Resolved
That the report be noted.
Audit and Risk Management Committee noted this item on Wednesday 26 October 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted.
1.1To provide Members of the Audit & Risk Management Committee with an opportunity to review the resiliency of the Council’s IT Infrastructure and the continuity plans in place.
2 OTHER OPTIONS CONSIDERED
2.1The report is provided for information purposes in response to a direct request by the Chair of the Audit & Risk Management Committee, and as such no other options have been considered.
3 BACKGROUND INFORMATION
3.1IT resilience means being prepared for any type of planned or unplanned disruption or disaster, and the ability to mitigate the risk of downtime allowing the organisation to continue working. IT resilience is an essential part of business resilience.
3.2Planned disruption can include maintenance and upgrades of systems or hardware, move to cloud technology, datacentre changes, integrations. Unplanned disruption can include infrastructure or hardware failures, natural disasters, security breaches, ransomware, or user error.
3.3As services are transformed, there is increasing dependence on digital technologies to deliver these. This leads to an increased risk of being disrupted by cyber-attacks and security breaches.
3.4Business Continuity is used to proactively implement policies, processes, and activities that ensure the smooth running of critical systems during and after a disruption. This includes the identification of risk and management of this, creation of business continuity plans, and validation and testing of processes and procedures.
3.5Disaster Recovery is the act of putting systems, data, and networks back to a previous state after a disruption or disaster has occurred. The disaster recovery plan focuses on the infrastructure and sets out the operational IT recovery processes following disruption, this includes the provision of alternative sites, data backup and offsite replication, and robust servers, storage, and networking.
3.6There are 4 stages to Business Continuity and Disaster Recovery:
o Stage 1: Prevention Mitigation of the risk o Stage 2: Preparedness Planning for the disruption o Stage 3: Response Developing plans detailing actions for responding to a disruption. o Stage 4: Recovery Developing plans detailing the recovery process following a disruption.
3.7Where applications are delivered via Software as a Service (SaaS) the management of the application and underlying infrastructure is delivered by the supplier. The IT role moves to monitoring and audit and ensuring that contracts include appropriate terms and deliverables around security, backup, and recovery options.
Prevention
3.8The Prevention stage is about mitigating the risk of unplanned disruptions.
3.9The risk is mitigated by ensuring suitable measures are in place are the different layers of the IT environment:
o Client devices: Computers, mobile phones, tablets o Network: Firewalls, routers, switches o Storage o Servers: Windows, Unix, Linux o Applications
3.10McAfee endpoint security solution is installed on computers and servers to protect against viruses and cyber-attacks.
3.11Security update processes are in place to ensure client devices, storage, servers, and network devices are kept up to date.
3.12A third party provides 24*7 monitoring of the Council’s Firewalls. The Firewall is the equivalent of the front door into the IT infrastructure.
3.13Cyber security training to provided to all Council staff to help prevent unplanned disruptions.
3.14Key IT staff have undertaken Certified Information Systems Security Professional (CISSP) training. This training is focussed on developing IT security skills and knowledge.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Firewall LogsAppendix A | 720 KB | Download |
PDF |
ICT Continuity ControlsReport | 182 KB | DownloadRead as text |
Follow Audit and Risk Management Committee at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Jun 2026 | External Audit Plan for Wirral Council 2025-26Resolved – That the external audit plan for Wirral Council’s Statutory financial statements for 2025/26 as prepared b... | Noted | Open |
| 24 Jun 2026 | External Audit Plan for Merseyside Pension Fund 2025-26Resolved – That the external audit plan for the Merseyside Pension Fund’s Statutory financial statements for 2025/26 ... | Noted | Open |
| 24 Jun 2026 | Annual governance statement 2025/26Resolved – That the draft Annual Governance Statement for 2025/26, including the actions planned in 2026/27 to addres... | Approved | Open |
| 24 Jun 2026 | Birkenhead town centre management action plan updateResolved – That 1. The progress made to date in implementing the Birkenhead Town Centre Management Action Plan recomm... | Noted | Open |
| 24 Jun 2026 | Annual cctv surveillance activity reportResolved – That the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.