City Region Sustainable Transport Settlement Highway Structural Maintenance Programme 2022-23

Approved Committee 4 papers

Environment, Climate Emergency and Transport Committee approved this item on Thursday 21 July 2022. Below is the council's own wording, with the papers it was decided on.

Item24

Resolved

Resolved – That (1) The allocation of indicative grant funding likely to be allocated to Wirral Council in the City Region Sustainable Transport Settlement (CRSTS) Combined Authority Transport Plan programme (Highways Structural Maintenance) amongst the relevant subject areas over the next 4 years, as set out in Appendix 1 to this report be approved and; (2) The proposed programme of works for Wirral’s Carriageways, Footway Improvements and Bridge Maintenance for 2022/23, using grant funding allocated to Wirral Council by Liverpool City Region Combined Authority (LCRCA) in the 2022/23 City Region Sustainable Transport Settlement (CRSTS), Combined Authority Transport Plan Programme (Highways Structural Maintenance), as set out in Appendix 2 to this report be approved and; (3) the indicative RAG rated highway network condition matrix as set out in Appendix 3 to this report, to be used by officers as one of the decision tools when developing highway structural maintenance programmes be accepted, and The Director of Neighbourhood Services, in consultation with the Chair and Party Spokespersons of the Environment, Climate Emergency and Transport Committee, be authorised to revise or amend the delivery or implementation of the work programmes, as deemed necessary, having due regard for the available resources and applicable risk-based prioritisation of locations selected for intervention and treatment.
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Environment, Climate Emergency and Transport Committee

Recommendations

The Environment, Climate Emergency and Transport Committee is recommended to:

(1) Approve the allocation of indicative grant funding likely to be allocated to Wirral Council in the City Region Sustainable Transport Settlement (CRSTS) Combined Authority Transport Plan programme (Highways Structural Maintenance) amongst the relevant subject areas over the next 4 years, as set out in Appendix 1 to this report; (2) Approve the proposed programme of works for Wirral’s Carriageways, Footway Improvements and Bridge Maintenance for 2022/23, using grant funding allocated to Wirral Council by Liverpool City Region Combined Authority (LCRCA) in the 2022/23 City Region Sustainable Transport Settlement (CRSTS), Combined Authority Transport Plan Programme (Highways Structural Maintenance), as set out in Appendix 2 to this report;

(3) Accept the indicative RAG rated highway network condition matrix as set out in Appendix 3 to this report, to be used by officers as one of the decision tools when developing highway structural maintenance programmes, and..

(4) Authorise the Director of Neighbourhood Services, in consultation with the Chair and Party Spokespersons of the Environment, Climate Emergency and Transport Committee, to revise or amend the delivery or implementation of the work programmes, as deemed necessary, having due regard for the available resources and applicable risk-based prioritisation of locations selected for intervention and treatment. SUPPORTING INFORMATION

Reason for recommendations

1.1To ensure that the Council can comply with its statutory duty, to maintain the public highway in Wirral, as set out in the Highways Act 1980, Road Traffic Regulations Act 1984, Road Traffic Act 1988, Local Government Act 2000, and the Traffic Management Act 2004.

1.2An element of this funding will be specifically allocated to Wirral Council for delivery of schemes on the Liverpool City Region’s Key Route Network (KRN), supporting the Council’s main strategic routes providing links to economic growth and regeneration sites, and cannot be used for any other purpose. The Council will inevitably incur risk reputational damage should it not accept funding specifically allocated to invest in the KRN.

2.0OTHER OPTIONS CONSIDERED

2.1The Council could decide to not accept the grant funding offered. This is not considered to be an appropriate option given that the programme identified within this report enables the Council to comply with its statutory duties.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
City Region Sustainable Transport Settlement Highway Structural Maintenance Programme 2022-23Report 486 KB DownloadRead as text
PDF
Enc 1. for Highway Structural Maintenance Programme 2022-23: Confirmation of Funding and Works ProgrammesReport 112 KB Download
PDF
Enc 2. for Highway Structural Maintenance Programme 2022-23: Confirmation of Funding and Works ProgrammesReport 95 KB Download
PDF
Enc 3. for Highway Structural Maintenance Programme 2022-23: Confirmation of Funding and Works ProgrammesReport 2.7 MB Download

At this meeting

Whole meeting

Who was there

10 of 19 attended
EG
Councillor Elizabeth GreyChair, present
SF
Councillor Steve FoulkesCommittee Member, present
SP
Councillor Sue PercyCommittee Member, present
TS
Councillor Tony SmithCommittee Member, present
PC
Councillor Paul ConnollyCommittee Member, apologies
AG
Councillor Andrew GardnerSpokesperson, present
LF
Councillor Leah FraserCommittee Member, present
VW
Councillor Vida WilsonCommittee Member, present
HG
Councillor Harry GormanVice-Chair, present
NG
Councillor Naomi GrahamCommittee Member, present
OO
Councillor Orod OsanlouCommittee Member, present
KA
Ken AbrahamOfficer, expected

All 19 on the meeting page

On this subject at Wirral

Search all
  1. City Region Sustainable Transport Settlement Highway Structural Maintenance Programme 2022-23This decision
  2. Transport for the City Region Resource FundingNoted
  3. City region sustainable transport settlement combined authority transport plan programme 2026/27Approved
  4. City region sustainable transport settlement – highway structural maintenance programme 2026-27Approved
  5. Liverpool City Region Local Nature Recovery StrategyDecided
  6. Approval of the Liverpool City Region Local Nature Recovery StrategyDecided

More from Wirral Environment, Climate Emergency and Transport Committee

All decisions
MeetingDecisionOutcome
8 Jul 2026 2026-27 budget monitoring report quarter 1Resolved – That the Environment, Climate Emergency and Transport Committee notes: 1. the forecast revenue position fo... Decided Open
8 Jul 2026 Carbon Budget Performance Report 2025-26It was agreed that the following two agenda items, “” and “Environment and Climate Emergency Action Plan Progress Rep... Agreed Open
8 Jul 2026 Environment and Climate Emergency Action Plan Progress Report 2025-26It was agreed that the two agenda items, “Carbon Budget Performance Report 2025-26” and “Environment and Climate Emer... Agreed Open
8 Jul 2026 Environment, climate emergency and transport performance reportResolved – That the Environment, Climate Emergency and Transport Committee notes the content of the report and highli... Decided Open
8 Jul 2026 Work ProgrammeIt was agreed that items requested on weed treatment provisions would be a part of the Hot House briefings. Briefing ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies