Resolved
That (1) the acceptance of a £4.6 million interest free loan from SALIX to deliver Phase 2 of the LED replacement programme be ... view the full minutes text for item 9.
Cabinet decided this item on Monday 16 July 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
That (1) the acceptance of a £4.6 million interest free loan from SALIX to deliver Phase 2 of the LED replacement programme be ... view the full minutes text for item 9.
Cabinet is requested to:
(1) Approve acceptance of a £4.6 million interest free loan from SALIX to deliver Phase 2 of the LED replacement programme; and
(2) Approve the implementation of the procurement strategy outlined in this report, in accordance with Contract Procurement Rules, to enable both the Phase 2 LED programme and the Street Lighting Column replacement programme to be delivered. SUPPORTING INFORMATION
1.0REASON/S FOR RECOMMENDATION/S
Street lighting is an important element of the transport network because of the safety and confidence it brings to road users. Wirral Council is committed to improving the efficiency of its services and options provided by new LED technology enable the street lighting service to minimise future energy use and reduce carbon emissions. Investment in the infrastructure is required to ensure that the Council maintain a fit for purpose asset in accordance with nationally accepted asset management principles.
Phase 1 of the LED programme delivered in 2015/6 saw the conversion of 7,533 high energy sodium lamps replaced with Light Emitting Diode (LED) lighting. Phase 2 will see the conversion of more than 27,000 units.
This will result in all lamps in Wirral being replaced over the next three years and will result in all Wirral’s lanterns being LED lights by March 2021.
2.0OTHER OPTIONS CONSIDERED
Do nothing – this option has been rejected as the street lighting assets are in poor condition due to a lack of previous investment resulting in significant deterioration and subsequent high maintenance revenue spending. Lack of investment increases the Council’s exposure to third party insurance claims. Public perception regarding street lighting provision and repair is poor.
3.0BACKGROUND INFORMATION
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Street Lighting Investment ProgrammeReport | 133 KB | DownloadRead as text |
Follow Cabinet at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Jul 2020 | MinutesThat the Minutes of the meetings of the Cabinet held on 17 and 24 February 2020 be confirmed as a correct record. | Decided | Open |
| 27 Jul 2020 | Executive Key Decisions Taken Under Delegated PowersThat the following Key Decisions taken under delegated authority for the period 21 February 2020 to the date of publi... | Noted | Open |
| 27 Jul 2020 | Capital Monitoring Quarter 1 2020/21That (1) the Cabinet recommends to the Council the approval of additional funding for the schemes referred to in para... | Approved | Open |
| 27 Jul 2020 | Financial Monitoring Outturn 2019-20That (1) Revenue (a) it be noted that the gross expenditure has been balanced to gross income with the appropriate al... | Noted | Open |
| 27 Jul 2020 | Treasury Management Annual Report 2019/20That (1) the 2019/20 Treasury Management Annual Report be agreed and recommended to the Council for approval at its m... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.