STREET LIGHTING IMPROVEMENT PROGRAMME, PROGRESS REPORT

Noted Committee 2 papers

Environment, Climate Emergency and Transport Committee noted this item on Wednesday 20 October 2021. Below is the council's own wording, with the papers it was decided on.

Item36

Resolved

That the contents of this report be noted and the team be congratulated for the successful delivery and output of the project.
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Environment, Climate Emergency and Transport Committee

ENVIRONMENT, CLIMATE EMERGENCY AND TRANSPORT COMMITTEE Wednesday, 20 October 2021

Report Title: STREET LIGHTING IMPROVEMENT PROGRAMME, PROGRESS REPORT Report of: DIRECTOR OF NEIGHBOURHOOD SERVICES

APPENDIX 1 – PROGRESS REPORT

1. Progress, performance and outcomes of the SSE Contract

1.1Governance and financial monitoring: The NEC3 Engineering and Construction Contract (ECC) form of contract with SSE has been diligently and professionally managed with a robust governance process under the highways capital programme portfolio and with a dedicated external specialist contract manager procured through the council’s professional services supply contract with Amey Consulting Ltd. Wirral Council provided project Senior Responsible Owner, Project Manager and Senior User roles to the Project Board from existing staffing resources. The contract supervision was provided from discrete external resources until January 2021 and from internal council staffing resources since then. Amey has authorised compensation events (variations) totalling £731,849 for additional works ordered under the SSE contract for reasons of expediency and best value, including: essential variations to electrical safety processes; additional cabling (where post-contract faults have been identified); additional column replacements (where stock condition was found to have deteriorated significantly since the 2017 survey); the inclusion of works to high mast lighting which posed a serious public safety risk; electric vehicle charging provision and a section of lighting infrastructure on the A5139 Docks Link Key Route Network, which had due to have been included in a separate contract for safety barrier replacements in 2018, but was unable to be completed because of insufficient technical information and budget provision at the time. The final outturn contract valuation price expected to be contractually due to SSE is £10,022,745, which will financed from the available budget provision.

1.2Progress and completion: Works on the SSE contract commenced on 2 October 2019 with a completion date of 1 October 2021. By August 2021 some 23,930 LED lanterns had been installed and 9,122 columns had been replaced under the contract with SSE. The final numbers ordered are 27,565 lanterns and 9,884 columns. At the time of writing this report, the current accepted programme shows completion on 8 October 2021. However,as a result of contract compensation events currently being evaluated the contractual completion date will be amended, but will not be later than the end of December 2021. Progress has been monitored monthly and at project board. Initially SSE concentrated resources on the installation of lanterns and by May 2020 had installed 1235 units more than programmed. During the same period the number of columns installed was 878 units less than programmed. When the pandemic restrictions were introduced in March 2020, the contract works were designated an essential service, SSE introduced safe working procedures and progressed both lantern and column installations with a focus upon column installations to restore the 878-unit deficit. At all times throughout the project total unit installations were ahead Page 1 of 6 of programme in terms of the Salix loan requirements. Progress has been consistently reported to the public using a dashboard format in a dedicated page on the council’s website here:

https://www.wirral.gov.uk/parking-roads-and-travel/major-projects/led-replacement- programme-phase-2

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Enc. 1 for STREET LIGHTING IMPROVEMENT PROGRAMME, PROGRESS REPORTReport 106 KB DownloadRead as text
PDF
STREET LIGHTING IMPROVEMENT PROGRAMME, PROGRESS REPORTReport 88 KB Download

At this meeting

Whole meeting

Who was there

11 of 20 attended
EG
Councillor Elizabeth GreyChair, present
HC
Councillor Helen CollinsonCommittee Member, present
SF
Councillor Steve FoulkesCommittee Member, present
CO
Councillor Clare O'HaganCommittee Member, present
IW
Councillor Irene WilliamsCommittee Member, present
BB
Councillor Bruce BerryCommittee Member, present
MC
Councillor Michael CollinsCommittee Member, present
SR
Councillor Simon R MountneySpokesperson, present
LR
Councillor Les RowlandsCommittee Member, present
CC
Councillor Christopher CookeVice-Chair, present
AB
Councillor Allan BrameCommittee Member, present
MJ
Mike JonesCommittee Officer, in attendance

All 20 on the meeting page

On this subject at Wirral

Search all
  1. STREET LIGHTING IMPROVEMENT PROGRAMME, PROGRESS REPORTThis decision
  2. Highways Infrastructure Asset Management Policy, Strategy and Street Lighting PolicyNoted
  3. Potholes and Street Lighting - UpdateNoted
  4. Street Lighting Investment ProgrammeDecided
  5. Street Lighting - Maintenance and Improvement UpdateNoted
  6. Street Lighting - Scottish Power PerformanceNoted

More from Wirral Environment, Climate Emergency and Transport Committee

All decisions
MeetingDecisionOutcome
8 Jul 2026 2026-27 budget monitoring report quarter 1Resolved – That the Environment, Climate Emergency and Transport Committee notes: 1. the forecast revenue position fo... Decided Open
8 Jul 2026 Carbon Budget Performance Report 2025-26It was agreed that the following two agenda items, “” and “Environment and Climate Emergency Action Plan Progress Rep... Agreed Open
8 Jul 2026 Environment and Climate Emergency Action Plan Progress Report 2025-26It was agreed that the two agenda items, “Carbon Budget Performance Report 2025-26” and “Environment and Climate Emer... Agreed Open
8 Jul 2026 Environment, climate emergency and transport performance reportResolved – That the Environment, Climate Emergency and Transport Committee notes the content of the report and highli... Decided Open
8 Jul 2026 Work ProgrammeIt was agreed that items requested on weed treatment provisions would be a part of the Hot House briefings. Briefing ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies