CITY REGION SUSTAINABLE TRANSPORT SETTLEMENT – HIGHWAY STRUCTURAL MAINTENANCE PROGRAMME 2026-27
ApprovedCommittee4 papers
AI summaryWirral's Environment, Climate Emergency and Transport Committee approved the 2026/27 highway maintenance programme, with total anticipated funding of £6,975,000, and delegated authority to amend delivery to the Director of Neighbourhood Services.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedCarriageways, footways and bridge maintenance for 2026/27
Money£6,975,000 total anticipatedIncludes £1,700,000 expected Pothole funding
What happens nextDelivery between April 2026 and March 2027Programme may be amended by Director of Neighbourhood Services
Who it affectsWirral road users, Key Route NetworkPlus ward members consulted on locations
What was decided
The Committee approved the proposed programme of works for the Council's Carriageways, Footway Improvements and Bridge Maintenance for 2026/27, using CRSTS grant funding allocated by the Liverpool City Region Combined Authority, and the spending of that grant once accepted by the Section 151 Officer, as set out in Appendix 2. Report P2
The Director of Neighbourhood Services was authorised to revise or amend the delivery or implementation of the work programmes, having regard for available resources and risk-based prioritisation, in consultation with the Chair and Party Spokespersons of the Committee. Report P3
Why
To enable the Council to comply with its statutory duty to maintain the public highway under the Highways Act 1980, the Road Traffic Regulations Act 1984, the Road Traffic Act 1988, the Local Government Act 2000 and the Traffic Management Act 2004. Report 1.1
To accept funding specifically allocated for the Liverpool City Region's Key Route Network supporting strategic routes to economic growth and regeneration sites, avoiding reputational risk of not accepting it. Report 1.2
An element of funding is ring-fenced to the Key Route Network and cannot be used for any other purpose, and all five-year CRSTS settlement is conditional on adequate programme delivery and monitoring reports to the LCRCA. Report 1.2, 3.3
What happens next
The Section 151 Officer will accept the grant funding, and a grant funding agreement will be executed between the Council and the LCRCA for 2026/27 CRSTS funding. Report 4.1, 5.2, 5.3
Works will be delivered between April 2026 and March 2027, with the proposed programme continually reviewed based on road network condition data, financial constraints, and consultation with the Chair and Party Spokespersons. Report 3.4, 8.1
Following scheme delivery, the Section 151 Officer will sign a declaration confirming grant funding was appropriately defrayed in accordance with grant conditions. Report 5.3
The money
£3,950,000 Anticipated CRSTS Highways Maintenance grant for 2026/27 (carriageways and footways) Report 3.2
£75,000 Anticipated CRSTS grant for bridge maintenance works in 2026/27 Report 3.2
£1,250,000 Further 2026/27 allocation ring-fenced to the Key Route Network (expected to be confirmed) Report 3.2
£1,700,000 Anticipated additional Department for Transport Pothole funding for 2026/27 Report 3.2
£6,975,000 Total anticipated funding for 2026/27 highways maintenance Report 3.2, 4.1
£5,275,000 CRSTS Highways Maintenance allocation for 2026/27 (must be used in year for highways maintenance only) Report 4.1
Options considered
Chosen: Approve the proposed programme of works using CRSTS grant funding and delegate amendment authority to the Director of Neighbourhood Services. Enables the Council to comply with its statutory duties and accept Key Route Network funding Report 2.1, P1, P2, P3
Rejected: Not utilise the grant funding offered or use the funding for a different purpose. Not considered appropriate as the proposed programme enables the Council to comply with its statutory duties Report 2.1
Implications
Financial: Grant-funded planned investment in the highway network will help mitigate future reactive maintenance interventions and help control revenue budget pressures; funding cannot be rolled forward if programmes are not delivered in year. Report 4.2, 7.3
Legal: Section 41 of the Highways Act 1980 imposes a duty on the Council as Highway Authority to maintain highways at public expense; Section 6 devolves a duty to maintain the Liverpool City Region Key Route Network. Report 5.1
Legal: A grant funding agreement will need to be executed between the Council and the LCRCA for 2026/27; the Director of Law and Corporate Services was previously authorised to negotiate and finalise agreements. Report 5.3
Risk: Failure to undertake the programme could result in the Council not meeting statutory duties, further network deterioration, reduced asset value, disproportionate future maintenance costs, adverse claims performance, and potential loss or clawback of funding. Report 7.1, 7.2, 7.3
Climate: Use of low temperature asphalt surfacing materials and surface treatments instead of planing and resurfacing is expected to reduce fossil fuel use, contaminated waste disposal, and carbon emissions, while supporting active travel and improved air quality. Report 10.1, 10.2, 10.3
Equalities: The Council has a legal requirement not to discriminate; an Equality Impact Assessment is available, with accessible format available on request. Report P31, P32
Staffing: Existing staff resources will be used, with delivery through the Highways Service delivery model approved on 16 March 2021 or discrete contracts under Contract Procedure Rules. Report 6.1
Other: The programme supports Community Wealth Building aims including local employment and training through Term Maintenance Contracts, buying supplies locally, and minimising waste and energy consumption. Report 11.1
Who and where
Wirral residents and road users, including bus passengers, cyclists and pedestrians Report 1.1, 3.4, 10.3
Users of the Liverpool City Region Key Route Network in Wirral Report 1.2, 3.2
Ward Members consulted on locations for inclusion in the programme Report 8.1
Liverpool City Region Combined Authority (LCRCA) as funding provider and monitor Report 3.1, 3.3, 5.3
Director of Neighbourhood Services (delivery and amendment authority) Report P3, 3.5
Highways term maintenance contractors and local supply chain Report 6.1
Timeline
16 March 2021: Highways Service delivery model approved by this Committee Report 6.1
21 July 2022: This Committee approved the CRSTS Highways Structural Maintenance grant funding allocation Report 3.1
11 March 2025: Committee authorised the Director of Law and Corporate Services to negotiate and finalise grant funding agreements over the next 3 years Report 3.5
10 March 2026: Committee decision approving 2026/27 highways maintenance programme
April 2026 to March 2027: Works delivery period, with some advance pre-patching for 2027/28 re-surfacing also possible Report 3.4
Plain English for the jargon
CRSTS: City Region Sustainable Transport Settlement: grant funding from the Liverpool City Region Combined Authority for transport investment.
LCRCA: Liverpool City Region Combined Authority, the body allocating CRSTS funding.
Key Route Network: Liverpool City Region's main strategic routes providing links to economic growth and regeneration sites, devolved to the Council under Section 6 of the Highways Act 1980.
Section 151 Officer: The Council's chief finance officer, with delegated authority under Part 3 Section C of the constitution to accept grant funding.
Pothole funding: Additional Department for Transport funding, separate from CRSTS, for pothole and related road maintenance.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item81
Resolved
Resolved – That the Environment, Climate Emergency and Transport Committee approves: 1. the proposed programme of works for the Council’s Carriageways, Footway Improvements and Bridge Maintenance for 2026/27, using any relevant grant funding allocated to the Council by the Liverpool City Region Combined Authority in the City Region Sustainable Transport Settlement - Highways Structural Maintenance allocation, and the spending of the associated grant funding on these works, once accepted by the Council’s Section 151 Officer, as set out in Appendix 2 to this report; 2. that the Director of Neighbourhood Services be authorised to revise or amend the delivery or implementation of the work programmes as referenced in recommendation 1, as deemed necessary, having due regard for the available resources and applicable risk-based prioritisation of locations selected for intervention and treatment, in consultation with the Chair and Party Spokespersons of the Environment, Climate Emergency and Transport Committee.
Word for word from the decision Wirral published for this meeting.Source: democracy.wirral.gov.uk
Report to Environment, Climate Emergency and Transport Committee
Recommendations
The Environment, Climate Emergency and Transport Committee is recommended to approve:
1. the proposed programme of works for the Council’s Carriageways, Footway Improvements and Bridge Maintenance for 2026/27, using any relevant grant funding allocated to the Council by the Liverpool City Region Combined Authority in the City Region Sustainable Transport Settlement - Highways Structural Maintenance allocation, and the spending of the associated grant funding on these works, once accepted by the Council’s Section 151 Officer, as set out in Appendix 2 to this report;
2. that the Director of Neighbourhood Services be authorised to revise or amend the delivery or implementation of the work programmes as referenced in recommendation 1, as deemed necessary, having due regard for the available resources and applicable risk-based prioritisation of locations selected for intervention and treatment, in consultation with the Chair and Party Spokespersons of the Environment, Climate Emergency and Transport Committee. SUPPORTING INFORMATION
1.0REASON/S FOR RECOMMENDATION/S
1.1The recommendations within this report are designed to ensure that the Council can comply with its statutory duty, to maintain the public highway in Wirral, as set out in the Highways Act 1980, the Road Traffic Regulations Act 1984, the Road Traffic Act 1988, the Local Government Act 2000, and the Traffic Management Act 2004.
1.2An element of this funding will be specifically allocated to the Council for delivery of schemes on the Liverpool City Region’s Key Route Network, supporting the Council’s main strategic routes providing links to economic growth and regeneration sites and cannot be used for any other purpose. The Council will inevitably incur risk reputational damage should it not accept funding specifically allocated to invest in the Key Route Network.
2.0OTHER OPTIONS CONSIDERED
2.1The Committee could decide to not utilise the grant funding offered or use the funding for a different purpose. This is not considered to be an appropriate option given that the programme identified within this report enables the Council to comply with its statutory duties.
3.0BACKGROUND INFORMATION
3.1This Committee on 21 July 2022 approved the grant funding allocated to the Council in the City Region Sustainable Transport Settlement (CRSTS) Combined Authority Transport Plan programme (Highways Structural Maintenance) amongst the relevant subject areas, as set out in Appendix 1 to this report.
3.2The grant funding anticipated for Highways Maintenance in 2026/27 is £3,950,000 and £75,000 for bridge maintenance works, set out at Appendix 1 to this report in table 1 and table 2 respectively. Allocation of a further £1,250,000 for 2026/27 ring- fenced to the Key Route Network is also expected to be confirmed is also set out at Appendix 1 to this report in table 3. It is anticipated that during 2026/27, the Department for Transport will allocate an additional Pothole funding approximately £1,700,000. Therefore, the total anticipated funding for 2026/27 is £6,975,000.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Climate Emergency and Transport Committee at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
Carbon Budget Performance Report 2025-26It was agreed that the following two agenda items, “” and “Environment and Climate Emergency Action Plan Progress Rep...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.