Resolved
Resolved (unanimously) – That the revised Capital Programme of £178.1m for 2023/24 be approved, including the virements of budget referred to in Appendix D.
Council approved this item on Monday 10 July 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved (unanimously) – That the revised Capital Programme of £178.1m for 2023/24 be approved, including the virements of budget referred to in Appendix D.
The Policy and Resources Committee is requested to recommend to Council that:
1 the revised Capital Programme of £178.1 million for 2023/24, including the virements of budget referred to in Appendix D of this report be approved, 2 note the financing of the Programme for 2022/23 and 3 note the additional year-end re-profiling of £38.2m from 2022/23 to 2023/24. SUPPORTING INFORMATION
1.0REASON/S FOR RECOMMENDATION/S
1.1Regular monitoring and reporting of the Capital Programme enables decisions to be taken faster, which may produce revenue benefits and will improve financial control in Wirral Council.
2.0OTHER OPTIONS CONSIDERED
2.1Other reporting frequencies could be considered, but quarterly reporting is a standard practice.
3.0BACKGROUND INFORMATION
Monitoring 2022/23
3.1The Capital Programme 2022/23 was considered by Policy and Resources Committee on 15 February 2022 and approved by Council on 28 February 2022. The Programme contributes towards projects that support all five Wirral Plan 2021-26 priorities. Government grant announcements and scheme affordability. It was highlighted that the Council’s revenue budget position limited the scope for unsupported capital expenditure.
3.2Policy and Resources Committee received regular updates in respect of capital monitoring throughout the year. The last monitoring report, for Quarter 3, was considered by Policy and Resources Committee on 27 February 2023. Since then, work has been on-going in order to conclude the accounts for the financial year.
3.3During the year the Programme was regularly reviewed which resulted in schemes being deferred to 2023/24 along with the supporting funding. This resulted in reduced Treasury Management costs through a reduced need to borrow in 2022/23.
Capital Outturn
3.4The capital expenditure for the year was £60.9m compared to the Revised Programme of £86.3m which was reported in February 2023 (Quarter 3). This is summarised in Table 1.
3.5The outturn also includes the Formula Capital schemes delegated to schools.
3.6As a result of the £17.437m borrowed to finance the capital programme in 2022/23, the General Fund will be charged with its first repayment via the Minimum Revenue Provision (MRP) in 2023/24 of £0.609m. This will bring the total MRP charge for 2023/24 to £6.423m for borrowing associated with delivering the Capital Programme.
3.7Capital Programme 2022/23 Position by Directorate
Table 1: Capital Outturn 2022/23 – Position by Directorate Q3 Forecast Actual Variance Variance Programme £m £m £m % Adult Care & Health 1.248 0.649 -0.599 -48% Children, Families & Education 7.402 7.021 -0.381 -5% Corporate Schemes 3.780 2.930 -0.850 -22% Neighbourhoods 27.685 23.842 -3.843 -14% Regeneration & Place 40.643 22.762 -17.881 -44% Resources 5.544 3.733 -1.811 -33% Total 86.302 60.937 -25.365 -29%
Capital Programme 2022/23 Position by Committee
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Outturn Report 2022-23Report | 581 KB | DownloadRead as text |
PDF |
Minute Extract: Capital Outturn 2022-23Report | 95 KB | Download |
Follow Council at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Jul 2026 | MINUTESResolved – That the minutes of the meetings held on 13 May 2026 and 20 May 2026 be approved as a correct record. | Approved | Open |
| 20 Jul 2026 | 2025-26 Capital OutturnResolved – That 1. the virements of budget referred to in Appendix F of the report be approved; and 2. the bids in Ap... | Approved | Open |
| 20 Jul 2026 | Revisions to the ConstitutionResolved – That the amendments to the Constitution, as detailed in sections 3.2 to 3.7 of the report, be approved. | Approved | Open |
| 20 Jul 2026 | Appointment of Independent PersonsResolved – That the appointment of the following Independent Persons of the Constitution and Standards Committee be a... | Approved | Open |
| 20 Jul 2026 | Annual Report of the Audit and Risk Management CommitteeResolved – That the ARMC Annual Report for 2025-26 be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.