun 2026 External Audit Plan for Merseyside Pension Fund 2025-26Resolved – That the external audit plan for the Merseyside Pension Fund’s Statutory financial statements for 2025/26 ... Noted Open
24 Jun 2026 Annual governance statement 2025/26Resolved – That the draft Annual Governance Statement for 2025/26, including the actions planned in 2026/27 to addres... Approved Open
24 Jun 2026 Birkenhead town centre management action plan updateResolved – That 1. The progress made to date in implementing the Birkenhead Town Centre Management Action Plan recomm... Noted Open
24 Jun 2026 Annual cctv surveillance activity reportResolved – That the report be noted. Noted Open