Resolved
That the report be noted .
Audit and Risk Management Committee noted this item on Tuesday 17 January 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted .
AUDIT AND RISK MANAGEMENT COMMITTEE
TUESDAY 17 JANUARY 2023
REPORT TITLE: PLANNING SYSTEM UPDATE
REPORT OF: DIRECTOR OF RESOURCES
REPORT SUMMARY This report is to update the Committee on the implementation of the public portal for planning, building control and the regulatory services.
The portal affects all wards across the Borough.
RECOMMENDATION The Audit and Risk Management Committee is recommended to note the report. SUPPORTING INFORMATION
1. REASON FOR RECOMMENDATION 1.1. To provide Members with an update to review the progress of migration from legacy products for planning, building control and the regulatory services.
2. OTHER OPTIONS CONSIDERED 2.1. Remaining on the legacy product was not an option as the software was approaching it’s end of life support.
3. BACKGROUND INFORMATION 3.1. As part of Wirral Council digital strategy, the application rationalization programme is to reduce the total number of applications in use across the organisation to reduce complexity and enable savings where possible.
3.2Three legacy systems were in use across Building Control, Planning, Land Charges, Environmental Health, Licensing, Housing, Grants, Adaptations and Trading Standards.
3.3The award of the new system was made after of two rounds of procurement to Tascomi, which was then acquired by Idox. No other supplier responded in full to the tender nor could fulfil all of the requirements of the specification.
3.4The procurement exercise was completed using the Crown Commercial Services (CCS) Framework, ‘RM3821 Data and Applications Solutions’. There are 14 suppliers on this framework under ‘Lot 2b – Environmental and Planning’.
3.5Idox group has positioned to become a market leader for regulatory software, having Uniform, Acolaid (legacy) and Idox cloud offerings. These are used by the majority of Councils across the UK.
3.6The Idox cloud solutions first went live for Public Protection – Houses in multiple occupancy (HMO) and Selective licencing in August 2021. Landlords use the public portal to submit applications and payments.
3.7Building Control went live October 2021.
3.8Planning went live June 2022.
3.9Public Protection phase 2 for regulatory services went live September 2022.
Planning Portal
3.10The Planning service receives circa 2000 applications a year and all applications are available to view by the public on the planning portal. The Idox Cloud product has a different look and feel to the previous Acolaid system. It displays less information and users report that it is harder to navigate than the previous system
3.11The planning service has a log of all issues raised by Members and the public, and as of the writing of this report 28 issues have been raised and logged, see Appendix 1 of this report. 3.12. Majority of issues raised are due to the functionality that the Idox portal does not provide compared to the previous planning system. While the Idox cloud portal is different, it is considered to be fit for purpose, as it exceeds the government’s minimum statutory information requirement.
3.13The one issue that is not functionality related is that of the email notifications going into the ‘Junk’ folder. Work is ongoing with Idox to resolve this issue.
3.14Each of the Idox cloud modules has a corresponding log of project issues. Project risks and issues are reviewed daily by the Wirral project manager and on a weekly update call with the Idox project manager.
3.15A monthly report is reviewed by the Digital Programme board and every three weeks by the Regulatory & Environmental Services Replacement Software (RESRS) project board chaired by the Chief Planner.
3.16Issues that occur once a service has gone live are raised with the Idox service desk.
3.17There have been three service outages since the system has gone live. On all three occasions it was related to issues with the server infrastructure. The longest outage meant the system was unavailable over a whole weekend. Idox have now migrated the system to the Amazon Web Services (AWS) cloud to mitigate these issues re- occurring.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Planning System UpdateReport | 298 KB | DownloadRead as text |
Follow Audit and Risk Management Committee at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Jun 2026 | External Audit Plan for Wirral Council 2025-26Resolved – That the external audit plan for Wirral Council’s Statutory financial statements for 2025/26 as prepared b... | Noted | Open |
| 24 Jun 2026 | External Audit Plan for Merseyside Pension Fund 2025-26Resolved – That the external audit plan for the Merseyside Pension Fund’s Statutory financial statements for 2025/26 ... | Noted | Open |
| 24 Jun 2026 | Annual governance statement 2025/26Resolved – That the draft Annual Governance Statement for 2025/26, including the actions planned in 2026/27 to addres... | Approved | Open |
| 24 Jun 2026 | Birkenhead town centre management action plan updateResolved – That 1. The progress made to date in implementing the Birkenhead Town Centre Management Action Plan recomm... | Noted | Open |
| 24 Jun 2026 | Annual cctv surveillance activity reportResolved – That the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.