Environment, Climate Emergency and Transport Committee approved this item on Monday 19 June 2023. Below is the council's own wording, with the papers it was decided on.
Resolved – that, 1. The extension of the current contract for parking enforcement services with NSL Limited, Registration No. 06033060 for a further period of 5 years be approved . 2. A report be brought back to Committee in advance of the 2026 review, looking at in-house and hybrid provision .
Word for word from the decision Wirral published for this meeting.Source: democracy.wirral.gov.uk
Report to Environment, Climate Emergency and Transport Committee
Appendix 1 - Parking Enforcement Contract Options Five possible options for the parking enforcement contract are detailed below: Option 1 – Cease contract - Not recommended. Ending the contract on 30 September 2023, in line with the initial 5 year timeline, creates risk and a high probability of increased contract expenditure, due to inflationary pressures, feeding into tender submissions. Sefton Council has recently gone down this route and only received 2 bids. Due to the current contract expiring on 30 September 2023 this isn’t a viable option. Pros Due diligence. It can help to provide the best possible value-for-money outcome from procurement activity. It allows testing of the market to secure best service, quality and value. Contract can be tailored for a ‘Best fit’ solution. Set detailed Service Level Agreements. Cons Will probably result in an increase in contract costs on a like for like basis. It could negatively impact on service levels. The cost of staff time involved in the procurement process doesn’t represent bast value given other options available. Evidence suggests that there is little competition in the market at this moment in time.
Option 2 – Extend contract by 5-years as permitted in the original contract – Recommended. Pros Reduced risk of loss of productivity by changing from one service provider to another. The incumbent service provider is performing satisfactorily. NSL Limited have extensive knowledge and experience of enforcement on Wirral. Ability to set a reduced fixed cost on the contract for the first 2-years offering a degree of financial stability. Reinvestment in equipment and technology allow the contractor to work smarter with a more targeted approach and upgrade of vehicles to electric /hybrid. Added value - NSL Limited’s parent company is ‘The Marston Group’ who operate a number of services through their portfolio of businesses i.e. Project Centre Limited (PCL), Videalert and Vortex that are complimentary to the services currently provided to Wirral Council. Added Social Value – continuing ongoing donations and support to local charities and groups. Allows time for the economy to recover and settle before other delivery models are reviewed and considered further. Cons This option may not provide the best possible value-for-money outcome from procurement activity. However, there are risks associated with this, particularly with increasing costs. The option doesn’t allow testing of the market to secure best service, quality and value. However, evidence is suggesting there are very few providers of this service in the market at present and a different supplier may not improve value for money or performance.
Option 3 – Extend for a period less than 5 years to allow further consideration of other options. Not recommended as this option is normally only considered for short periods of say 6 to 12 months to allow for a full re-tender process. Pros Extension period could be set to allow sufficient time (2 to 3 years) for a full evaluation and implementation of the options, particularly if considering bringing the service in-house in full or part. Cons Contractor is unlikely to invest during a shorter extension period. Therefore older and less reliable equipment may be in use. Less ability and willingness to make savings. Risk that contract costs increase. Contractor won’t be able to make the same efficiency savings over the term of a shorter contract length.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Climate Emergency and Transport Committee at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
Carbon Budget Performance Report 2025-26It was agreed that the following two agenda items, “” and “Environment and Climate Emergency Action Plan Progress Rep...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.