ECET Quarter 4 Revenue and Capital Monitoring Budget Report
NotedCommittee1 paper
Environment, Climate Emergency and Transport Committee noted this item on Monday 19 June 2023. Below is the council's own wording, with the papers it was decided on.
Resolved – that, 1. the draft, unaudited 2022/23 outturn adverse variance of £3.437m be noted. 2. the draft, unaudited 2022/23 capital variance be noted. 3. Agree the transfer to and use of earmarked reserves, as detailed in Appendix 2 be agreed; 4. the progress on delivery of the 2022/23 savings programme be noted
Word for word from the decision Wirral published for this meeting.Source: democracy.wirral.gov.uk
Report to Environment, Climate Emergency and Transport Committee
Reasons for recommendations
1.1It is vitally important that the Council has robust processes in place to manage and monitor the in-year financial position, to ensure it delivers a balanced position at the end of the year.
1.2Regular monitoring and reporting of the revenue budgets and savings achievements enables decisions to be taken in a timely manner, which may produce revenue benefits and will improve financial control of Wirral Council.
1.3This report presents timely information on the year-end financial position for 2022/23.
2.0OTHER OPTIONS CONSIDERED
2.1The Policy & Resources Committee has previously determined the budget monitoring process to follow and this report details the agreed course of action.
2.2In striving to manage budgets, available options have been evaluated to maintain a balance between service delivery and a balanced budget.
3.0BACKGROUND INFORMATION
3.1As at the end of the financial year 2022/23 the outturn position for the Environment, Climate Emergency and Transport Committee is £3.437m adverse against a budget of £63.761m. The reasons for this are detailed in the table below: TABLE 1: Summary of Committee variances £000 Customer Behaviour Changes Parking income shortfall due hybrid working 590 Mitigated through COVID-19 Reserves -572 Sub-Total 18
Macro-Economic Conditions Nationally agreed Pay Award 560 Additional unforeseen energy costs due to inflation - £657K relates to Street Lighting 657 Waste Contract Inflation increases 1,013 The above variances are mitigated in part due to a reduction in contribution to -600 reserves relating to the Waste Levy Highways Maintenance Increases (Cost of materials and supply chain costs) 900 Sub-Total 2,530
Ongoing Decisions Parking relating to new sites delayed subject to agreement of parking strategy 500 Sub-Total 500
Other Highways Winter Gritting pressures 380 Highways Developer Income Shortfalls 448 Other smaller favourable variances within Highways/Transport Levy -439 Sub-Total 389
NET POSITION 3,437
3.2Income generation has not yet returned to pre pandemic levels as footfall and usage in some areas remains less than it was in 2019/20, which is in line with the national position. There has been some improvement from Quarter 2 onwards due to new pricing structures, and slight increases in footfall now that most areas are fully operational.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Climate Emergency and Transport Committee at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
Carbon Budget Performance Report 2025-26It was agreed that the following two agenda items, “” and “Environment and Climate Emergency Action Plan Progress Rep...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.