West Kirby Flood Alleviation Scheme - Construction Contract Procurement and Project Costs

Decided Finance 5 papers

Audit and Risk Management Committee decided this item on Tuesday 24 October 2023. Below is the council's own wording, with the papers it was decided on.

Item23

Resolved

Resolved – That: After considering the report to the Environment, Climate Emergency and Transport Committee on 14 March 2023 concerning the West Kirby Flood Alleviation Scheme; and The Background to the procurement of the contract and the reasons for the increases in costs of the project presented to the Committee, On the available evidence Committee is satisfied that the contracts for West Kirby flood defence works were procured in accordance with the law and administered in accordance with the requirements of those contracts.
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Audit and Risk Management Committee

Recommendations

The Audit and Risk Management Committee is recommended to:

1. Consider the report to Environment, Climate Emergency and Transport Committee on 14 March 2023 concerning the West Kirby Flood Alleviation Scheme;

2. Consider the background to the procurement of the contract and all increases in costs of the project, and

3. Resolve that on the available evidence the Committee is satisfied that the contracts for West Kirby flood defence works were procured in accordance with the law and administered in accordance with the requirements of those contracts. SUPPORTING INFORMATION

Reason for recommendations

1.1Following a report to the Environment Climate Emergency and Transport Committee on 14 March 2023 a substantive motion was resolved resulting in an amendment to the recommendations of the report to include the following additions:

 officers be thanked for the considerable amount of work put into the project, and

 the report be referred to the Audit & Risk Management Committee so that consideration can be given to reviewing concerns relating to the procurement of the construction contract and the increase in cost of the project.

1.2Further project costs have been incurred and additional budget has been secured in the form of Grant in Aid from the Environment Agency (EA) since the report to the Environment Climate Emergency and Transport Committee on 14 March 2023. The construction contract final account has now been settled and the all the project costs are fully defined.

2.0OTHER OPTIONS CONSIDERED

2.1To do nothing is not an option. This report is a referral from the Environment Climate Emergency and Transport Committee. Other procurement options are discussed in section 3.0 to this report.

3.0BACKGROUND INFORMATION

3.1Procurement Route: The delivery of the West Kirby Flood Alleviation Scheme has utilised two different procurement frameworks. Four different contracts have been procured through these frameworks since the scheme received financial and technical approval from the EA in January 2018:

3.1.1 Merseytravel Multi-Party Consultancy Framework (1). The framework was established by Merseytravel in 2015 following competitive tendering under the Office of the Journal of the European Union (OJEU) Regulations and Public Contracts Regulations (PCR) (2015), to provide technical and professional multi-disciplinary consultancy services to local authorities in the Merseytravel area. Wirral Council has access under agreement to this framework and such services, to support Council officer resource for the West Kirby Flood Alleviation scheme, were procured using a mini-competition approach across suppliers in Lot 4, Civil & Structural, of the framework. AECOM provided the most economically advantageous bid and were awarded the contract with Wirral Council in July 2018. The contract value, based on the initial scope of works, with construction costs estimated at £2.280m, was £147,305.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
OJEU Contract NoticeAppendix A 156 KB Download
PDF
West Kirby Flood Alleviation EfficienciesAppendix B 111 KB Download
PDF
West Kirby Flood Alleviation Scheme: Master Compensation Event RegisterAppendix C 528 KB Download
PDF
VolkerStevin Social Value ReportAppendix D 1.4 MB Download
PDF
West Kirby Flood Alleviation Scheme: Construction Contract Procurement and Project CostsReport 428 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 9 attended
JJ
Councillor Jennifer JohnsonChair, present
GD
Councillor George DaviesVice-Chair, present
PB
Councillor Paula BasnettCommittee Member, present
MS
Councillor Mark SkillicornCommittee Member, present
IL
Councillor Ian LewisCommittee Member, present
SK
Councillor Stuart KellySpokesperson, present
NG
Councillor Naomi GrahamSpokesperson, apologies, sent representative
JB
Joanne ByrneIndependent Persons, apologies
JG
Councillor Judith GrierDeputy, present as substitute

On this subject at Wirral

Search all
  1. West Kirby Flood Alleviation Scheme - Construction Contract Procurement and Project CostsThis decision
  2. APP/26/00261 - The Links, 100 - 102 Meols Drive, West Kirby, Wirral, CH48 5DBApproved
  3. West kirby marine lake managementApproved
  4. APP-24-00816 - WEST KIRBY GRAMMAR SCHOOL FOR GIRLS, GRAHAM ROAD, WEST KIRBY, WIRRAL, CH48 5DP - Proposed (isolated) demolition to enable the erection of a Sports Hall, 6th Form Centre with dining facilities and associated re-modelling works to facade, means of access, parking and landscapingApproved
  5. APP/23/00551: The Grange, Grange Road, West Kirby, Wirral, CH48 4EE Demolition of house and out buildings to provide 12 apartments together with associated parking, access and landscaping and works including the relocation of the substation. (Amended Description)Approved
  6. APP/23/00551; The Grange, Grange Road, West Kirby, Wirral, CH48 4EE, Demolition of house and outbuildings to provide 12 apartments together with associated parking, access and landscaping and works including the relocation of the substation.Deferred

More from Wirral Audit and Risk Management Committee

All decisions
MeetingDecisionOutcome
24 Jun 2026 External Audit Plan for Wirral Council 2025-26Resolved – That the external audit plan for Wirral Council’s Statutory financial statements for 2025/26 as prepared b... Noted Open
24 Jun 2026 External Audit Plan for Merseyside Pension Fund 2025-26Resolved – That the external audit plan for the Merseyside Pension Fund’s Statutory financial statements for 2025/26 ... Noted Open
24 Jun 2026 Annual governance statement 2025/26Resolved – That the draft Annual Governance Statement for 2025/26, including the actions planned in 2026/27 to addres... Approved Open
24 Jun 2026 Birkenhead town centre management action plan updateResolved – That 1. The progress made to date in implementing the Birkenhead Town Centre Management Action Plan recomm... Noted Open
24 Jun 2026 Annual cctv surveillance activity reportResolved – That the report be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies